Jackpot Mining Company operates a copper mine in central
Montana. The company paid $1,150,000 in 2018 for the mining site
and spent an additional $630,000 to prepare the mine for extraction
of the copper. After the copper is extracted in approximately four
years, the company is required to restore the land to its original
condition, including repaving of roads and replacing a greenbelt.
The company has provided the following three cash flow
possibilities for the restoration costs (FV of $1, PV of $1, FVA of
$1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate
factor(s) from the tables provided.):
Cash Outflow | Probability | |||
1 | $ | 330,000 | 25% | |
2 | 430,000 | 40% | ||
3 | 630,000 | 35% | ||
To aid extraction, Jackpot purchased some new equipment on July 1,
2018, for $230,000. After the copper is removed
from this mine, the equipment will be sold for an estimated
residual amount of $24,000. There will be no residual value for the
copper mine. The credit-adjusted risk-free rate of interest is
10%.
The company expects to extract 10.3 million pounds of copper from
the mine. Actual production was 1.9 million pounds in 2018 and 3.3
million pounds in 2019.
Required:
1. Compute depletion and depreciation on the mine
and mining equipment for 2018 and 2019. The units-of-production
method is used to calculate depreciation.
|
Restoration costs |
Cash outflow |
Probability |
Probable Restoration Cost |
|||||||||
Possibility 1 |
330000 |
25% |
82500 |
|||||||||
Possibility 2 |
430000 |
40% |
172000 |
|||||||||
Possibility 3 |
630000 |
35% |
220500 |
|||||||||
$475000 |
||||||||||||
|
||||||||||||
n = 4 i = 10% |
||||||||||||
Restoration costs (475000*0.68301) |
$324430 |
PV factor of $1 n = 4, i=10% is 0.68301
Mining site |
1150000 |
Development costs |
630000 |
Restoration costs |
324430 |
$2104430 |
Depletion expense (mine) |
2018 |
2019 |
Depletion per pound |
2104430/10300000 |
=$0.2043 per pound |
Pounds extracted |
1900000 |
3300000 |
Depletion expense |
$388170 |
$674190 |
Depreciation expense (mining equipment) |
2018 |
2019 |
Depreciation per pound |
(230000-24000)/10300000 |
=$0.02 per pound |
Pounds extracted |
1900000 |
3300000 |
Depletion expense |
$38000 |
$66000 |
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,150,000 in 2018...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,000,000 in 2018 for the mining site and spent an additional $600,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs (FV of $1....
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,650,000 in 2021 for the mining site and spent an additional $730,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,150,000 in 2018 for the mining site and spent an additional $630,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately 4 years the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...
I will give thumbs up for correct answers! Thank you! Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,800,000 in 2021 for the mining site and spent an additional $760,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,350,000 in 2021 for the mining site and spent an additional $670,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...
explain each year 2018 and 2019 Help Save & El Submit Check my work mode: This shows what is correct or Incorrect for the work you have completed so far. It does not indicate completion Return to question Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,000,000 in 2018 for the mining site and spent an additional $600,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,750,000 in 2021 for the mining site and spent an additional $750,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,750,000 in 2021 for the mining site and spent an additional $750,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,400,000 in 2021 for the mining site and spent an additional $680,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...
Check my work Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,750,000 in 2021 for the mining site and spent an additional $750,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs:...