Question

Fey Companys organization chart includes the president; the vice president of production; three assembly plants-Dallas, AtlaPrepare the reports in a responsibility system for: The Finishing Department-Dallas. To Dallas Department Manager-Finishing F

0 0
Add a comment Improve this question Transcribed image text
Answer #1
To Dallas Department
Manager-Finishing
Favorable
Unfavorable
Neither Favorable
Controllable Costs: Budget Actual nor Unfavorable
Direct Materials $ 47,100 $ 44,630 $ 2,470 Favorable
Direct Labor $ 83,260 $ 84,360 $ -1,100 Unfavorable
Manufacturing Overhead $ 51,720 $ 52,400 $ -680 Unfavorable
Total $ 182,080 $ 181,390 $ 690 Favorable
Notes:
1. Actual material cost is less than budgeted material cost, so Favorable Variance.
2. Actual direct labor cost is more than budgeted direct labor cost, so Unfavorable Variance.
3. Actual MOH cost is more than Budgeted MOH cost, so Unfavorable Variance.
4. Total actual manufacturing costs is less than total budgeted manufacturing cost, so
Favorable Variance.
MOH = Manufacturing Overheads
Add a comment
Know the answer?
Add Answer to:
Fey Company's organization chart includes the president; the vice president of production; three assembly plants-Dallas, Atlanta,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas, Atlanta,...

    Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas, Atlanta, and Tucson; and two departments within each plant—Machining and Finishing. Budget and actual manufacturing cost data for July 2017 are as follows. Finishing Department—Dallas: direct materials $42,040 actual, $44,840 budget; direct labor $84,880 actual, $81,840 budget; manufacturing overhead $53,660 actual, $51,910 budget. Machining Department—Dallas: total manufacturing costs $220,090 actual, $216,510 budget. Atlanta Plant: total manufacturing costs $423,760 actual, $421,070 budget. Tucson Plant: total manufacturing...

  • Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas, Atlanta,...

    Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas, Atlanta, and Tucson; and two departments within each plant—Machining and Finishing. Budget and actual manufacturing cost data for July 2017 are as follows. Finishing Department—Dallas: direct materials $42,040 actual, $44,840 budget; direct labor $84,880 actual, $81,840 budget; manufacturing overhead $53,660 actual, $51,910 budget. Machining Department—Dallas: total manufacturing costs $220,090 actual, $216,510 budget. Atlanta Plant: total manufacturing costs $423,760 actual, $421,070 budget. Tucson Plant: total manufacturing...

  • Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas, Atlanta,...

    Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas, Atlanta, and Tucson; and two departments within each plant—Machining and Finishing. Budget and actual manufacturing cost data for July 2017 are as follows. Finishing Department—Dallas: direct materials $42,040 actual, $44,840 budget; direct labor $84,880 actual, $81,840 budget; manufacturing overhead $53,660 actual, $51,910 budget. Machining Department—Dallas: total manufacturing costs $220,090 actual, $216,510 budget. Atlanta Plant: total manufacturing costs $423,760 actual, $421,070 budget. Tucson Plant: total manufacturing...

  • Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas,...

    Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas, Atlanta, and Tucson; and two departments within each plant—Machining and Finishing. Budget and actual manufacturing cost data for July 2017 are as follows. Finishing Department—Dallas: direct materials $42,060 actual, $45,060 budget; direct labor $84,660 actual, $84,520 budget; manufacturing overhead $53,080 actual, $50,780 budget. Machining Department—Dallas: total manufacturing costs $222,520 actual, $216,690 budget. Atlanta Plant: total manufacturing costs $424,970 actual, $420,760 budget. Tucson Plant: total manufacturing...

  • Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas, Atlanta,...

    Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas, Atlanta, and Tucson; and two departments within each plant—Machining and Finishing. Budget and actual manufacturing cost data for July 2017 are as follows. Finishing Department—Dallas: direct materials $44,690 actual, $44,370 budget; direct labor $82,320 actual, $83,980 budget; manufacturing overhead $50,390 actual, $51,190 budget. Machining Department—Dallas: total manufacturing costs $220,830 actual, $218,820 budget. Atlanta Plant: total manufacturing costs $422,220 actual, $421,470 budget. Tucson Plant: total manufacturing...

  • Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas, Atlanta,...

    Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas, Atlanta, and Tucson; and two departments within each plant—Machining and Finishing. Budget and actual manufacturing cost data for July 2017 are as follows. Finishing Department—Dallas: direct materials $42,060 actual, $45,060 budget; direct labor $84,660 actual, $84,520 budget; manufacturing overhead $53,080 actual, $50,780 budget. Machining Department—Dallas: total manufacturing costs $222,520 actual, $216,690 budget. Atlanta Plant: total manufacturing costs $424,970 actual, $420,760 budget. Tucson Plant: total manufacturing...

  • Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas,...

    Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas, Atlanta, and Tucson; and two departments within each plant—Machining and Finishing. Budget and actual manufacturing cost data for July 2017 are as follows. Finishing Department—Dallas: direct materials $41,050 actual, $48,060 budget; direct labor $82,530 actual, $82,470 budget; manufacturing overhead $50,810 actual, $50,290 budget. Machining Department—Dallas: total manufacturing costs $223,720 actual, $218,800 budget. Atlanta Plant: total manufacturing costs $424,010 actual, $421,830 budget. Tucson Plant: total manufacturing...

  • Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas, Atlanta,...

    Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas, Atlanta, and Tucson; and two departments within each plant—Machining and Finishing. Budget and actual manufacturing cost data for July 2017 are as follows. Finishing Department—Dallas: direct materials $42,060 actual, $45,060 budget; direct labor $84,660 actual, $84,520 budget; manufacturing overhead $53,080 actual, $50,780 budget. Machining Department—Dallas: total manufacturing costs $222,520 actual, $216,690 budget. Atlanta Plant: total manufacturing costs $424,970 actual, $420,760 budget. Tucson Plant: total manufacturing...

  • Exercise 22-13 (Part Level Submission) Fey Company's organization chart includes the president; the vice president of...

    Exercise 22-13 (Part Level Submission) Fey Company's organization chart includes the president; the vice president of production; three assembly plants-Dallas, Atlanta, and Tucson; and two departments within each plant-Machining an Finishing. Budget and actual manufacturing cost data for July 2017 are as follows. Finishing Department-Dallas: direct materials $42,500 actual, $44,000 budget; direct labor $83,400 actual, $82,000 budget; manufacturing overhead $51,000 actual, $49,200 budget. Machining Department-Dallas: total manufacturing costs $220,000 actual, $219,000 budget. Atlanta Plant: total manufacturing costs $424,000 actual, $420,000...

  • Exercise 22-13 (Part Level Submission) Fey Company’s organization chart includes the president; the vice president of...

    Exercise 22-13 (Part Level Submission) Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas, Atlanta, and Tucson; and two departments within each plant—Machining and Finishing. Budget and actual manufacturing cost data for July 2017 are as follows. Finishing Department—Dallas: direct materials $44,680 actual, $45,200 budget; direct labor $84,290 actual, $81,470 budget; manufacturing overhead $51,440 actual, $52,000 budget. Machining Department—Dallas: total manufacturing costs $221,000 actual, $216,000 budget. Atlanta Plant: total manufacturing costs $423,230 actual, $424,070...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT