If a job consists of a batch of identical units, how can managers find the unit cost?
By dividing the total job cost by the number of units in the job = A |
||
By tracing direct materials to each unit = B |
||
By tracing direct labor to each unit = C |
||
By multiplying the total job cost by the number of units in the job = D |
Option A is the answer | |
If the batch of units are identical(similar to each other), Unit cost = Total cost incurred/no of units. Comment if you face any issues |
If a job consists of a batch of identical units, how can managers find the unit...
Pritchet Computer Company uses a job order costing system in which each batch manufactured is a different job. Pritchet Computer Company assigns direct materials and direct labor to each job. The company assigns labor costs at $22 per hour. It allocates manufacturing overhead to jobs based on a predetermined overhead allocation rate, computed as a percentage of direct labor costs. At the beginning of 2020, the controller prepared the following budget: (Click the icon to view the budget.) In November...
Hello, what is the answer to the question? EXERCISE 2–3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate LO2-3 @ Mickley Company's plantwide predetermined overhead rate is $14.00 per direct labor-hour and its direct labor wage rate is $17.00 per hour. The following information pertains to Job A-500: Direct materials $231 Direct labor $153 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 40 units,...
A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and was completed in 22.000 hours at a total labor cost of $269,500. What is the total labor cost variance? Ο $2,000 unfavorable Ο $3,000 unfavorable Ο $5,500 unfavorable Ο $8,000 unfavorable. Ο ( 59.000 unfavorable. Georgia, Inc. has collected the following data on one of its products. The direct materials quantity variance is: Direct materials standard (4...
Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate [LO2-3] Mickley Company's plantwide predetermined overhead rate is $22.00 per direct labor-hour and its direct labor wage rate is $15.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 210 $ 300 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 30 units, what is the unit product cost for...
Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate [LO2-3) Mickley Company's plantwide predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage rate is $11.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 60 units, what is the unit product cost for this job? (Round your...
Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate (LO2-3] Mickley Company's plantwide predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage rate is $10.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 260 $ 100 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 70 units, what is the unit product cost for...
Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate [LO2-3] Mickley Company's plantwide predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage rate is $14.00 per hour. The following information pertains to Job A-500: $ 240 $140 Direct materials Direct labor Required: 1. What is the total manufacturing cost assigned 2. If Job A-500 consists of 60 units, what is the unit product cost for this job? (Round your...
Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate [LO2-3] 0.62 points Mickley Company's plantwide predetermined overhead rate is $14.00 per direct labor-hour and its direct labor wage rate is $17.00 per hour. The following information pertains to Job A-500: eBook Hint Direct materials Direct labor $ 231 $ 153 Print References Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 40 units, what...
Exercise 2-4 (Algo) Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates (LO2-4) Fickel Company has two manufacturing departments---Assembly and Testing & Packaging. The predetermined overhead rates in Assembly and Testing & Packaging are $14.00 per direct labor-hour and $10.00 per direct labor-hour, respectively. The company's direct labor wage rate is $17.00 per hour. The following information pertains to Job N-60: Direct materials Direct labor Assembly $355 $102 Testing & Packaging $31 $34 Required: 1. What...
Exercise 2-5 (Algo) Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates (LO2-4] Braverman Company has two manufacturing departments—Finishing and Fabrication. The predetermined overhead rates in Finishing and Fabrication are $20.00 per direct labor-hour and 120% of direct materials cost, respectively. The company's direct labor wage rate is $26.00 per hour. The following information pertains to Job 700: Direct materials Direct labor Finishing $460 $390 Fabrication $ 85 $286 Required: 1. What is the total manufacturing...