1.
Primare Corporation | ||
Schedule of cost of goods manufactured | ||
Direct Meterial | ||
Beginning raw meterial inventory | $ 10,100 | |
Add: Purchase of raw meterial | $ 31,000 | |
Raw meterials available for production | $ 41,100 | |
Less: Ending raw meterial inventory | $ 18,600 | |
Raw material used in production | $ 22,500 | |
Less: Indirect material included in manufacturing overhead | $ 4,920 | 17,580 |
Direct labour | $ 58,600 | |
Manufacturing overhead applied to work in process inventory | $ 88,100 | |
Total Manufactoring Cost | $ 164,280 | |
Add:Beginning work in progress inventory | $ 54,100 | |
Less: Ending work in progress inventory | $ 69,000 | |
Cost of goods manufactured | $ 149,380 |
2.
Primare Corporation | |
Schedule of cost of goods sold | |
Finished goods inventory, beginning | $ 34,700 |
Add: Cost of goods manufactured | $ 149,380 |
Goods available for sale | $ 184,080 |
Less: Finished goods inventory, ending | $ 43,700 |
Unadjusted cost of goods sold | $ 140,380 |
Add: Underapplied overhead | $ 4,030 |
Adjusted cost of goods sold | $ 144,410 |
You can reach me over comment box if you have any doubts. Please
rate this answer
Primare Corporstion has provided the following dats concerning last month's manufacturing operations. Purchases of raw materials...
Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials Indirect materials included in manufacturing overhead Direct labor Manufacturing overhead applied to work in process Underapplied overhead $30,000 $ 4,920 $58,300 $88,100 $ 4,200 Inventories Raw materials Work in process Finished goods Beginning $ 10,500 $ 55,400 $ 35,000 Ending $ 19,000 $ 68,200 $ 43,200 Required: 1. Prepare a schedule of cost of goods manufactured for the month. 2. Prepare a schedule of...
Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials Indirect materials included in manufacturing overhead Direct labor Manufacturing overhead applied to work in process Underapplied overhead $32,000 $ 4,850 $59,900 $88,700 $ 4,030 Inventories Raw materials Work in process Finished goods Beginning $ 11,900 $ 55,400 $ 34,600 Ending $ 19,400 $ 65,500 $ 44,000 Required: 1. Prepare a schedule of cost of goods manufactured for the month 2. Prepare a schedule of...
Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials Indirect materials used in production Direct labor Manufacturing overhead applied to work in process Underapplied overhead $32,000 $ 4,600 $58,800 $88,300 $ 4,060 Inventories Raw materials Work in process Finished goods Beginning $ 10,600 $ 54,700 $ 33,200 Ending $ 18, 800 $ 68,300 $ 42,100 Required: 1. Prepare a schedule of cost of goods manufactured for the month. 2. Prepare a schedule of...
Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials Indirect materials used in production Direct labor Manufacturing overhead applied to work in process Underapplied overhead $31,000 $ 4,920 $58,700 $88,000 $ 4,050 Inventories Raw materials Work in process Finished goods Beginning $ 11,200 $ 54,300 $ 33,900 Ending $ 18,500 $ 65,800 $ 42,500 Required: 1. Prepare a schedule of cost of goods manufactured for the month. 2. Prepare a schedule of cost...
Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials Indirect materials included in manufacturing overhead Direct labor Manufacturing overhead applied to work in process Underapplied overhead $ 31,000 $ 4,570 $ 59,000 $ 88,900 $ 4,190 Inventories Raw materials Work in process Finished goods Beginning $ 10,700 $ 54,400 $ 33,600 Ending $ 18,300 $ 68,200 $ 42,700 Required: 1. Prepare a schedule of cost of goods manufactured for the month. 2. Prepare...
Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials Indirect materials included in manufacturing overhead Direct labor Manufacturing overhead applied to work in process Underapplied overhead $32,000 $ 4,660 $58, 100 $87,900 $ 4,020 Inventories Raw materials Work in process Finished goods Beginning $ 11,600 $ 54,200 $ 34,000 Ending $ 18,700 $ 65,900 $ 43,200 Required: 1. Prepare a schedule of cost of goods manufactured for the month. 2. Prepare a schedule...
Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials Indirect materials included in manufacturing overhead Direct labor Manufacturing overhead applied to work in process Underapplied overhead $ 30,000 $ 5,000 $ 58,000 $ 87,000 $ 4,000 Inventories Raw materials Work in process Finished goods Beginning Ending $ 12,000 $18,000 $ 56,000 $ 65,000 $ 35,000 $ 42,000 Required: 1. Prepare a schedule of cost of goods manufactured for the month. 2. Prepare a...
Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials Indirect materials included in manufacturing overhead Direct labor Manufacturing overhead applied to work in process Underapplied overhead $31,000 $ 4,710 $59,400 $88,800 $ 4,010 Inventories Raw materials Work in process Finished goods Beginning Ending $ 11,500 $ 19,700 $ 54,700 $ 66,600 $ 34,300 $ 42,400 Required: 1. Prepare a schedule of cost of goods manufactured for the month. 2. Prepare a schedule of...
Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials Indirect materials included in manufacturing overhead Direct labor Manufacturing overhead applied to work in process Underapplied overhead $31,000 $ 4,620 $58, 200 $87,200 $ 4,070 Inventories Raw materials Work in process Finished goods Beginning $ 10,000 $ 54,500 $ 34,800 Ending $ 18,700 $ 67,800 $ 42,600 Required: 1. Prepare a schedule of cost of goods manufactured for the month. 2. Prepare a schedule...
Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials Indirect materials included in manufacturing overhead Direct labor Manufacturing overhead applied to work in process Underapplied overhead $ 31,000 $ 4,640 $ 58,200 $ 88,400 $ 4,020 Inventories Beginning Ending Raw materials $11,700 $19,100 Work in $55,800 $68,700 process Finished $34,000 $43,200 goods Required: 1. Prepare a schedule of cost of goods manufactured for the month. 2. Prepare a schedule of cost of goods...