Question

Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $1,700,000 investment in threading equipment to get the project started: The project will last for 5 years. The accounting department estimates that annual fixed costs will be $450,000 and that variable cost should be $210 per ton; account will depreciate the initial fixed asset investment straight line to zero over the five year project life. It also estimates a salvage value of $500,000 after dismanatling costs. The marketing department estimates that the automakers will let the contract at a selling price of $230 per ton. The engineering department estimates you will need an initial working capital investment of $450,000. You will require a 13 percent return and face a marginal tax rate of 38 percent.

1. What is the estimated OCF for this project? The NPV? Should ou pursue this project?

2. Suppose you believe that the accounting department's initial cost and salvage value projections are accurate only to within \pm 15 percent; the marketing department's price estimate is accurate only to within \pm 10 percent; and the engineering department's net working capital estimate is accurate only to with \pm 15 percent. What is your worst case scenario? What is your best case scenario? Do you still want to pursue this project? (Assuming there is an equal likelihood of occurrences in all possible scenarios.)

3. Suppose you are confident about your projections but you are a little unsure about Detroit's actual machine screw requirement. What is the sensitivity of the project OCF to changes in the quantity supplied? Is there some minimum level of output below which you would not want to operate and if so; why?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

160000 depre ciation 17 -340,00 Pereay expendi ture$u50 000 Fixed Salvage value - 500, 000 dapreciafed The entire value SimceCal. of N.p.v 03 Tflow 1100, 000 Inibia OUT HInitias workingdapitl 21S0000 alu Inflows melwtiy value of Present value Selvogecase np.v wor st Inital Gt Increases TO $1955000 e $391000 Apnddepreciatin Salvage value decrea ses is f So0000-15 4a5 000 5LRest case NPV decreaseg IS Ini i Hial Cott 1y5,00 1445000 dep 289 o00 Solvage value S00000 415. 6SE Price 1 by loy 3eling ConN°P.v of Cal us0 000 C0.85)+ 891220 (PUIFA 131,5) -1445000 CI13)5 Rest Case NPV -$1,724,329 82 Sales :- Breal even Break even

Add a comment
Know the answer?
Add Answer to:
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production. You will need an initial $2,200,000 investment in threading equipment to get the project started; the project will last for five years. The accounting department estimates that annual fixed costs will be $700,000 and that variable costs should be $400 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. It also estimates a salvage value...

  • Scenario Analysis [L02] Consider a project to supply Detroit with 30,000 tons of machine screws annually...

    Scenario Analysis [L02] Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production. You will need an initial $4.3 million investment in threading equipment to get the project started: the project will last for five years. The accounting department estimates that annual fixed costs will be $1.025 million and that variable costs should be $190 per ton: accounting will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. It...

  • Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $4,800,000 investment in threading equipment to get the project started; the project will last for three years. The accounting department estimates that annual fixed costs will be $850,000 and that variable costs should be $250 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the three-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $4,700,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,125,000 and that variable costs should be $210 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production. You will need an initial $4.3 million investment in threading equipment to get the project started; the project will last for five years. The accounting department estimates that annual fixed costs will be $1.025 million and that variable costs should be $190 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. It also estimates a...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,300,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,275,000 and that variable costs should be $240 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production. You will need an initial $4,500,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,075,000 and that variable costs should be $200 per ton; accounting will depreciate the in itial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage...

  • Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will...

    Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,500,000 and that variable costs should be $285 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,500,000 and that variable costs should be $285 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,500,000 and that variable costs should be $285 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT