Question

Various activities at Companhia de Textils, S.A., a manufacturing company located in Brazil, are listed below. The company maRequired information [The following information applies to the questions displayed below.) Adria Company recently implemented

1 0
Add a comment Improve this question Transcribed image text
Answer #1

a). Preventive maintenance is performed on general purpose production equipment- Facility level activity because these activities are performed for general operation they are not inclined towards special or individual product and other specific things.so preventive maintenance is a general purpose function therefore it will come under this heading.

b). Products are assembled by hand-​​ product level activity because these activities are performed to maintain to assist is product formation

c).A security patrols the company ground after normal working hours- Facility level activity because patrols means act of walking around an area so that it can be ensured it is face as it is a general operation not related to any product.

d).purchased orders are issued for material to be used in production- Batch level activity because order is given for each and every batch of production then only purchase orders are issued.

e).Modification are made to Product design- Product level activity because includes actions undertaken to assist the product varieties or to improve the products so modification is also a slight improvement that why it will come under this.

f) New employees are hired by personal office- Facility level activity as this activity is related to general operations of the company.

g). Matching settings are changed between batches of different product- Batch level activity as resetting of particular batch will come under this head of activity.

h).Parts inventories are maintained in the store room- Facility level activity as it is related to the maintenance aspect which is general purpose.

i). Insurance cost are incurred on company facilities- facility level activity as this includes general operations not related to specific product so insurance cost incurred will be computed under this activity.

Activity Rate for each cost pool calculation

1. Labour related = Expected over head cost Expected activity Sap). = $22,000 8 00 Чрн) Чрек DLH Видиюля.

cost Activity reate = Expected over head Expected activity $3,000 order 3,000 $ 1 per order > Puechase 10 Loco - Material - 8

at reate Activity - Expected overhead lost Expected Activity As per Question General faclory = $ 200,000 o 40,000 J$5 Per MHS

Add a comment
Know the answer?
Add Answer to:
Various activities at Companhia de Textils, S.A., a manufacturing company located in Brazil, are listed below....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information [The following information applies to the questions displayed below.] Adria Company recently implemented an...

    Required information [The following information applies to the questions displayed below.] Adria Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company's five activity cost pools: Activity Cost Pool Labor-related Purchase orders Material receipts Relay assembly General factory Activity Measure Direct labor-hours Number of orders Number of receipts Number of relays Machine-hours Expected Overhead Cost $ 42,500 $ 5,600 $ 10,000 $ 14,400 $245,000 Expected...

  • Adria Company recently Implemented an activity-based costing system. At the beginning of the year, management made...

    Adria Company recently Implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company's five activity cost pools: Activity Cost Pool Labor-related Purchase orders Material receipts Relay assembly General factory Activity -Measure Direct labor-hours Number of orders Number of receipts Number of relays Machine-hours Expected Overhead Cost $ 48,000 $ 6.900 $ 11.400 $ 11,700 $ 328,000 Expected Activity 8,000 DLHS 2,300 orders 950 receipts 1,300 relays 41,000...

  • Required information [The following information applies to the questions displayed below.] Adria Company recently implemented an...

    Required information [The following information applies to the questions displayed below.] Adria Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company's five activity cost pools: Activity Cost Pool Labor-related Purchase orders Material receipts Relay assembly General factory Activity Measure Direct labor-hours Number of orders Number of receipts Number of relays Machine-hours Expected Overhead Cost $ 32,000 $ 3,000 $ 9,000 $ 12,000 $ 200,000...

  • Required information [The following information applies to the questions displayed below.) Adria Company recently implemented an...

    Required information [The following information applies to the questions displayed below.) Adria Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company's five activity cost pools: Activity Cost Pool Labor-related Purchase orders Material receipts Relay assembly General factory Activity Measure Direct labor-hours Number of ordere Number of receipts Number of relays Machine-hours Expected Overhead Coat $ 60,000 $ 16,800 $ 15,000 $ 35,200 $400,000 Expected...

  • Required information [The following information applies to the questions displayed below.) Adria Company recently implemented an...

    Required information [The following information applies to the questions displayed below.) Adria Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company's five activity cost pools: Activity Cost Pool Labor-related Purchase orders Material receipts Relay assembly General factory Activity Measure Direct labor-hours Number of orders Number of receipts Number of relays Machine-hours Expected Overhead Cost $ 60.000 $ 16,800 $ 15,000 $ 35,200 $400,000 Expected...

  • Adria Company recently implemented an activity-based costing system. At the beginning of the year, management made...

    Adria Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company’s five activity cost pools: Activity Cost Pool Activity Measure Expected Overhead Cost Expected Activity Labor-related Direct labor-hours $ 30,000 7,500 DLHs Purchase orders Number of orders $ 10,200 3,400 orders Material receipts Number of receipts $ 8,800 800 receipts Relay assembly Number of relays $ 12,000 2,400 relays General factory Machine-hours $ 172,000 43,000...

  • Adria Company recently implemented an activity-based costing system. At the beginning of the year, management made...

    Adria Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company's five activity cost pools: Activity Cost Pool Labor-related Purchase orders Material receipts Relay assembly General factory Activity Measure Direct labor-hours Number of orders Number of receipts Number of relays Machine-hours Expected Overhead Cost $ 35,000 $ 4,000 $ 10,450 $ 7,000 $240,000 Expected Activity 7.000 DLHS 2,000 orders 950 receipts 1.000 relays 40,000 Mits...

  • Adria company recently implemented in activity-based costing system at the beginning of the year management made...

    Adria company recently implemented in activity-based costing system at the beginning of the year management made the following estimate of cost and activity in the companies five activity cost pause part to the expected activity for the year was distributed among the companies for products as follows using the ABC data determine the total amount of overhead costs assign to each product please give me the answers for product A,B,C and D. thank you Adna Company recently implemented an activity...

  • Sultan Company uses an activity-based costing system.         At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system.         At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for Its five activity cost pools: Activity Measure Expected Overhead Expected Activity DLHS Activity Cost Pool Cost 135,600 24 Labor-related Direct labor-hours 22,600 $ 8,400 $ 68,870 240...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Labor-related Purchase orders Parts management Board etching General factory Activity Measure Direct labor-hours Number of orders Number of part types Number of boards Machine-hours Expected Overhead Cost $ 284.000 $ 6,790 $ 71,340 $ 57,900 $ 229,900 Expected Activity 35,500 DLHS 194 orders 82 part types 1.930 boards...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT