Question

Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied
Compute the total manufacturing costs assigned to jobs in January in each department. Manufacturing Costs Department D A Depa
0 0
Add a comment Improve this question Transcribed image text
Answer #1

computing the over head rate...

Department D = Manufacturing overhead / Direct labour costs

= $959,000 / $1,370,000 =70%

Department E = Manufacturing overhead / Direct labour hours

= $1, 500,000 / 125000 = $12

Department K= Manufacturing overhead / Machine hours

= $720,000 / 120,000 = $6

computing total manufacturing costa assigned to jobs in januvary in each department

Department D = ($120,000 * 70%)= 84000

=(84,000 + 120,000+140,000) =$344,000

Department E= (11,000 * $12 )= $1,32,000

= (1,32,000 + 110,000 +126,000)=$368,000

Department K=(10410*$6)=$62460

=(62460+37500+78000)=$177,960

TOTAL MANUFACTURING COSTS ASSIGNED TO JOBS IN JAN MANUFACTURING COSTS DEPARTMENT D $344,000 DEPARTMENTE $368,000 DEPARTMENT K

TOTAL MANUFACTURING COSTS ASSIGNED TO JOBS IN JAN MANUFACTURING COSTS DEPARTMENT D $344,000 DEPARTMENTE $368,000 DEPARTMENT K

Add a comment
Know the answer?
Add Answer to:
Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing...

    Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D Manufacturing overhead $1,500,000 $720,000 $450,000 Direct labor costs $959,000 $1,370,000 100,000 400,000 Direct labor hours $1,250,000 125,000 500,000 40,000...

  • Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing...

    Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D Manufacturing overhead $1,500,000 $720,000 Direct labor costs $1,250,000 $450,000 $959,000 $1,370,000 100,000 400,000 Direct labor hours 125,000 40,000 Machine...

  • Vaughn Company uses a job order cost system in each of its three manufacturing departments. Manufacturing...

    Vaughn Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department Manufacturing overhead Direct labor costs Direct labor hours Machine hours D $ 959,000 $ 1,370,000 100,000 400,000 $1,500,000 $1,250,000 125,000...

  • Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing...

    Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. D Manufacturing overhead Direct labor costs Direct labor hours Machine hours Department Ек $784,000 $1,500,000 $780,000 $1,120,000 $1,250,000 $450,000 100,000 125,000...

  • Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing...

    Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D Manufacturing overhead Direct labor costs Direct labor hours Machine hours $945,000 $1,350,000 100,000 400,000 $1,750,000 $1,250,000 125,000 500,000 $1,080,000...

  • Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing...

    Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D E K Manufacturing overhead $1,080,000 $1,500,000 $1,020,000 Direct labor costs $1,542,857 $1,250,000 $450,000 Direct labor hours 100,000 125,000 40,000...

  • Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing...

    Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Manufacturing overhead Direct labor costs Direct labor hours Machine hours Department к $784,000 $1,500,000 $780,000 $1,120,000 $1,250,000 $450,000 100,000 125,000 40,000...

  • Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing...

    Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D. direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department D. Manufacturing overhead $784,000 $1,500,000 $780,000 Direct labor costs $1,120,000 100,000 $1,250,000 $450,000 Direct labor hours 125,000 40,000 Machine hours...

  • P2.4A (LO 3,5), AP Agassi Company uses a job order cost system in each of its...

    P2.4A (LO 3,5), AP Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. Department E K Manufacturing overhead Direct labor costs Direct labor hours Machine hours $1,200,000 $1,500,000 100,000 400,000...

  • P2-4A Agassi Company uses a job order cost system in each of its three manufacturing Compute...

    P2-4A Agassi Company uses a job order cost system in each of its three manufacturing Compute predetermned departments. Manufacturing overhead is applied to jobs on the basis of direct labor overhead rates, apply cost in Department D, direct labor hours in Department E, and machine hours in overhead Department K. under- or overapplied overhead In establishing the predetermined overhead rates for 2017, the following estimates were made for the year LO 3, 5), AP Department Manufacturing overhead Direct labor costs...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT