Question

Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,650,000 in 2021 for the mining site and spent an additional $730,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.)

Cash Outflow Probability
1 $ 430,000 15%
2 530,000 45%
3 730,000 40%


To aid extraction, Jackpot purchased some new equipment on July 1, 2021, for $260,000. After the copper is removed from this mine, the equipment will be sold for an estimated residual amount of $34,000. There will be no residual value for the copper mine. The credit-adjusted risk-free rate of interest is 10%.

The company expects to extract 11.3 million pounds of copper from the mine. Actual production was 2.9 million pounds in 2021 and 4.3 million pounds in 2022.

Required:
1. Compute depletion and depreciation on the mine and mining equipment for 2021 and 2022. The units-of-production method is used to calculate depreciation. (The expected format for rounding is presented in the appropriate rows of the table. Round your final answers to nearest whole dollar.)Restoration costs: Cash outflow Probability 15% Possibility 1 Possibility 2 Possibility 3 430,000 530,000 730,000 45% Probabl

0 1
Add a comment Improve this question Transcribed image text
Answer #1

Computation of Depletion and Depreciation On mine & equipment for 2021 & 2022 Restoration costs Cash outflow Probability Prob

Add a comment
Answer #2

Computation of Depletion and Depreciation On mine & equipment for 2021 & 2022 Restoration costs Cash outflow Probability Prob

Add a comment
Know the answer?
Add Answer to:
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,650,000 in 2021...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,150,000 in 2018...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,150,000 in 2018 for the mining site and spent an additional $630,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs (FV of $1,...

  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,000,000 in 2018...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,000,000 in 2018 for the mining site and spent an additional $600,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs (FV of $1....

  • I will give thumbs up for correct answers! Thank you! Jackpot Mining Company operates a copper...

    I will give thumbs up for correct answers! Thank you! Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,800,000 in 2021 for the mining site and spent an additional $760,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three...

  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,350,000 in 2021...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,350,000 in 2021 for the mining site and spent an additional $670,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...

  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,750,000 in 2021...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,750,000 in 2021 for the mining site and spent an additional $750,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...

  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,750,000 in 2021...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,750,000 in 2021 for the mining site and spent an additional $750,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...

  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,150,000 in 2018...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,150,000 in 2018 for the mining site and spent an additional $630,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately 4 years the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...

  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,400,000 in 2021...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,400,000 in 2021 for the mining site and spent an additional $680,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...

  • Check my work Jackpot Mining Company operates a copper mine in central Montana. The company paid...

    Check my work Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,750,000 in 2021 for the mining site and spent an additional $750,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs:...

  • explain each year 2018 and 2019 Help Save & El Submit Check my work mode: This...

    explain each year 2018 and 2019 Help Save & El Submit Check my work mode: This shows what is correct or Incorrect for the work you have completed so far. It does not indicate completion Return to question Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,000,000 in 2018 for the mining site and spent an additional $600,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT