Question

Scenario Analysis [L02] Consider a project to supply Detroit with 30,000 tons of machine screws annually...

Scenario Analysis [L02] Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production. You will need an initial $4.3 million investment in threading equipment to get the project started: the project will last for five years. The accounting department estimates that annual fixed costs will be $1.025 million and that variable costs should be $190 per ton: accounting will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. It also estimates a salvage value of $400,000 after dismantling costs. The marketing department estimates that the automakers will let the contract at a selling price of $290 per ton. The engineering department estimates you will need an initial net working capital investment of $410,000. You require a return of 13 percent and face a tax rate of 22 percent on this project.

a. What is the estimated OCF for this project? The NPV? Should you pursue this project?

b. Suppose you believe that the accounting department's initial cost and salvage value projections are accurate only to within ±15 percent; the marketing depart-ment's price estimate is accurate only to within ±10 percent; and the engineering department's net working capital estimate is accurate only to within ±5 percent. What is your worst-case for this project? Your best-case scenario? Do scenario for you still want to pursue the project?

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Scenario Analysis [L02] Consider a project to supply Detroit with 30,000 tons of machine screws annually...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production. You will need an initial $4.3 million investment in threading equipment to get the project started; the project will last for five years. The accounting department estimates that annual fixed costs will be $1.025 million and that variable costs should be $190 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. It also estimates a...

  • Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production. You will need an initial $2,200,000 investment in threading equipment to get the project started; the project will last for five years. The accounting department estimates that annual fixed costs will be $700,000 and that variable costs should be $400 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $4,800,000 investment in threading equipment to get the project started; the project will last for three years. The accounting department estimates that annual fixed costs will be $850,000 and that variable costs should be $250 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the three-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $1,700,000 investment in threading equipment to get the project started: The project will last for 5 years. The accounting department estimates that annual fixed costs will be $450,000 and that variable cost should be $210 per ton; account will depreciate the initial fixed asset investment straight line to zero over the five year project life. It also estimates a...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,300,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,275,000 and that variable costs should be $240 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production. You will need an initial $4,600,000 investment in threading equipment to get the project started; the project will last for 3 years. The accounting department estimates that annual fixed costs will be $750,000 and that variable costs should be $410 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 3-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will...

    Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,500,000 and that variable costs should be $285 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,500,000 and that variable costs should be $285 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • 20 points Consider a project to supply Detroit with 27,000 tons of machine screws annually for...

    20 points Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,000,000 Investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,200,000 and that variable costs should be $225 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a...

  • Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production. You will need an initial $4,500,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,075,000 and that variable costs should be $200 per ton; accounting will depreciate the in itial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT