Question

Required Information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer

  • Requirement 5

2021

2022

2023

Revenue

$                3,000,000.00

$               3,078,799.00

$                    3,921,201.00

Gross Profit (Loss)

$                   360,000.00

$             (1,020,000.00)

$                        160,000.00

  • Workings

Working

2021

2022

2023

A

Contract Price

$             10,000,000.00

$             10,000,000.00

$                  10,000,000.00

B

Cost Incurred to Date

$                2,640,000.00

$               6,480,000.00

$                  10,500,000.00

C

Estimated cost yet to be incurred to complete the contract

$                6,160,000.00

$               4,180,000.00

$                                         -  

D = B+C

Total Cost

$                8,800,000.00

$             10,660,000.00

$                  10,500,000.00

E = (B/D) x 100

% of Completion

30.00%

60.79%

100.00%

F = A x E

Revenue to date

$                3,000,000.00

$               6,078,799.25

$                  10,000,000.00

G

Revenue of Previous year

$                                     -  

$               3,000,000.00

$                    6,078,799.25

H = F - G

Net Revenue this year

$                3,000,000.00

$               3,078,799.25

$                    3,921,200.75

I (=B)

Cost to date

$                2,640,000.00

$               6,480,000.00

$                  10,500,000.00

J

Cost to date of previous year

$                                     -  

$               2,640,000.00

$                    6,480,000.00

K = I - J

Net Cost for the year

$                2,640,000.00

$               3,840,000.00

$                    4,020,000.00

L = A - D

Estimated Gross Profit (Loss)

$                1,200,000.00

$                 (660,000.00)

$                     (500,000.00)

M

Gross Profit (Loss) to be recognised

$                   360,000.00

$             (1,020,000.00)

$                        160,000.00

Add a comment
Know the answer?
Add Answer to:
Required Information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,640,000 $ 2,300,000 $ 2,926,000 Estimated costs to complete as of year-end 6,160,000 2,660,000 0 Billings during the year 2,080,000 2,860,000 5,060,000 Cash collections during the year 1,840,000 2,800,000 5,360,000 Westgate recognizes revenue over time according to...

  • ! 9 Required information [The following information applies to the questions displayed below.) Part 5 of...

    ! 9 Required information [The following information applies to the questions displayed below.) Part 5 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,926,000 10 points Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000...

  • 8 Required information (The following information applies to the questions displayed below.) Part 4 of 5...

    8 Required information (The following information applies to the questions displayed below.) Part 4 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 10 points Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000 1,840,000 2022 $2,300,000...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,640,000 $ 2,300,000 $ 2,926,000 Estimated costs to complete as of year-end 6,160,000 2,660,000 0 Billings during the year 2,080,000 2,860,000 5,060,000 Cash collections during the year 1,840,000 2,800,000 5,360,000 Westgate recognizes revenue over time according to...

  • 5 Required information (The following information applies to the questions displayed below.) Part 1 of 5...

    5 Required information (The following information applies to the questions displayed below.) Part 1 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: - 2023 $2,926,000 10 points Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,926,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000 1,840,000 2022 $2,300,000 2,660,000 2,860,000 2,800,000 5,060,000 5,360,000 Westgate recognizes revenue over time according to percentage of completion. Problem...

  • ! 7 Required information [The following information applies to the questions displayed below.] Part 3 of...

    ! 7 Required information [The following information applies to the questions displayed below.] Part 3 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 10 points Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000 1,840,000 2022...

  • Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9] (The following information...

    Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9] (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT