Question

IRR Question 3: A project has the following cash flows: Investment today: -$500,000 Cash Flows Years 1-3: $200,000 Cash Flow
0 0
Add a comment Improve this question Transcribed image text
Answer #1

The initial cash flow is CF0 = ($5,00,000)

CF1= $2,00,000

CF2= $2,00,000

CF3= $2,00,000

CF4= $2,50,000

So, the IRR of the project is . IRR is the rate at which the NPV is zero,

($5,00,000) + 2,00,000/ (1 + x)^1 + 2,00,000/ (1 +x)^2 + 2,00,000/ (1 + x)^3 + 2,50,000/ (1 + x)^4 = 0,

solving for X we get,

IRR = 24.2151

So, the IRR is between 20% and 25%.

Add a comment
Know the answer?
Add Answer to:
IRR Question 3: A project has the following cash flows: Investment today: -$500,000 Cash Flows Years...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The IRR evaluation method assumes that cash flows from the project are reinvested at the same...

    The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes more reasonable assumption other than the project's IRR. Consider the following situation: Blue Llama Mining Company is analyzing a project that requires an initial investment of $3,000,000. The project's expected cash flows are: Year Cash Flow...

  • The IRR evaluation method assumes that cash flows from the project are reinvested at the same...

    The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Cute Camel Woodcraft Company is analyzing a project that requires an initial investment of $2,750,000. The project’s expected cash flows are: Year Cash...

  • The IRR evaluation method assumes that cash flows from the project are reinvested at the same...

    The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Green Caterpillar Garden Supplies Inc. is analyzing a project that requires an initial investment of $2,750,000. The project’s expected cash flows are: Year...

  • 4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...

    4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation: Grey Fox Aviation Company is analyzing a project that requires an initial investment of $2,500,000. The...

  • 4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...

    4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Grey Fox Aviation Company is analyzing a project that requires an initial investment of $2,500,000. The...

  • The IRR evaluation method assumes that cash flows from the project are reinvested at the same...

    The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR Consider the following situation: Fuzzy Button Clothing Company is analyzing a project that requires an initial investment of $3,225,000. The project's expected cash flows are: Cash Flow...

  • 4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...

    4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation: Blue Llama Mining Company is analyzing a project that requires an initial investment of $2,750,000. The...

  • The IRR evaluation method assumes that cash flows from the project are reinvested at the same...

    The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation: Celestial Crane Cosmetics is analyzing a project that requires an initial investment of $3,000,000. The project's expected cash flows are: Year Year 1...

  • 4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...

    4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation: Celestial Crane Cosmetics is analyzing a project that requires an initial investment of $2,500,000. The project's...

  • The IRR evaluation method assumes that cash flows from the project are reinvested at the same...

    The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation: Green Caterpillar Garden Supplies Inc. is analyzing a project that requires an initial investment of $500,000. The project's expected cash flows are: Year...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT