Answer:
Correct option is B. $2.54
Explanation:
Step 1:
Per machine setup hour cost = $900000 / 12000 = $75
Per machine operation = $500000 / 10000 = $50
Per inspection cost = $120000 / 4000 = $30
Step 2:
calculation of Total manufacturing overhead:
Setup cost = 7 setup hours x $75 = $525
Machine operation cost = 5 x $50 = $250
Inspection cost = 8 x $30 = $240
Total manufacturing overhead = $525 + $250 + $240 = $1015
Step 3:
Per unit manufacturing overhead cost = $1015 / 400 units = $2.54
help! San Antonio Foundry recently implemented an activity-based costing system. It has determined the following costs...
Activity cost pool Machine setup Machine operation Inspections Esimated acivity costs $600,000 $500,000 $120.000 Estimated Allocation Base 12,000 setup hours 10,000 machine hours 2,000 inspections The following data is for the production of its U2 shafts during the month of January 300 $20,000 $10,000 Units produced Direct materials cost Direct labor cost Setup hours Machine hours Inspections Determine the amount of manufacturing overhead allocated. Round your answer to two decimal places O A. $1,080.00 O B. $160.00 O C. $3.60...
Two-Stage ABC for Manufacturing Detroit Foundry, a large manufacturer of heavy equipment components, has determined the following activity cost pools and cost driver levels for the year: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup $720,000 12,000 setup hours Material handling 120,000 3,000 material moves Machine operation 680,000 10,000 machine hours The following data are for the production of single batches of two products, C23 Cams and U2 Shafts during the month of August: C23 Cams U2 Shafts...
Two-Stage ABC for Manufacturing Detroit Foundry, a large manufacturer of heavy equipment components, has determined the following activity cost pools and cost driver levels for the year: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup $600,000 12,000 setup hours Material handling 120,000 2,000 material moves Machine operation 500,000 10,000 machine hours The following data are for the production of single batches of two products, C23 Cams and U2 Shafts during the month of August: C23 Cams U2 Shafts...
Two-Stage ABC for Manufacturing Detroit Foundry, a large manufacturer of heavy equipment components, has determined the following activity cost pools and cost driver levels for the year: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup $720,000 12,000 setup hours Material handling 120,000 3,000 material moves Machine operation 680,000 10,000 machine hours The following data are for the production of single batches of two products, C23 Cams and U2 Shafts during the month of August: C23 Cams U2 Shafts...
If you could please explain how you get the answers it would
really help me
E5-4B. Stage Two ABC for Manufacturing Detroit Foundry, a large manufacturer of heavy equipment components, has determined the following activity cost pools and cost driver levels for the year: LO2 Activity Cost Pool Activity Cost Activity Cost Driver Machine setup Materials handling Machine operation $720,000 120,000 12,000 setup hours 3,000 tons of materials 10,000 machine hours 680,000 The following data are for the production of...
CLICK HERE TO REVIEW LEARNING OBIECTIVES QUESTION 6 Not complete Marked out of 16.00 Flag question Two-Stage ABC for Manufacturing Detroit Foundry, a large manufacturer of heavy equipment components, has determined the following activity cost pools and cost driver levels for the year: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup Material handling Machine operation $624,000 12,000 setup hours 144,000 2,000 material moves 10,000 machine hours The following data are for the production of single batches of two...
Two-Stage ABC for Manufacturing Assume Sherwin-Williams Company, a large paint manufacturer, has determined the following activity cost pools and cost driver levels for the latest period: Activity Cost Pool Activity Cost Activity Cost Driver Machine setup $900,000 2,500 setup hours Material handling 820,000 4,000 material moves Machine operation 400,000 20,000 machine hours The following data are for the production of single batches of two products, Mirlite and Subdue: Mirlite Subdue Gallons produced 60,000 25,000 Direct labor hours 400 250 Machine...
Activity-Based Costing Slack Corporation has the following predicted indirect costs and cost drivers for 2019 for the given activity cost pools: Fabrication Department Finishing Department Maintenance. ... Materials handling Machine setups Inspections .. $ 20,000 30,000 70,000 $10,000 15,000 5,000 25,000 $55,000 Cost Driver Machine hours Material moves Machine setups Inspection hours $120,000 The following activity predictions were also made for the year: Fabrication Department Finishing Department Machine hours .. Materials moves.. Machine setups Inspection hours. 10,000 3,000 700 5,000...
EXPLAIN STEP BY STEP Traditional Product Costing versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing overhead cost for one of its plants to be $1,591,000, consisting of the following activity cost pools for the current month: Activity Centers Activity Costs Cost Drivers Activity Level Assembly setups $ 330,000 Setup hours 2,000 Materials handing 162,000 Number of moves 600 Assembly 900,000 Assembly hours 18,000 Maintenance 199,000 Maintenance hours 1,990 Total $1,591,000 Total direct labor hours used...
Churchill Products is considering updating its cost system to an activity-based costing system and is interested in understanding the effects. The company’s cost accountant has identified three overhead cost pools along with appropriate cost drivers for each pool. Cost Pools Costs Activity Drivers Utilities $ 320,000 64,000 machine-hours Scheduling and setup 310,000 620 setups Material handling 795,000 1,590,000 pounds of material The company manufactures three models of water basins (Oval, Round, and Square). The plans for production for the next...