Please refer to below spreadsheet for calculation and answer. Cell reference also provided.
Cell reference -
Hope this will help, please do comment if you need any further explanation. Your feedback would be highly appreciated.
You are considering the following two projects and can take only one. Your cost of capital...
You are considering the following two projects and can take only one. Your cost of capital is 11.0 %. The cash flows for the two projects are as follows (S million): Year 3 $40 $30 Year 0 -$100 -$100 Project Year 2 Year 4 Year 1 $50 $25 $50 $30 $40 $20 1,42 B a. What is the IRR of each project? b. What is the NPV of each project at your cost of capital? c. At what cost of...
You are considering the following two projects and can take only one. Your cost of capital is 11.2%. The cash flows for the two projects are as follows ($ million): Project Year 0 - $101 - $101 Year 1 $22 $52 Year 2 $29 $40 Year 3 $40 $29 Year 4 $52 $18 a. What is the IRR of each project? b. What is the NPV of each project at your cost of capital? c. At what cost of capital...
Problem 8-27 (bookmatch) Question Help O You are considering the following two projects and can take only one. Your cost of capital is 11.0%. The cash flows for the two projects are as follows ($ million): Project Year 1 Year 0 - $100 - $100 $25 $50 Year 2 $30 $40 $30 Year 3 $40 $30 Year 4 $50 $20 a. What is the IRR of each project? b. What is the NPV of each project at your cost of...
You are considering the following two projects and can take only one. Your cost of capital is 11.4%. The cash flows for the two projects are as follows ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$98 $27 $29 $38 $51 B −$98 $51 $38 $29 $18 a. What is the IRR of each project? b. What is the NPV of each project at your cost of capital? c. At what cost of capital...
You are considering the following two projects and can only take one. Your cost of capital is 11.4 %. The cash flows for the two projects are as follows ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$102 $27 $31 $39 $49 B −$102 $49 $39 $31 $20 a. What is the IRR of each project? b. What is the NPV of each project at your cost of capital? c. At what cost of...
You are considering the projects below and can take only one. Your cost of capital is 11%. Complete the steps below using cell references to given data or previous calculations. In some cases, a simple cell reference is all you need. To copy/paste a formula across a row or down a column, an absolute cell reference or a mixed cell reference may be preferred. If a specific Excel function is to be used, the directions will specify the use of...
P 8-30 (similar to) Question Help You are considering the following two projects and can take only one. Your cost of capital is 11.3%. The cash flows for the two projects are as follows (S milion) Project Year 0 Year 1 $22 Year 2 Year 3 Year 4 $99 $99 $52 $30 $41 $41 $30 B $52 S21 a. What is the IRR of each project? b. What is the NPV of each project at your cost of capital? c....
5) You are choosing between two projects, but can only take one. The cash flows for the projects are given in the following table: 0 1 2 3 4 A -50 25 20 20 15 B -100 20 40 50 60 a. What are the IRRs of the two projects? Use an excel spread sheet b. If your discount rate is 5%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects...
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACCC is 9 %. 0 1 2 4 Project A...
14) Cedric is considering between two mutually exclusive projects. The following table gives the cash flows of each project: 0 1 2 3 4 A -$50 25 20 20 15 B -$100 20 40 50 60 a. If your discount rate is 6%, what are the NPVs of the two projects? b. What are the IRRs of the two projects? c. Why do IRR and NPV rank the two projects differently? NPV IRR