CLICK HERE TO REVIEW LEARNING OBIECTIVES QUESTION 6 Not complete Marked out of 16.00 Flag question Two-Stage ABC for Manufacturing Detroit Foundry, a large manufacturer of heavy equipment components, has determined the following activity cost pools and cost driver levels for the year: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup Material handling Machine operation $624,000 12,000 setup hours 144,000 2,000 material moves 10,000 machine hours The following data are for the production of single batches of two products, C23 Cams and U2 Shafts during the month of August: C23 Cams U2 Shafts Units produced Machine hours Direct labor hours Direct labor cost Direct materials cost $32,000 $22,000 Tons of materials Setup hours Determine the unit costs of C23 Cams and U2 Shafts using ABC. Round cost per gallon to two decimal places. 400 $7,000 $12,000 13 Product Costs C23 Cams U2 Shafts Direct materials Direct labor Manufacturing overhead: Machine setups Material handling Machine operation Total job costs Units produced Cost per unit produced Check

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Calculation of Activity rates

Activity Cost Pool

Activity driver

Overhead Cost

Expected Activity (B)

Acttvity rate (A/B)

Machine setups

Number of Setup hour

$ 6,24,000.00

12,000

$            52.00

Per Setup hour

Machine handling

Number of Material move

$ 1,44,000.00

2000

$            72.00

Per Material move

machine operation

Number of Machine hour

$ 5,00,000.00

10000

$            50.00

Per Machine hour

Overhead Cost assigned to C23 cams

Activity name

Activity Rates

Activity

ABC Cost

(A)

(B)

(A x B)

Machine setups

$        52.00

3

$   156.00

Machine handling

$        72.00

13

$   936.00

machine operation

$        50.00

4

$   200.00

Overhead Cost assigned to Component U2 Shafts

Activity rate(A)

Activity Driver Incurred (B)

Overhead Assigned (C=A*B)

Machine setups

$ 52.00

7

$      364.00

Machine handling

$ 72.00

8

$      576.00

machine operation

$ 50.00

5

$      250.00

Solution

Product Costs

C23 Cams

U2 shafts

Direct material

$         7,000.00

$   12,000.00

Direct labor

$      32,000.00

$   22,000.00

Manufacturing overheads

Machine setups

$            156.00

$         364.00

Machine handling

$            936.00

$         576.00

Machine operation

$            200.00

$         250.00

Total job costs

$      40,292.00

$   35,190.00

Units produced

                      500

                  300

Cost per Unit produced

$               80.58

$         117.30

Add a comment
Know the answer?
Add Answer to:
CLICK HERE TO REVIEW LEARNING OBIECTIVES QUESTION 6 Not complete Marked out of 16.00 Flag question...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Two-Stage ABC for Manufacturing Detroit Foundry, a large manufacturer of heavy equipment components, has determined the...

    Two-Stage ABC for Manufacturing Detroit Foundry, a large manufacturer of heavy equipment components, has determined the following activity cost pools and cost driver levels for the year: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup $720,000 12,000 setup hours Material handling 120,000 3,000 material moves Machine operation 680,000 10,000 machine hours The following data are for the production of single batches of two products, C23 Cams and U2 Shafts during the month of August: C23 Cams U2 Shafts...

  • Two-Stage ABC for Manufacturing Detroit Foundry, a large manufacturer of heavy equipment components, has determined the...

    Two-Stage ABC for Manufacturing Detroit Foundry, a large manufacturer of heavy equipment components, has determined the following activity cost pools and cost driver levels for the year: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup $600,000 12,000 setup hours Material handling 120,000 2,000 material moves Machine operation 500,000 10,000 machine hours The following data are for the production of single batches of two products, C23 Cams and U2 Shafts during the month of August: C23 Cams U2 Shafts...

  • Two-Stage ABC for Manufacturing Detroit Foundry, a large manufacturer of heavy equipment components, has determined the...

    Two-Stage ABC for Manufacturing Detroit Foundry, a large manufacturer of heavy equipment components, has determined the following activity cost pools and cost driver levels for the year: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup $720,000 12,000 setup hours Material handling 120,000 3,000 material moves Machine operation 680,000 10,000 machine hours The following data are for the production of single batches of two products, C23 Cams and U2 Shafts during the month of August: C23 Cams U2 Shafts...

  • If you could please explain how you get the answers it would really help me E5-4B....

    If you could please explain how you get the answers it would really help me E5-4B. Stage Two ABC for Manufacturing Detroit Foundry, a large manufacturer of heavy equipment components, has determined the following activity cost pools and cost driver levels for the year: LO2 Activity Cost Pool Activity Cost Activity Cost Driver Machine setup Materials handling Machine operation $720,000 120,000 12,000 setup hours 3,000 tons of materials 10,000 machine hours 680,000 The following data are for the production of...

  • CLICK HERE TO REVIEW LEARNING OBJECTIVES QUESTION 5 Not complete Marked out of 16.00 Flag question...

    CLICK HERE TO REVIEW LEARNING OBJECTIVES QUESTION 5 Not complete Marked out of 16.00 Flag question Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity cost pools and cost driver levels for the latest period Activity Cost Pool Activity Cost Activity Cost Driver Machine setup Material handling Machine operation $1,000,000 870,000 200,000 2,500 setup hours 5,000 material moves 20,000 machine hours The following data are for the production of single batches of two...

  • CLICK HERE TO REVIEW LEARNING OBJECTIVES QUESTION 1 Not yet answered Marked out of 16.00 Flag...

    CLICK HERE TO REVIEW LEARNING OBJECTIVES QUESTION 1 Not yet answered Marked out of 16.00 Flag question Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity cost pools and cost driver levels for the latest period: Activity Cost Pool Machine setup Material handling Machine operation Activity Cost $990,000 860,000 200,000 Activity Cost Driver 2,500 setup hours 5,000 material moves 20,000 machine hours The following data are for the production of single batches of...

  • Mys Euestion 10 Not complete Marked out of 1.00 P Flag question Iwo-Stage ABC for Manufacturing...

    Mys Euestion 10 Not complete Marked out of 1.00 P Flag question Iwo-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity cost pools and cost driver levels for the latest period: Activity cost pool Activity cost Activity cost driver Machine setup $950,000 2.500 setup hours Material handling 620,000 5.000 material moves Machine operation 200.000 20.000 machine hours The following data are for the production of single batches of two products, Mirlite and Subdue:...

  • Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity...

    Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity cost pools and cost driver levels for the latest period: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup 5900,000 2,500 setup hours Material handling 820.000 4.000 material moves Machine operation 400,000 20,000 machine hours The following data are for the production of single batches of two products, Mirlite and Subdue: Mirlite Subdue Gallons produced 60.000 25,000 Direct Isbor hours 400 250 Machine...

  • Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity...

    Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity cost pools and cost driver levels for the latest period: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup $900,000 2,500 setup hours Material handling 820,000 4,000 material moves Machine operation 400,000 20,000 machine hours The following data are for the production of single batches of two products, Mirlite and Subdue: Mirlite Subdue Gallons produced 60,000 25,000 Direct labor hours 400 250 Machine...

  • Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity...

    Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity cost pools and cost driver levels for the latest period: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup $900,000 2,500 setup hours Material handling 820,000 4,000 material moves Machine operation 400,000 20,000 machine hours The following data are for the production of single batches of two products, Mirlite and Subdue: Mirlite Subdue Gallons produced 60.000 25,000 Direct labor hours 400 250 Machine...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT