Question

The following is a system of simultaneous linear equations to allocate costs using the reciprocal method. Matrix algebra is n
oTT ry UCcupancy R&D 0.50 0.50 Supervision 0.30 0.30 0.20 0.10 0.10 The equation for department S1 (building occupancy) is: M
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Department S1 (Building Occupancy)
Its own cost = $89000
Department S3 's cost alloted to it = 0.10*S3
therefore department S1 cost would be
S1 =$89000+0.10 S3
Correct Option: THIRD
Add a comment
Know the answer?
Add Answer to:
The following is a system of simultaneous linear equations to allocate costs using the reciprocal method....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following is a system of simultaneous linear equations to allocate costs using the reciprocal method....

    The following is a system of simultaneous linear equations to allocate costs using the reciprocal method. Matrix algebra is not required. The following costs were incurred in three operating departments and three service departments in Westmoreland Company. Department Direct Costs Label Subassemblies $ 561,000 P1 Final assembly 786,000 P2 Marketing 296,000 P3 Building occupancy 96,000 S1 Research & development 131,000 S2 Supervision 56,000 S3 Use of services by other departments is as follows.    User Departments Service Cost Center Sub-assemblies...

  • The following is a system of simultaneous linear equations to allocate costs using the reciprocal method....

    The following is a system of simultaneous linear equations to allocate costs using the reciprocal method. Matrix algebra is not required. The following costs were incurred in three operating departments and three service departments in Westmoreland Company. Label P2 Department Subassemblies Final assembly Marketing Building occupancy Research & development Supervision Direct Costs $552,000 777,000 287,000 87,000 122,000 47,000 Use of services by other departments is as follows. Sub- Service Cost Center assemblies Building occupancy 0.30 R&D 0.50 Supervision 0.20 Final...

  • Cordner Corporation has two production departments, P1 and P2, and two service departments, S1 and 52....

    Cordner Corporation has two production departments, P1 and P2, and two service departments, S1 and 52. Direct costs for each department and the proportion of service costs used by the various departments for the month of July are as follows: Proportion of Services Used by: S1 S2 P1 P2 0.70 0.10 0.20 0.20 0.30 0.50 Department Direct costs $ 60, 000 S2 $100,000 $160,000 P2 $140,000 S1 P1 Under the step method of allocation, the total amount of service costs...

  • Cordner Corporation has two production departments, P1 and P2, and two service departments, S1 and S2....

    Cordner Corporation has two production departments, P1 and P2, and two service departments, S1 and S2. Direct costs for each department and the proportion of service costs used by the various departments for the month of July are as follows: Proportion of Services Used by: S1 S2 P1 0.70 0.10 0.20 0.20 0.30 0.50 Department Direct costs $ 60,000 $100,000 $160,000 $140,000 P2 Under the direct method of cost allocation, the amount of S1 costs allocated to S2 would be:...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT