Controllable costs | Budget | Actual | Favourable Unfavourable Neither Favourable nor UnFavourable | |
Direct Materials | $ 44,000 | $ 42,500 | $ 1,500 | F |
Direct Labor | $ 82,000 | $ 83,400 | $ 1,400 | U |
Manufacturing overhead | $ 49,200 | $ 51,000 | $ 1,800 | U |
Total | $ 175,200 | $ 176,900 | $ 1,700 | U |
Exercise 22-13 (Part Level Submission) Fey Company's organization chart includes the president; the vice president of...
Exercise 22-13 (Part Level Submission) Fey Company's organization chart includes the president; the vice president of production; three assembly plants-Dallas, Atlanta, and Tucson; and two departments within Finishing. Budget and actual manufacturing cost data for July 2017 are as follows. Finishing Department-Dallas: direct materials $42,500 actual, $44,000 budget; direct labor $83,400 actual, $82,000 budget; manufacturing overhead $51,000 actual, $4 Machining Department-Dallas: total manufacturing costs $220,000 actual, $219,000 budget. Atlanta Plant: total manufacturing costs $424,000 actual, $420,000 budget. Tucson Plant: total...
Exercise 22-13 (Part Level Submission) Fey Company's organization chart includes the president; the vice president of production; three assembly plants-Dallas, Atlanta, and Tucson; and two departments within each plant-Machining Finishing. Budget and actual manufacturing cost data for July 2017 are as follows. Finishing Department-Dallas: direct materials $42,500 actual, $44,000 budget; direct labor $83,400 actual, $82,000 budget; manufacturing overhead $51,000 actual, $49,200 budget. Machining Department-Dallas: total manufacturing costs $220,000 actual, $219,000 budget. Atlanta Plant: total manufacturing costs $424,000 actual, $420,000 budget....
Exercise 22-13 (Part Level Submission) Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas, Atlanta, and Tucson; and two departments within each plant—Machining and Finishing. Budget and actual manufacturing cost data for July 2017 are as follows. Finishing Department—Dallas: direct materials $44,680 actual, $45,200 budget; direct labor $84,290 actual, $81,470 budget; manufacturing overhead $51,440 actual, $52,000 budget. Machining Department—Dallas: total manufacturing costs $221,000 actual, $216,000 budget. Atlanta Plant: total manufacturing costs $423,230 actual, $424,070...
Exercise 10-13 (Part Level Submission) Fultz Company's organization chart includes the president; the vice president of production; three assembly plants - Dallas, Atlanta, and Tucson; and two departments within each plant - Machining and Finishing. Budget and actual manufacturing cost data for July 2014 are as follows. Finishing Department - Dallas: Direct materials $43,640 actual, $45,010 budget; direct labor $83,520 actual, $84,010 budget; manufacturing overhead $52,310 actual, $50,410 budget. Machining Department - Dallas: Total manufacturing costs $224,620 actual, $218,390 budget....
Exercise 10-13 (Video) Fey Company's organization chart includes the president; the vice president of production; three assembly plants-Dallas, Atlanta, and Tucson; and two departments within each plant-Machining and Finishing. Budget and actual manufacturing cost data for July 2020 are as follows. Finishing Department-Dallas: direct materials $42,550 actual, $44,170 budget; direct labor $84,700 actual, $84,040 budget; manufacturing overhead $51,980 actual, $49,810 budget. Machining Department Dallas: total manufacturing costs $224,070 actual, $216,310 budget. Atlanta Plant: total manufacturing costs $424,370 actual, $424,610 budget....
Fey Company's organization chart includes the president; the vice president of production; three assembly plants-Dallas, Atlanta, and Tucson; and two departments within each plant-Machining and Finishing. Budget and actual manufacturing cost data for July 2017 are as follows. Finishing Department-Dallas: direct materials $44,630 actual, $47,100 budget; direct labor $84,360 actual, $83,260 budget; manufacturing overhead $52,400 actual, $51,720 budget. Machining Department-Dallas: total manufacturing costs $223,350 actual, $218,600 budget. Atlanta Plant: total manufacturing costs $422,140 actual, $420,720 budget. Tucson Plant: total manufacturing...
Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas, Atlanta, and Tucson; and two departments within each plant—Machining and Finishing. Budget and actual manufacturing cost data for July 2017 are as follows. Finishing Department—Dallas: direct materials $42,060 actual, $45,060 budget; direct labor $84,660 actual, $84,520 budget; manufacturing overhead $53,080 actual, $50,780 budget. Machining Department—Dallas: total manufacturing costs $222,520 actual, $216,690 budget. Atlanta Plant: total manufacturing costs $424,970 actual, $420,760 budget. Tucson Plant: total manufacturing...
Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas, Atlanta, and Tucson; and two departments within each plant—Machining and Finishing. Budget and actual manufacturing cost data for July 2017 are as follows. Finishing Department—Dallas: direct materials $42,060 actual, $45,060 budget; direct labor $84,660 actual, $84,520 budget; manufacturing overhead $53,080 actual, $50,780 budget. Machining Department—Dallas: total manufacturing costs $222,520 actual, $216,690 budget. Atlanta Plant: total manufacturing costs $424,970 actual, $420,760 budget. Tucson Plant: total manufacturing...
Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas, Atlanta, and Tucson; and two departments within each plant—Machining and Finishing. Budget and actual manufacturing cost data for July 2017 are as follows. Finishing Department—Dallas: direct materials $42,060 actual, $45,060 budget; direct labor $84,660 actual, $84,520 budget; manufacturing overhead $53,080 actual, $50,780 budget. Machining Department—Dallas: total manufacturing costs $222,520 actual, $216,690 budget. Atlanta Plant: total manufacturing costs $424,970 actual, $420,760 budget. Tucson Plant: total manufacturing...
Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas, Atlanta, and Tucson; and two departments within each plant—Machining and Finishing. Budget and actual manufacturing cost data for July 2017 are as follows. Finishing Department—Dallas: direct materials $44,690 actual, $44,370 budget; direct labor $82,320 actual, $83,980 budget; manufacturing overhead $50,390 actual, $51,190 budget. Machining Department—Dallas: total manufacturing costs $220,830 actual, $218,820 budget. Atlanta Plant: total manufacturing costs $422,220 actual, $421,470 budget. Tucson Plant: total manufacturing...