Question

B constructed a warehouse for its own use. B started construction on January 1 and completed...

B constructed a warehouse for its own use. B started construction on January 1 and completed construction on December 31.  Construction expenditures were as follows:

  • $350,000 on January 1
  • $420,000 on May 31
  • $250,000 on September 1
  • $140,000 on November 1

During the entire year B had the following outstanding notes payable:

  • A 5.00%, 5-year $8,000,000 note payable
  • A 4.50%, 7-year $4,000,000 note payable
  • A 3.00%, 4-year $5,000,000 note payable
  1. What were B’s total interest costs for the year?
  2. What amount of interest should B capitalize on this construction project?
  3. What was B’s interest expense for the year?

When necessary, round any interest rate as follows:  4.873% = 4.9% while 3.314% = 3.3%.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
a)
Total interest cost of B for the year
Amount Interest rate Interest amount
$    800,000 5% $     40,000
$    400,000 4.50% $     18,000
$    500,000 3% $     15,000
$     73,000
b)
Interest to be capitalized
Weighted average rate = 800,000x5%+400,000x4.5%+500,000x3%
         1,700,000
= 4.30%
Borrowig cost = (350,000x4.3%)+(420,000x4.3%x7/12)+(250,000x4.3%x4/12)+(140,000x4.3%x2/12)
= 30,172
c)
Interest expense for the year
= 73000 - 30172
= 42828
Add a comment
Know the answer?
Add Answer to:
B constructed a warehouse for its own use. B started construction on January 1 and completed...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Arlington Company is constructing a building. Construction began on January 1 and was completed on December...

    Arlington Company is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $4,000,000 on March 1, $3,300,000 on June 1, and $5,000,000 on December 31. Arlington Company borrowed $2,000,000 on January 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 3-year, $4,000,000 note payable and an 11%, 4-year, $7,500,000 note payable. What is the actual interest for Arlington Company?...

  • Windsor Furniture Company started construction of a combination office and warehouse building for its own use...

    Windsor Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $8,000,000 on January 1, 2020. Windsor expected to complete the building by December 31, 2020. Windsor has the following debt obligations outstanding during the construction period. $3,200,000 Construction loan-12% interest, payable semiannually, issued December 31, 2019 Short-term loan- 10% interest, payable monthly, and principal payable at maturity on May 30, 2021 2,240,000 Long-term loan-1 1% interest, payable on January...

  • Cheyenne Furniture Company started construction of a combination office and warehouse building for its own use...

    Cheyenne Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $8,000,000 on January 1, 2020. Cheyenne expected to complete the building by December 31, 2020. Cheyenne has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $3,200,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 2,240,000 Long-term loan-11% interest, payable on January 1 of...

  • Harrisburg Furniture Company started construction of a combination office and warehouse building for its own use...

    Harrisburg Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $5,000,000 on January 1, 2020. Harrisburg expected to complete the building by December 31, 2020. Harrisburg has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $2,000,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 1,400,000 Long-term loan-11% interest, payable on January 1 of...

  • Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 6% note $5,000,000, 2% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 540,000 September 30, 2018 750,000 November 30, 2018 750,000 January 30, 2019 690,000 The company’s fiscal year-end is December 31. Required: Calculate...

  • Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 8% note $5,000,000, 4% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 660,000 September 30, 2018 930,000 November 30, 2018 930,000 January 30, 2019 870,000 The company’s fiscal year-end is December 31. Required: Calculate...

  • Pronghorn Furniture Company started construction of a combination office and warehouse building for its own use...

    Pronghorn Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $8,500,000 on January 1, 2020. Pronghorn expected to complete the building by December 31, 2020. Pronghorn has the following debt obligations outstanding during the construction period. Construction loan-10% interest, payable semiannually, issued December 31, 2019 $3,400,000 Short-term loan-8% interest, payable monthly, and principal payable at maturity on May 30, 2021 $2,380,000 Long-term loan-9% interest, payable on January 1 of...

  • Coronado Furniture Company started construction of a combination office and warehouse building for its own use...

    Coronado Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $7,500,000 on January 1, 2020. Coronado expected to complete the building by December 31, 2020. Coronado has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $3,000,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 2,100,000 Long-term loan-11% interest, payable on January 1 of...

  • Pronghorn Furniture Company started construction of a combination office and warehouse building for its own use...

    Pronghorn Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $13,000,000 on January 1, 2020. Pronghorn expected to complete the building by December 31, 2020. Pronghorn has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019                                        $5,200,000Short-term loan-10% interest, payable monthly, and principal...

  • Teal Furniture Company started construction of a combination office and warehouse building for its own use...

    Teal Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $5,000,200 on January 1, 2017. Teal expected to complete the building by December 31, 2017. Teal has the following debt obligations outstanding during the construction period. Please make the answer clear to see and bold. Thank you so much for all your help. Exercise 10-7 (Part Level Submission) Teal Furniture Company started construction of a combination office and warehouse...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT