Calculation of activity rate for each cost pool | |||||
Activity cost pool | Expected overhead cost | Expected activity | Activity rate | ||
Labor related | $35,000 | 7000 | $5 | per DLHs | |
Purchase orders | $4,000 | 2000 | $2 | per order | |
Material receipts | $10,450 | 950 | $11 | per receipts | |
Relay assembly | $7,000 | 1000 | $7 | per relays | |
General factory | $240,000 | 40000 | $6 | per MHs | |
Calculation of overhead cost assigned to each product | |||||
Product A | Product B | Product C | Product D | ||
Labor related | $12,000 | $2,500 | $17,500 | $3,000 | |
2400*5 | 500*5 | 3500*5 | 600*5 | ||
Purchase orders | $200 | $700 | $1,600 | $1,500 | |
100*2 | 350*2 | 800*2 | 750*2 | ||
Material receipts | $4,400 | $2,288 | $3,762 | $0 | |
400*11 | 208*11 | 342*11 | 0*11 | ||
Relay assembly | $1,190 | $1,190 | $2,100 | $2,520 | |
170*7 | 170*7 | 300*7 | 360*7 | ||
General factory | $72,000 | $42,000 | $48,000 | $78,000 | |
12000*6 | 7000*6 | 8000*6 | 13000*6 | ||
Total overhead costs | $89,790 | $48,678 | $72,962 | $85,020 | |
Adria Company recently implemented an activity-based costing system. At the beginning of the year, management made...
Adria Company recently Implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company's five activity cost pools: Activity Cost Pool Labor-related Purchase orders Material receipts Relay assembly General factory Activity -Measure Direct labor-hours Number of orders Number of receipts Number of relays Machine-hours Expected Overhead Cost $ 48,000 $ 6.900 $ 11.400 $ 11,700 $ 328,000 Expected Activity 8,000 DLHS 2,300 orders 950 receipts 1,300 relays 41,000...
Adria Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company’s five activity cost pools: Activity Cost Pool Activity Measure Expected Overhead Cost Expected Activity Labor-related Direct labor-hours $ 30,000 7,500 DLHs Purchase orders Number of orders $ 10,200 3,400 orders Material receipts Number of receipts $ 8,800 800 receipts Relay assembly Number of relays $ 12,000 2,400 relays General factory Machine-hours $ 172,000 43,000...
Adria company recently implemented in activity-based costing system
at the beginning of the year management made the following estimate
of cost and activity in the companies five activity cost pause part
to the expected activity for the year was distributed among the
companies for products as follows using the ABC data determine the
total amount of overhead costs assign to each product please give
me the answers for product A,B,C and D. thank you
Adna Company recently implemented an activity...
Required information [The following information applies to the questions displayed below.] Adria Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company's five activity cost pools: Activity Cost Pool Labor-related Purchase orders Material receipts Relay assembly General factory Activity Measure Direct labor-hours Number of orders Number of receipts Number of relays Machine-hours Expected Overhead Cost $ 42,500 $ 5,600 $ 10,000 $ 14,400 $245,000 Expected...
Required information [The following information applies to the questions displayed below.] Adria Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company's five activity cost pools: Activity Cost Pool Labor-related Purchase orders Material receipts Relay assembly General factory Activity Measure Direct labor-hours Number of orders Number of receipts Number of relays Machine-hours Expected Overhead Cost $ 32,000 $ 3,000 $ 9,000 $ 12,000 $ 200,000...
Rusties Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company's five activity cost pools: Activity Cost Pool Labor-related Purchase orders Product testing Template etching General factory Activity Measure Direct labor-hours Number of orders Number of tests Number of templates Machine-hours Expected Overhead Cost $ 43,308 $ 2,160 $ 5,700 $ 1,950 $ 68,600 Expected Activity 2,406 DLHS 540 orders 300 tests 65 templates 9,800...
Required information [The following information applies to the questions displayed below.) Adria Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company's five activity cost pools: Activity Cost Pool Labor-related Purchase orders Material receipts Relay assembly General factory Activity Measure Direct labor-hours Number of orders Number of receipts Number of relays Machine-hours Expected Overhead Cost $ 60.000 $ 16,800 $ 15,000 $ 35,200 $400,000 Expected...
Rustles Company recently implemented an activity-based costing system. At the beginning of the year. management made the following estimates of cost and activity in the company's five activity cost pools: Activity Cost Pool Labor-related Purchase orders Product testing Template etching General factory Activity Measure Direct labor-hours Number of orders Number of tests Number of templates Machine-hours Expected Overhead Cost $ 24,585 $ 3.270 $ 3,640 $ 1,050 $ 107,100 Expected Activity 2,235 DLHs 545 orders 280 tests 50 templates 11,900...
Required information [The following information applies to the questions displayed below.) Adria Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company's five activity cost pools: Activity Cost Pool Labor-related Purchase orders Material receipts Relay assembly General factory Activity Measure Direct labor-hours Number of ordere Number of receipts Number of relays Machine-hours Expected Overhead Coat $ 60,000 $ 16,800 $ 15,000 $ 35,200 $400,000 Expected...
Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Labor-related Purchase orders Parts management Board etching General factory Activity Measure Direct labor-hours Number of orders Number of part types Number of boards Machine-hours Expected Overhead Cost $ 284.000 $ 6,790 $ 71,340 $ 57,900 $ 229,900 Expected Activity 35,500 DLHS 194 orders 82 part types 1.930 boards...