Budgeted production | 870 |
(*) Direct labor hours per unit | 0.25 |
Total direct labor hours required for production | 217.50 |
(*) Direct labor cost per hour | 12.00 |
Budgeted direct labor cost | 2610 |
Total amount budgeted for manufacturing overhead = Budgeted direct labor cost * 110% = 2610 * 110% | 2871 |
QUESTIONS e Teller Co s planning to set 900 boos of the production deed labor Clay...
24. Which of the following costs are variable? 10,000 Units 30,000 Units $100,000 40,000 90,000 50,000 Cost $300,000 240,000 90,000 150,000 2. 4. A) only 2 B) only 1 C) 1 and 2 D) 1 and4 25. Eddy Company is starting business and is unsure of whether to sell its product assembled or unassembled. The unit cost of the unassembled product is $60 and Eddy Company would sell it for $135. The cost to assemble the product is estimated at...