Question

Problem 2 Mobil Company has hired a consultant to propose a way to increase the companys revenues. The consultant has evalua

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The Net Present Value (NPV) of Project Turtle

Year

Annual cash flows ($)

Present Value Factor (PVF) at 9.00%

Present Value of annual cash flows ($)

[Annual cash flow x PVF]

1

1,80,000

0.9174312

1,65,137.61

2

1,80,000

0.8416800

1,51,502.40

3

1,80,000

0.7721835

1,38,993.03

4

1,80,000

0.7084252

1,27,516.54

5

1,80,000

0.6499314

1,16,987.65

6

1,80,000

0.5962673

1,07,328.12

7

1,80,000

0.5470342

98,466.16

8

1,80,000

0.5018663

90,335.93

9

1,80,000

0.4604278

82,877.00

10

1,80,000

0.4224108

76,033.95

TOTAL

11,55,178.39

Net Present Value (NPV) = Present Value of annual cash inflows – Initial Investment

= $11,55,178.39 - $11,05,000

= $50,178.39

The Net Present Value (NPV) of Project Snake

Year

Annual cash flows ($)

Present Value Factor (PVF) at 9.00%

Present Value of annual cash flows ($)

[Annual cash flow x PVF]

1

1,05,000

0.9174312

96,330.28

2

1,05,000

0.8416800

88,376.40

3

1,05,000

0.7721835

81,079.27

4

1,05,000

0.7084252

74,384.65

5

1,05,000

0.6499314

68,242.80

6

1,05,000

0.5962673

62,608.07

7

1,05,000

0.5470342

57,438.60

8

1,05,000

0.5018663

52,695.96

9

1,05,000

0.4604278

48,344.92

10

1,05,000

0.4224108

44,353.13

TOTAL

6,73,854.06

Net Present Value (NPV) = Present Value of annual cash inflows – Initial Investment

= $6,73,854.06 - $625,000

= $ 48,854.06

Profitability Index (PI) for Project Turtle

Profitability Index (PI) = Present Value of annual cash inflows / Initial Investment

= $11,55,178.39 / $11,05,000

= 1.05

Profitability Index (PI) for Project Snake

Profitability Index (PI) = Present Value of annual cash inflows / Initial Investment

= $673,854.06 / $625,000

= 1.08

DECISION

-As per the Net Present Value method, the Project Turtle should be accepted, since it has the highest NPV of $50,178.39.

-As per the PI method, the Project Snake should be accepted, since it has the higher Profitability Index of 1.08.

NOTE

The formula for calculating the Present Value Inflow Factor (PVIF) is [1 / (1 + r)n], where “r” is the Discount Rate/Cost of capital and “n” is the number of years.

Add a comment
Know the answer?
Add Answer to:
Problem 2 Mobil Company has hired a consultant to propose a way to increase the company's...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Q3. Mobile company hired a consultant to propose a way to increase company revenues. The consultant...

    Q3. Mobile company hired a consultant to propose a way to increase company revenues. The consultant has evaluated two mutually exclusive project with the following information provided for each project. Project X Project Y Capital investment Annual cash flow Estimated useful life 1,105,000 180,000 10 years 625,000 105,000 10 years Mobile uses discount rate of 9% to evaluate both project Instructions: a. Calculate NPV of both projects b. Calculate profitably index for each project C. Which project should be accepted

  • Q3. Mobile company hired a consultant to propose a way to increase company revenues. The consultant...

    Q3. Mobile company hired a consultant to propose a way to increase company revenues. The consultant has evaluated two mutually exclusive project with the following information provided for each project. Project X Project Y Capital investment Annual cash flow Estimated useful life 1,105,000 180,000 10 years 625,000 105,000 10 years Mobile uses discount rate of 9% to evaluate both project Instructions: a. Calculate NPV of both projects b. Calculate profitably index for each project C. Which project should be accepted

  • Q3. Mobile company hired a consultant to propose a way to increase company revenues. The consultant...

    Q3. Mobile company hired a consultant to propose a way to increase company revenues. The consultant has evaluated two mutually exclusive project with the following information provided for each project. Project X Project Y Capital investment Annual cash flow Estimated useful life 1,105,000 180,000 10 years 625,000 105,000 10 years Mobile uses discount rate of 9% to evaluate both project Instructions: a. Calculate NPV of both projects b. Calculate profitably index for each project C. Which project should be accepted

  • JC Warehouse Corporation has estimated the cash flows of Projects A, B, and C as follows.

    JC Warehouse Corporation has estimated the cash flows of Projects A, B, and C as follows.  YearProject AlphaProject BetaProject Delta0-$100,000-$200,000-$100,000170,000130,00075,000270,000130,00060,000 Suppose the company requires a 12 percent return on investment.1.1 Calculate the payback period for each of the three projects.1.2 Calculate the NPV for each of the three projects.1.3 Calculate the profitability index for each of the three projects.1.4 Suppose these three projects are independent and the company has an unlimited amount of funds. If the company makes decision based...

  • Problem 7-14 Problems with Profitability Index The Bosa Corporation is trying to choose between the following...

    Problem 7-14 Problems with Profitability Index The Bosa Corporation is trying to choose between the following two mutually exclusive design projects: Year Cash Flow (1) -$ 66,000 29,000 29,000 29,000 Cash Flow (II) -$17,800 9,600 9,600 9,600 a-1 If the required return for both projects is 10 percent, what is the profitability Index for both projects? (Do not round Intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.) Profitability Index Project I Project II a-2 If the...

  • VDSL Company has two mutually exclusive projects. Below is a table representing the initial investment and...

    VDSL Company has two mutually exclusive projects. Below is a table representing the initial investment and cash flows for these projects over four (4) years. Project A Project B Year Cash Flow Cash Flow $ $ 0 -750,000 -750,000 1 250,000 200,000 2 350,000 400,000 3 250,000 100,000 4 200,000 175,000 a. If the company’s required rate of return is 8%, calculate the Profitability Index of each project and determine which project is the best investment. b.   If the company...

  • Quattro, Inc. has the following mutually exclusive projects available. The company has historically used a four-year cut...

    Quattro, Inc. has the following mutually exclusive projects available. The company has historically used a four-year cutoff for projects. The required return is 11 percent. The payback for Project A is ____ while the payback for Project B is ____. The NPV for Project A is _____ while the NPV for Project B is ____. Which project, if any, should the company accept? 3.92 years; 3.64 years; $780.85; $1,211.48; accept both Projects 3.92 years; 3.79 years; -$17,108.60; $1,211.48; accept Project...

  • please show the step by step calculations required for solving this problem! :) Year The Sloan Corporation is trying...

    please show the step by step calculations required for solving this problem! :) Year The Sloan Corporation is trying to choose between the following two mutually exclusive design projects: Cash Flow Cash Flow (LU) -$74,000 - $17.000 34.000 9,200 34,000 9,200 34,000 9,200 WNO 2-1 If the required return is 12 percent, what is the profitability index for both projects? (Do not round intermediate calculations. Round your answers to 3 decimal places e.g., 32.161.) Project Project II a-2 if the...

  • Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a...

    Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a three year cutoff for projects. The required return is 10 percent. Year U AWN- Project F -$ 195,000 98,400 86,300 81,600 72,000 64,800 Project G $298,000 71,600 94,500 123,600 166,800 187,200 a. Calculate the payback period for both projects. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) b. Calculate the NPV for both projects. (Do not round...

  • Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a...

    Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a three-year cutoff for projects. The required return is 10 percent. Year Project F Project G o-NM $140,000 57,500 52,500 62,500 57,500 52,500 $210,000 37,500 52,500 92,500 122,500 137,500 a. Calculate the payback period for both projects. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) b. Calculate the NPV for both projects. (Do not round intermediate calculations and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT