Fedora, Inc, uses a weighted-average process-costing system and has one production department. All materials are introduced at the start of manufacturing; in contrast, conversion cost is incurred uniformly throughout production. The company had respective work-in-process inventories on May 1 and May 31 of 62,500 units and 72,500 units, the latter of which was 50% complete. The production supervisor noted that Fedora completed 100,000 units during the month.
Costs in the May 1 work-in-process inventory were subdivided as
follows: materials, $42,500; conversion, $95,000. During May,
Fedora charged production with $388,750 of material and $760,000 of
conversion, resulting in a material cost per equivalent unit of
$2.50.
Required:
Answers
Units Reconciliation |
|
Units to account for: |
|
Beginning WIP |
62,500 |
Units started this period |
110,000 [172500 – 62500] |
Total Units to account for |
172,500 |
Total Units accounted for: |
|
Completed & Transferred out |
100,000 |
Ending WIP |
72,500 |
Total Units accounted for |
172,500 |
EUP - Weighted Average Method |
Units |
% Material |
EUP Materials |
% Conversion |
EUP - Conversion |
Units TRANSFERRED |
100,000 |
100% |
100,000 |
100% |
100,000 |
Units of ENDING WIP |
72,500 |
100% |
72,500 |
50% |
36,250 |
Equivalent Units of Production |
172,500 |
136,250 ANSWER |
COST per EUP |
Conversion |
Cost of Beginning WIP |
$ 95,000.00 |
Cost incurred during the period |
$ 760,000.00 |
Total Costs |
$ 855,000.00 |
Equivalent units of production |
136,250 |
Cost per EUP |
$ 6.27523 or $ 6.28 |
Cost of ending WIP Inventory = $ 408,900
Cost of ending WIP |
EUP |
Cost per EUP |
Total Cost |
|
- Direct Materials |
72,500 |
$ 2.50 |
$ 181,250.00 |
|
- Conversion |
36,250 |
$ 6.28 |
$ 227,650.00 |
|
Total cost of ending WIP |
$ 408,900.00 |
--Work in Process Inventory must have been credited. [Finished goods inventory is debited]
Fedora, Inc, uses a weighted-average process-costing system and has one production department. All materials are introduced...
Fedora, Inc, uses a weighted average process-costing system and has one production department. All materials are introduced at the start of manufacturing: in contrast, conversion cost is incurred uniformly throughout production. The company had respective work in process inventories on May 1 and May 31 of 62,100 units and 70,500 units, the latter of which was 50% complete. The production supervisor noted that Fedora completed 100,000 units during the month. Costs in the May 1 work-in-process inventory were subdivided as...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete 76,000 Pounds started into production during May 410,000 Pounds completed and transferred out ? Pounds in process, May 31; materials 60% complete; conversion 40% complete 36,000 Cost data:...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: 70,000 350,000 30,000 Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete Pounds started into production during May Pounds completed and transferred out Pounds in process, May 31; materials 70% complete; conversion 30% complete Cost data: dala:...
Helix Corporation uses the weighted-average method in its process costing system. It produces prefabricated flooring in a series of steps carried out in production departments. All of the material that is used in the first production department is added at the beginning of processing in that department. Data for May for the first production department follow: Units 67,000 47,000 Work in process inventory, May 1 Work in process inventory, May 31 Materials cost in work in process inventory, May 1...
Builder Products, Inc., uses the weighted average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: points 8 04:22:47 60,000 250,000 20,000 Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete Pounds started into production during May Pounds completed and transferred out Pounds in process, May 31; materials 60% complete; conversion 40%...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: Production data: Pounds in process, May 1; materials 100% complete ; 55,000 330,000 conversion 908 complete Pounds started into production during May Pounds completed and transferred out Pounds in process, May 31; materials 60% complete ; con version 40% complete 15,000...
Builder Products, Inc., uses the weighted average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion Information on work in the first department, Cooking, is given below for May: 76,000 410,000 36,000 Production data Pounds in process, May 1; materials 100% complete; conversion 901 complete Pounds started into production during May Pounds completed and transferred out Pounds in process, May 31, materials 601 complete conversion 404 complete Cost data:...
Helix Corporation uses the weighted-average method in its process costing system. It produces prefabricated flooring in a series of steps carried out in production departments. All of the material that is used in the first production department is added at the beginning of processing in that department. Data for May for the first production department follow: Units 81,000 61,000 Work in process inventory, May 1 Work in process inventory, May 31 Materiale cont in work in process inventory, May 1...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete 88,000 Pounds started into production during May 530,000 Pounds completed and transferred out ? Pounds in process, May 31; materials 60% complete; conversion 40% complete 65,000 Cost data:...
Helix Corporation uses the weighted-average method in its process costing system. It produces prefabricated flooring in a series of steps carried out in production departments. All of the material that is used in the first production department is added at the beginning of processing in that department. Data for May for the first production department follow: Percent Complete Units Materials Conversion Work in process inventory, May 1 59,000 100 % 30 % Work in process inventory, May 31 39,000 100...