First we need to calculate the labour hours that are expected in the coming year. Than only we will be able to calculate the Overhead rate per direct labour hour.
Since the total cost that is estimated for the direct labour is $240828
And the rate of direct labour is $12.81
The direct labour hour can be calculated as 240828/12.81
This means a total of 18,800 hours of direct labour.
#1
Now we need to calculate the total cost and then we need to divide this cost in the total expected hours.
So the cost that will be included is
Factory machinery depreciation + Factory supervisor salaries + Factory supplies + Factory property tax
59500+141000+42900+30250
=273650
So Pre-determined overhead rate can be calculated as = cost/labour hours
273650/18800
=14.55
#2
The applied overhead rate will be calculated as per the hours that are expected to work in the coming year.
Since the hours that are 18800 and the rate is 14.55 we get the applied overhead rate that is
18800*14.55
=273540
1.66 points E2-5 Calculating Predetermined Overhead Rate and Applied Overhead [LO 2-3] Bike Company manufactures oustom...
E2-5 (Algo) Calculating Predetermined Overhead Rate and Applied Overhead [LO 2-3) Wheeler's Bike Company manufactures custom racing bicycles. The company uses a job order cost system to determine the cost of each bike. Estimated costs and expenses for the coming year follow: Bike parts Factory machinery depreciation Factory supervisor salaries Factory direct labor Factory supplies Factory property tax Advertising cost Administrative salaries Administrative-related depreciation Total expected costs $341,800 57,000 134,500 207,819 39,400 33,250 20,000 50,500 19,700 $983,969 Required: 1. Calculate...
E2-5 (Algo) Calculating Predetermined Overhead Rate and Applied Overhead [LO 2-3) Wheeler's Bike Company manufactures custom racing bicycles. The company uses a job order cost system to determine the cost of each bike. Estimated costs and expenses for the coming year follow: Bike parts Factory machinery depreciation Factory supervisor salaries Pactory direct labor Factory supplies Factory property tax Advertising cost Administrative salaries Administrative related depreciation Total expected costs $352,800 61,000 143,000 216,635 44,400 30,750 27,500 52,500 24,200 $952,785 es Required:...
d Assignment E2-5 (Algo) Calculating Predetermined Overhead Rate and Applied Overhead [LO 2-3) Wheeler's Bike Company manufactures custom racing bicycles. The company uses a job order cost system to determine the cost of each bike. Estimated costs and expenses for the coming year follow. $340, 62, 14e 50 234 549 Bike parte Factory machinery depreciation Factory Supervisor salaries Factory direct labor Factory supplies Factory property tax Advertising cost Adsinstrative salaries Administrative-related depreciation Total expected costs 343,699 Required: 1. Calculate the...
COMPE2-5 1 whelp Save E2-5 (Algo) Calculating Predetermined Overhead Rate and Applied Overhead (LO 2-3) Wheeler's Bike Company manufactures custom racing bicycles. The company uses a job order cost system to determine the cost of each bike. Estimated costs and expenses for the coming year follow: $340, Bee 53. see Skipped 199,123 Elke parts Factory machinery depreciation Factory supervisor salaries Factory direct labor Factory supplies Factory property tax Advertising cost Administrative salaries Administrative-related depreciation Total expected costs 25, see eBook...
Wheeler's Bike Company manufactures custom racing bicycles. The company uses a job order cost system to determine the cost of each bike. Estimated costs and expenses for the coming year follow: Bike parts Factory machinery depreciation Factory supervisor salaries Factory direct labor Factory supplies Factory property tax Advertising cost Administrative salaries Administrative-related depreciation Total expected costs $ 350,800 61,000 143,500 228,966 43,400 30, 750 26,000 50,000 24,700 $959, 116 Required: 1. Calculate the predetermined overhead rate per direct labor hour...
Wheeler's Bike Company manufactures custom racing bicycles. The company uses a job order cost system to determine the cost of each bike. Estimated costs and expenses for the coming year follow: Bike parts Factory machinery depreciation Factory supervisor salaries Factory direct labor $345,800 61,000 143,000 232,380 41,400 32,750 Factory supplies Factory property tax Advertising cost 22,000 52,500 18,700 Administrative salaries Administrative-related depreciation $949,530 Total expected costs Required: 1. Calculate the predetermined overhead rate per direct labor hour if the average...
Wheeler's Bike Company manufactures custom racing bicycles. The company uses a job order cost system to detemine the cost of each bike. Estimated costs and expenses for the coming year follow: $355,800 Bike parts Factory machinery depreciation Factory supervisor salaries Factory direct labor Factory supplies Factory property tax Advertising cost Administrative salaries Administrative-related depreciation Total expected costs 53,500 142,500 225,456 45.400 24,750 21,500 55,000 24,200 $948,106 Required: 1. Calculate the predetermined overhead rate per direct labor hour if the average...
Wheeler's Bike Company manufactures custom racing bicycles. The company uses a job order cost system to determine the cost of each bike. Estimated costs and expenses for the coming year follow Bike parts Factory machinery depreciation Factory supervisor salaries Factory direct labor Factory supplies Factory property tax Advertising cost Administrative salaries Administrative-related depreciation Total expected costs 350,800 55,000 136,500 211,951 41,400 25,750 26,000 51,500 $922,601 Required 1. Calculate the predetermined overhead rate per direct labor hour if the average direct...
Wheeler's Bike Company manufactures custom racing bicycles. The company uses a job order cost system to determine the cost of each bike. Estimated costs and expenses for the coming year follow: Bike parts Factory machinery depreciation Factory supervisor salaries Factory direct labor Factory supplies Factory property tax Advertising cost Administrative salaries Administrative-related depreciation Total expected costs $342,800 58,000 143,000 236, 253 42,900 26,250 19,500 54,000 20, 200 $942,903 Required: 1. Calculate the predetermined overhead rate per direct labor hour if...
Wheeler’s Bike Company manufactures custom racing bicycles. The company uses a job order cost system to determine the cost of each bike. Estimated costs and expenses for the coming year follow: Bike parts $ 351,800 Factory machinery depreciation 54,500 Factory supervisor salaries 139,500 Factory direct labor 238,266 Factory supplies 38,900 Factory property tax 28,750 Advertising cost 22,500 Administrative salaries 47,000 Administrative-related depreciation 18,700 Total expected costs $ 939,916 Required: 1. Calculate the predetermined overhead rate per direct labor hour if...