Question

Coronado Furniture Company started construction of a combination office and warehouse building for its own use...

Coronado Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $7,500,000 on January 1, 2020. Coronado expected to complete the building by December 31, 2020. Coronado has the following debt obligations outstanding during the construction period.

Construction loan-12% interest, payable semiannually, issued December 31, 2019 $3,000,000
Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 2,100,000
Long-term loan-11% interest, payable on January 1 of each year. Principal payable on January 1, 2024 1,500,000

Assume that Coronado completed the office and warehouse building on December 31, 2020, as planned at a total cost of $7,800,000, and the weighted-average amount of accumulated expenditures was $5,400,000. Compute the avoidable interest on this project.

Compute the depreciation expense for the year ended December 31, 2021. Coronado elected to depreciate the building on a straight-line basis and determined that the asset has a useful life of 30 years and a salvage value of $450,000.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Calculation of weighted average interest rate:
Type of loan Principal Interest Rate Interest
Short Term Loan-10% Interest                                                       2,100,000 10%          210,000
Long Term Loan-11% Interest                                                       1,500,000 11%          165,000
Total                                                       3,600,000          375,000
Weighted Average Interest Rate= Total Interest / Total Principal
=375000/3600000
=10.42%
Available Interest Calculation:
Particulars Principal Balance of Weighted Average Accumulated Expenditure Interest Rate Available Interest
Interest on Loan specifically for Contruction                                                       3,000,000 12%          360,000
Interest on remaining loan upto weighted average expenditure total using weighted average interest rate                                                       2,400,000 10.42%          250,080
Total                                                       5,400,000          610,080
Available Interest $ 610,080
Calculation of Depreciation Expense:
Total Cost =Cost Incurred + Interest Capitalised
=7800000+610080
=8410080
Depreciation Expense =(Total Cost-Estimated Salvage Value)/Estimated Useful Life
=(8410080-450000)/30
Depreciation Expense =265336
Add a comment
Know the answer?
Add Answer to:
Coronado Furniture Company started construction of a combination office and warehouse building for its own use...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Pearl Furniture Company started construction of a combination office and warehouse building for its own use...

    Pearl Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $7,500,000 on January 1, 2020. Pearl expected to complete the building by December 31, 2020. Pearl has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 Long-term loan-11% interest, payable on January 1 of each year....

  • Coronado Furniture Company started construction of a combination office and warehouse building for its own use at an est...

    Coronado Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $14,500,000 on January 1, 2020. Coronado expected to complete the building by December 31, 2020. Coronado has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $5,800,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 4,060,000 Long-term loan-11% interest, payable on January 1 of...

  • Sheridan Furniture Company started construction of a combination office and warehouse building for its own use...

    Sheridan Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $13,500,000 on January 1, 2020. Sheridan expected to complete the building by December 31, 2020. Sheridan has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 Long-term loan-11% interest, payable on January 1 of each year....

  • Oriole Furniture Company started construction of a combination office and warehouse building for its own use...

    Oriole Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $13,500,000 on January 1, 2020. Oriole expected to complete the building by December 31, 2020. Oriole has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $5,400,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 3,780,000 Long-term loan-11% interest, payable on January 1 of...

  • Pronghorn Furniture Company started construction of a combination office and warehouse building for its own use...

    Pronghorn Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $8,500,000 on January 1, 2020. Pronghorn expected to complete the building by December 31, 2020. Pronghorn has the following debt obligations outstanding during the construction period. Construction loan-10% interest, payable semiannually, issued December 31, 2019 $3,400,000 Short-term loan-8% interest, payable monthly, and principal payable at maturity on May 30, 2021 $2,380,000 Long-term loan-9% interest, payable on January 1 of...

  • Martinez Furniture Company started construction of a combination office and warehouse building for its own use...

    Martinez Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $15,000,000 on January 1, 2020. Martinez expected to complete the building by December 31, 2020. Martinez has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 Long-term loan-11% interest, payable on January 1 of each year....

  • Pearl Furniture Company started construction of a combination office and warehouse building for its own use...

    Pearl Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $15,000,000 on January 1, 2020. Pearl expected to complete the building by December 31, 2020. Pearl has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $6,000,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 4,200,000 Long-term loan-11% interest, payable on January 1 of...

  • Blue Furniture Company started construction of a combination office and warehouse building for its own use...

    Blue Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $3,000,000 on January 1, 2020. Blue expected to complete the building by December 31, 2020. Blue has the following debt obligations outstanding during the construction period. $1,200,000 Construction loan-12% interest, payable semiannually, issued December 31, 2019 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 840,000 600,000 Long-term loan-11% interest, payable on January 1...

  • Pearl Furniture Company started construction of a combination office and warehouse building for its own use...

    Pearl Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $15,000,000 on January 1, 2020. Pearl expected to complete the building by December 31, 2020. Pearl has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $6,000,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 4,200,000 Long-term loan-11% interest, payable on January 1 of...

  • Windsor Furniture Company started construction of a combination office and warehouse building for its own use at an esti...

    Windsor Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $10,500,000 on January 1, 2020. Windsor expected to complete the building by December 31, 2020. Windsor has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $4,200,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 2,940,000 Long-term loan-11% interest, payable on January 1 of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT