Question

Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,150,000 in 2018...

Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,150,000 in 2018 for the mining site and spent an additional $630,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.):

Cash Outflow Probability
1 $ 330,000 25%
2 430,000 40%
3 630,000 35%


To aid extraction, Jackpot purchased some new equipment on July 1, 2018, for $230,000. After the copper is removed from this mine, the equipment will be sold for an estimated residual amount of $24,000. There will be no residual value for the copper mine. The credit-adjusted risk-free rate of interest is 10%.

The company expects to extract 10.3 million pounds of copper from the mine. Actual production was 1.9 million pounds in 2018 and 3.3 million pounds in 2019.

Required:
1. Compute depletion and depreciation on the mine and mining equipment for 2018 and 2019. The units-of-production method is used to calculate depreciation.

Restoration costs: Cash outflow Probability Probable Restoration Cost
Possibility 1 $330,000 25%
Possibility 2 430,000 40%
Possibility 3 630,000 35%
$0
Table or Calculator function:
n = 4
i =
Present value of probable restoration costs
Cost of copper mine:
Mining site
Development cost
Restoration cost
Depletion expense (mine): 2018 2019
Depletion per pound (#.####) $0.0000
Pounds extracted
Depletion expense
Depreciation expense (mining equipment) 2018 2019
Depreciation per pound (#.##) $0.00
Pounds extracted
Depreciation expense
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Restoration costs

Cash outflow

Probability

Probable Restoration Cost

Possibility 1

330000

25%

82500

Possibility 2

430000

40%

172000

Possibility 3

630000

35%

220500

$475000

Table or Calculator function:

n = 4

i = 10%

Restoration costs (475000*0.68301)

$324430

PV factor of $1 n = 4, i=10% is 0.68301

Mining site

1150000

Development costs

630000

Restoration costs

324430

$2104430

Depletion expense (mine)

2018

2019

Depletion per pound

2104430/10300000

=$0.2043 per pound

Pounds extracted

1900000

3300000

Depletion expense

$388170

$674190

Depreciation expense (mining equipment)       

2018

2019

Depreciation per pound

(230000-24000)/10300000

=$0.02 per pound

Pounds extracted

1900000

3300000

Depletion expense

$38000

$66000

Add a comment
Know the answer?
Add Answer to:
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,150,000 in 2018...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,000,000 in 2018...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,000,000 in 2018 for the mining site and spent an additional $600,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs (FV of $1....

  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,650,000 in 2021...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,650,000 in 2021 for the mining site and spent an additional $730,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...

  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,150,000 in 2018...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,150,000 in 2018 for the mining site and spent an additional $630,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately 4 years the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...

  • I will give thumbs up for correct answers! Thank you! Jackpot Mining Company operates a copper...

    I will give thumbs up for correct answers! Thank you! Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,800,000 in 2021 for the mining site and spent an additional $760,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three...

  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,350,000 in 2021...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,350,000 in 2021 for the mining site and spent an additional $670,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...

  • explain each year 2018 and 2019 Help Save & El Submit Check my work mode: This...

    explain each year 2018 and 2019 Help Save & El Submit Check my work mode: This shows what is correct or Incorrect for the work you have completed so far. It does not indicate completion Return to question Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,000,000 in 2018 for the mining site and spent an additional $600,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four...

  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,750,000 in 2021...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,750,000 in 2021 for the mining site and spent an additional $750,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...

  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,750,000 in 2021...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,750,000 in 2021 for the mining site and spent an additional $750,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...

  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,400,000 in 2021...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,400,000 in 2021 for the mining site and spent an additional $680,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...

  • Check my work Jackpot Mining Company operates a copper mine in central Montana. The company paid...

    Check my work Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,750,000 in 2021 for the mining site and spent an additional $750,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs:...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT