computing the over head rate...
Department D = Manufacturing overhead / Direct labour costs
= $959,000 / $1,370,000 =70%
Department E = Manufacturing overhead / Direct labour hours
= $1, 500,000 / 125000 = $12
Department K= Manufacturing overhead / Machine hours
= $720,000 / 120,000 = $6
computing total manufacturing costa assigned to jobs in januvary in each department
Department D = ($120,000 * 70%)= 84000
=(84,000 + 120,000+140,000) =$344,000
Department E= (11,000 * $12 )= $1,32,000
= (1,32,000 + 110,000 +126,000)=$368,000
Department K=(10410*$6)=$62460
=(62460+37500+78000)=$177,960
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing...
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D Manufacturing overhead $1,500,000 $720,000 $450,000 Direct labor costs $959,000 $1,370,000 100,000 400,000 Direct labor hours $1,250,000 125,000 500,000 40,000...
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D Manufacturing overhead $1,500,000 $720,000 Direct labor costs $1,250,000 $450,000 $959,000 $1,370,000 100,000 400,000 Direct labor hours 125,000 40,000 Machine...
Vaughn Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department Manufacturing overhead Direct labor costs Direct labor hours Machine hours D $ 959,000 $ 1,370,000 100,000 400,000 $1,500,000 $1,250,000 125,000...
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. D Manufacturing overhead Direct labor costs Direct labor hours Machine hours Department Ек $784,000 $1,500,000 $780,000 $1,120,000 $1,250,000 $450,000 100,000 125,000...
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D Manufacturing overhead Direct labor costs Direct labor hours Machine hours $945,000 $1,350,000 100,000 400,000 $1,750,000 $1,250,000 125,000 500,000 $1,080,000...
Agassi Company uses a job order cost system in each of its
three manufacturing departments. Manufacturing overhead is applied
to jobs on the basis of direct labor cost in Department D, direct
labor hours in Department E, and machine hours in Department
K.
In establishing the predetermined overhead rates for 2020, the
following estimates were made for the year.
Department
D
E
K
Manufacturing overhead
$1,080,000
$1,500,000
$1,020,000
Direct labor costs
$1,542,857
$1,250,000
$450,000
Direct labor hours
100,000
125,000
40,000...
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Manufacturing overhead Direct labor costs Direct labor hours Machine hours Department к $784,000 $1,500,000 $780,000 $1,120,000 $1,250,000 $450,000 100,000 125,000 40,000...
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D. direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D. Manufacturing overhead $784,000 $1,500,000 $780,000 Direct labor costs $1,120,000 100,000 $1,250,000 $450,000 Direct labor hours 125,000 40,000 Machine hours...
P2.4A (LO 3,5), AP Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department E K Manufacturing overhead Direct labor costs Direct labor hours Machine hours $1,200,000 $1,500,000 100,000 400,000...
P2-4A Agassi Company uses a job order cost system in each of its three manufacturing Compute predetermned departments. Manufacturing overhead is applied to jobs on the basis of direct labor overhead rates, apply cost in Department D, direct labor hours in Department E, and machine hours in overhead Department K. under- or overapplied overhead In establishing the predetermined overhead rates for 2017, the following estimates were made for the year LO 3, 5), AP Department Manufacturing overhead Direct labor costs...