Two-Stage ABC for Manufacturing
Detroit Foundry, a large manufacturer of heavy equipment
components, has determined the following activity cost pools and
cost driver levels for the year:
Activity Cost Pool | Activity Cost |
Activity Cost Driver |
|
---|---|---|---|
Machine setup | $600,000 |
12,000 setup hours |
|
Material handling | 120,000 |
2,000 material moves |
|
Machine operation | 500,000 |
10,000 machine hours |
The following data are for the production of single batches of two products, C23 Cams and U2 Shafts during the month of August:
C23 Cams | U2 Shafts | |
---|---|---|
Units produced | 500 | 300 |
Machine hours | 4 | 5 |
Direct labor hours | 200 | 400 |
Direct labor cost | $5,000 | $10,000 |
Direct materials cost | $30,000 | $20,000 |
Tons of materials | 13 | 8 |
Setup hours | 3 | 7 |
Determine the unit costs of C23 Cams and U2 Shafts using
ABC.
Round cost per gallon to two decimal places.
Product Costs | ||
---|---|---|
C23 Cams | U2 Shafts | |
Direct materials | Answer | Answer |
Direct labor | Answer | Answer |
Manufacturing overhead: | ||
Machine setups | Answer | Answer |
Material handling | Answer | Answer |
Machine operation | Answer | Answer |
Total job costs | Answer | Answer |
Units produced | Answer | Answer |
Cost per unit produced | Answer | Answer |
Product costs | ||||||
C23 Cams | U2 Shafts | |||||
Direct materials | 30000 | 20000 | ||||
Direct labor | 5000 | 10000 | ||||
Manufacturing overhead: | ||||||
Machine setups | 150 | 350 | ||||
Machine handling | 780 | 480 | ||||
Machine operation | 200 | 250 | ||||
Total job costs | 36130 | 31080 | ||||
Units produced | 500 | 300 | ||||
cost per unit produced | 72.26 | 103.6 | ||||
Cost per activity | ||||||
activity cost | activity cost driver | Activity rate | ||||
machine setup | 600000 | 12000 | 50 | per setup | ||
material handling | 120000 | 2000 | 60 | per material move | ||
machine operation | 500000 | 10000 | 50 | per machine hr |
Please give a thumbs up if it is helpful & let me know if any doubt
Two-Stage ABC for Manufacturing Detroit Foundry, a large manufacturer of heavy equipment components, has determined the...
Two-Stage ABC for Manufacturing Detroit Foundry, a large manufacturer of heavy equipment components, has determined the following activity cost pools and cost driver levels for the year: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup $720,000 12,000 setup hours Material handling 120,000 3,000 material moves Machine operation 680,000 10,000 machine hours The following data are for the production of single batches of two products, C23 Cams and U2 Shafts during the month of August: C23 Cams U2 Shafts...
Two-Stage ABC for Manufacturing Detroit Foundry, a large manufacturer of heavy equipment components, has determined the following activity cost pools and cost driver levels for the year: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup $720,000 12,000 setup hours Material handling 120,000 3,000 material moves Machine operation 680,000 10,000 machine hours The following data are for the production of single batches of two products, C23 Cams and U2 Shafts during the month of August: C23 Cams U2 Shafts...
CLICK HERE TO REVIEW LEARNING OBIECTIVES QUESTION 6 Not complete Marked out of 16.00 Flag question Two-Stage ABC for Manufacturing Detroit Foundry, a large manufacturer of heavy equipment components, has determined the following activity cost pools and cost driver levels for the year: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup Material handling Machine operation $624,000 12,000 setup hours 144,000 2,000 material moves 10,000 machine hours The following data are for the production of single batches of two...
If you could please explain how you get the answers it would really help me E5-4B. Stage Two ABC for Manufacturing Detroit Foundry, a large manufacturer of heavy equipment components, has determined the following activity cost pools and cost driver levels for the year: LO2 Activity Cost Pool Activity Cost Activity Cost Driver Machine setup Materials handling Machine operation $720,000 120,000 12,000 setup hours 3,000 tons of materials 10,000 machine hours 680,000 The following data are for the production of...
Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity cost pools and cost driver levels for the latest period: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup 5900,000 2,500 setup hours Material handling 820.000 4.000 material moves Machine operation 400,000 20,000 machine hours The following data are for the production of single batches of two products, Mirlite and Subdue: Mirlite Subdue Gallons produced 60.000 25,000 Direct Isbor hours 400 250 Machine...
Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity cost pools and cost driver levels for the latest period: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup $900,000 2,500 setup hours Material handling 820,000 4,000 material moves Machine operation 400,000 20,000 machine hours The following data are for the production of single batches of two products, Mirlite and Subdue: Mirlite Subdue Gallons produced 60,000 25,000 Direct labor hours 400 250 Machine...
Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity cost pools and cost driver levels for the latest period: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup $900,000 2,500 setup hours Material handling 820,000 4,000 material moves Machine operation 400,000 20,000 machine hours The following data are for the production of single batches of two products, Mirlite and Subdue: Mirlite Subdue Gallons produced 60.000 25,000 Direct labor hours 400 250 Machine...
Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity cost pools and cost driver levels for the latest period: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup $900,000 2,500 setup hours Material handling 820,000 4,000 material moves Machine operation 400,000 20,000 machine hours The following data are for the production of single batches of two products, Mirlite and Subdue: Mirlite Subdue Gallons produced 60,000 25,000 Direct labor hours 400 250 Machine...
help! San Antonio Foundry recently implemented an activity-based costing system. It has determined the following costs pools and cost drivers for the year: Activity cost pool Esimated acivity costs Estimated Allocation Base Machine setup $900,000 12,000 setup hours Machine operation $500,000 10,000 machine hours Inspections $120,000 4,000 inspections The following data is for the production of its U2 shafts during the month of January: Units produced 400 Direct materials cost $20,000 Direct labor cost $10,000 Setup hours 7 Machine hours...
Two-Stage ABC for Manufacturing Merlot Company has determined its activity cost pools and cost drivers to be the following: Cost Pools Setup Material handling Machine operation packing Total indirect manufacturing costs $112,000 25,600 480,000 60,000 $677,600 Cost drivers Setups Material moves Machine hours Packing orders 350 640 20,000 1,200 One product made by Merlot, metal casements, used the following activities during the period to produce 500 units: Setups Material moves 80 Machine hours 1,900 Packing orders 150 20 a. Calculate...