Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9] (The following inform

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Percentage Completion Method
Particulars 2021 2022 2023
Cost incurred till previous year 0 2640000 6480000
Add:Cost incurred during the year 2640000 3840000 4020000
Total cost incurred till date 2640000 6480000 10500000
Add: Estimated cost to be incurred 6160000 4180000 0
Total estimated cost to be incurred 8800000 10660000 10500000
Percentage of completion (A) 30% 60.79% 100%
(Cost incurred till date /Total estimated cost )
Total revenue (B) 10000000 10000000 10000000
Total revenue recognized (A *B) 3000000 6078799 10000000
Less:Revenue recognized in previous year 0 3000000 6078799
Revenue recognized in current year 3000000 3078799 3921201

Calculation of amount of Revenue and Gross Profit to be recognized in each of the years:

Particulars 2021 2022 2023
Revenue 3000000 3078799 3921201
Less:Cost incurred 2640000 3840000 4020000
Gross profit 360000 -761201 -98799
Add a comment
Know the answer?
Add Answer to:
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9] (The following information...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9) [The following information...

    Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9) [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000...

  • Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9] The following information...

    Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9] The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $ 2,640,000...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,640,000 $ 2,300,000 $ 2,926,000 Estimated costs to complete as of year-end 6,160,000 2,660,000 0 Billings during the year 2,080,000 2,860,000 5,060,000 Cash collections during the year 1,840,000 2,800,000 5,360,000 Westgate recognizes revenue over time according to...

  • ! 9 Required information [The following information applies to the questions displayed below.) Part 5 of...

    ! 9 Required information [The following information applies to the questions displayed below.) Part 5 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,926,000 10 points Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,640,000 $ 2,300,000 $ 2,926,000 Estimated costs to complete as of year-end 6,160,000 2,660,000 0 Billings during the year 2,080,000 2,860,000 5,060,000 Cash collections during the year 1,840,000 2,800,000 5,360,000 Westgate recognizes revenue over time according to...

  • 8 Required information (The following information applies to the questions displayed below.) Part 4 of 5...

    8 Required information (The following information applies to the questions displayed below.) Part 4 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 10 points Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000 1,840,000 2022 $2,300,000...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,926,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000 1,840,000 2022 $2,300,000 2,660,000 2,860,000 2,800,000 5,060,000 5,360,000 Westgate recognizes revenue over time according to percentage of completion. Problem...

  • Required Information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction...

    Required Information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year- end Billings during the year Cash collections during the year 2021 $2, 640,000 6,160,000 2,080,000 1, 840,000 2022 $2,300,000 2,660,000 2,860,000 2,800,000 2023...

  • 5 Required information (The following information applies to the questions displayed below.) Part 1 of 5...

    5 Required information (The following information applies to the questions displayed below.) Part 1 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: - 2023 $2,926,000 10 points Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000...

  • Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9) The followi...

    Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9) The following information applies to the questions displayed below) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $1,870,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT