(The three projects which are available are R ,F ,W
Benefit cost ratio = program Benefits/Program cost
if Benefit cost Ratio is greater than 1 , then that option is called feasibile option
Projects | Benefits | Cost | Benefit cost ratio |
R | 10 | 8 | 1.25 |
F | 13 | 10 | 1.3 |
W | 5 | 1 | 5 |
if road is made by spending $4 million and individual benfits to projects
projects | Benefits | Benefits of road | total | total cost | Benefit cost ratio |
R | 10 | 8 | 18 | 12 | 1.5 |
F | 13 | 5 | 18 | 14 | 1.28 |
w | 5 | -1 | 4 | 5 | 0.8 |
(a)if road is not bulit then all three projects are feasibile for company as the benefits are more than the cost in all the projects , the maximum benefit is generated from project W , second best is F and 3rd is R
And if road is built the maximum benfits which will genrating is Project R and project F
Project W cannot be considered if road is constructed.
(B)
Benefit cost ratio = program Benefits/Program cost
if Benefit cost Ratio is greater than 1 , then that opt
Projects | Benefits | Cost | Benefit cost ratio |
R | 10 | 8 | 1.25 |
F | 13 | 10 | 1.3 |
W | 5 | 1 | 5 |
project W Is the most Feasibile option
if road is made by spending $4 million and individual benfits to projects
projects | Benefits | Benefits of road | total | total cost | Benefit cost ratio |
R | 10 | 8 | 18 | 12 | 1.5 |
F | 13 | 5 | 18 | 14 | 1.28 |
w | 5 | -1 | 4 | 5 | 0.8 |
(C) if project is to be selected as per the Cba then Project W should we choosen as cost is just $1 Million and if road is build then also cost of project is least of W i.e 5 million
and as per Benefit cost ratio Project W , and if road is build then Project R
(D) if we have budget of 12 million as per Cba decisioon project that can be benefical will be project W & R which add total cost of 11 million
and if road is built then alternative which are available will Project W and other option which can be considered can be project R
Exercise 2: Choosing Among Projects (40 points) Three mutually exclusive projects are being considered for a...
The Ulmer Uranium Company has the opportunity to invest in one of two mutually exclusive projects. Project A costs $10 million and should project cash flows of $4 per year for 5 years. Project B costs $15 million and should produce cash flows of $3.5 million for 10 years. The cost of capital is 10%. Which of these two projects should be selected? Show any calculations needed to support your answer.
Question is above picture.
5. Assume the seven projects were not mutually exclusive and you
were faced with a budget constraint that allowed you to pick only
two. Which two projects would appear at the top of your preferred
list? Why?
5 5 + - E New tab → 0 Career: D O Course R HW 1 X Syllabus GOECD ILI GOECD iLit Field Cha Online Bc C Three ML c Get Hom 0 file:///C:/Users/bwjon/AppData/Local/Packages/Microsoft. MicrosoftEdge_3wekyb3d8bbwe/Tempstate/Downloads/HW%201%20APEC%205950%20(3).pdf ☆ B ... Find...
4. Project Selection 20 points) Three mutually exclusive projects are being considered. The cash flows for each project are shown below. Use an MARR of 12% per year. Which of the three alternatives, if any, should be chosen? Why? State any assumptions required. 17.000 First cost, $ Annual revenue, $/yr Salvage value, $ Useful life, yr 12.000 6,000 4,000 26,200 8,200 4,500 4,500 5,200 3 6 4
Three mutually exclusive projects are being considered: A B C Initial cost $100 $150 $200 Annual benefit $10 $17.62 $55.48 Useful life. infinite 20 years 5 years Construct a choice table for interest rates from 0%-100%. Also – provide a plot of either PW or EAW as a function of i. b. The firm wants 8% rate of return on investments. Which equipment should be purchased?
Need cash flow diagram
04) Three mutually exclusive alternative are being considered Initial Cost Benefit at the end of the first Year Uniform Annual Benefits at end of subsequent years Useful Life in years $500 $200 $100 $400 $200 $125 $300 $200 $100 At the end of its useful life, an alternative is not replaced. If MARR is 10%, which alternatives should be selected? a) Based on the payback period? b) Based on benefit-cost ratio analysis c) Benefit/Costs Analysis using...
10 points QUESTION 10 Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) -$27,476 9,057 10,536 11,849 13,814 -$318,844 0 1 27,700 56,000 55,000 399,000 4 The required return is 15 percent for both projects. Which one of the following statements related to these projects is correct? 1.The IRR decision rule should be used as the basis for selecting the project in this situation 2. The profitability rule implies accepting Project A. 3. Only NPV...
Question 14 (2 points) 1. Two projects being considered are mutually exclusive and have the following cash flows: Year Project A Project B 0 -$50,000 -$50,000 15,000 0 2 15,000 0 3 15,000 0 4 15,000 5 15,000 99,000 1 0 If the required rate of return on these projects is 10 percent, which would be chosen and why?
Choosing Between two Mutually Exclusive Projects Question 2: A company can cither invest in project A, project B, or neither (the projects are mutually exclusive and the company has no other investment options). Project A requires an initial investment of $1,000,000 and provides cash flows of $300,000 a year for six years. The project will also return $200,000 in capital back to the company in year six. Project B requires a $375,000 investment and will have cash flows of $200,000...
Question 2. (18 points) Three mutually exclusive alternative publ respective costs and benefits are included in the following table. Each of the se PW for vow years, and MARR is 15% per year, which, if any, of these projects shou lic-works projects are currently under useful life oft v0 d be selected? Use PW for YOUr calculations. You can use either B-C method. $10,500,000 $13,000,000$9,500,000 650,000 Annual Operating and Maintenance Costs Market Value 750,000 625,000 2,000,000 | 1,750,000 | 1,250,000...
2 Piercy, LLC, has identified the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) -$ 77.500 43,000 29,000 23,000 21,000 -$ 77.500 10 points 21,500 28,000 34,000 41,000 2 00.25.04 4 eBook a-1. What is the IRR for each of these projects? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) a-2.If you apply the IRR decision rule. which project should the company accept? b-1. Assume...