Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer :- Computation of predetermined overhead rate for each department:-

1. Department D = Manufacturing Overhead / Direct labor costs

Department D = $784,000 / $1,120,000

Department D = 70%

2. Department E = Manufacturing Overhead / Direct labor hours

Department E = $1,500,000 / 125,000

Department E = $12 per direct labor hour

3. Department K = Manufacturing Overhead / Machine hours

Department K = $780,000 / 120,000

Department K = $6.5 per machine hour

If you still have any query ask in comment section. If you like the answer plz rate. Thanks

Add a comment
Know the answer?
Add Answer to:
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing...

    Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. D Manufacturing overhead Direct labor costs Direct labor hours Machine hours Department Ек $784,000 $1,500,000 $780,000 $1,120,000 $1,250,000 $450,000 100,000 125,000...

  • Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing...

    Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D. direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D. Manufacturing overhead $784,000 $1,500,000 $780,000 Direct labor costs $1,120,000 100,000 $1,250,000 $450,000 Direct labor hours 125,000 40,000 Machine hours...

  • Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing...

    Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D Manufacturing overhead $1,500,000 $720,000 Direct labor costs $1,250,000 $450,000 $959,000 $1,370,000 100,000 400,000 Direct labor hours 125,000 40,000 Machine...

  • Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing...

    Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D E K Manufacturing overhead $1,080,000 $1,500,000 $1,020,000 Direct labor costs $1,542,857 $1,250,000 $450,000 Direct labor hours 100,000 125,000 40,000...

  • Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing...

    Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D Manufacturing overhead Direct labor costs Direct labor hours Machine hours $945,000 $1,350,000 100,000 400,000 $1,750,000 $1,250,000 125,000 500,000 $1,080,000...

  • Problem 2-4A (Video) Agassi Company uses a job order cost system in each of its three...

    Problem 2-4A (Video) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department Manufacturing overhead Direct labor costs Direct labor hours Machine hours $1,260,000 $1,800,000 100,000 400,000 $1,750,000 $1,250,000 125,000...

  • Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing...

    Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D E Manufacturing overhead $1,500,000 $720,000 Direct labor costs $1,250,000 $450,000 $959,000 $1,370,000 100,000 400,000 Direct labor hours 125,000 40,000...

  • Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing...

    Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D Manufacturing overhead $1,500,000 $720,000 $450,000 Direct labor costs $959,000 $1,370,000 100,000 400,000 Direct labor hours $1,250,000 125,000 500,000 40,000...

  • Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing...

    Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D E K Manufacturing overhead $770,000 $1,500,000 $780,000 Direct labor costs $1,100,000 $1,875,000 $675,000 Direct labor hours 150,000 125,000 60,000...

  • Vaughn Company uses a job order cost system in each of its three manufacturing departments. Manufacturing...

    Vaughn Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department Manufacturing overhead Direct labor costs Direct labor hours Machine hours D $ 959,000 $ 1,370,000 100,000 400,000 $1,500,000 $1,250,000 125,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT