Percentage Completion Method | |||
Particulars | 2021 | 2022 | 2023 |
Cost incurred till previous year | 0 | 2640000 | 6480000 |
Add:Cost incurred during the year | 2640000 | 3840000 | 4020000 |
Total cost incurred till date | 2640000 | 6480000 | 10500000 |
Add: Estimated cost to be incurred | 6160000 | 4180000 | 0 |
Total estimated cost to be incurred | 8800000 | 10660000 | 10500000 |
Percentage of completion (A) | 30% | 60.79% | 100% |
(Cost incurred till date /Total estimated cost ) | |||
Total revenue (B) | 10000000 | 10000000 | 10000000 |
Total revenue recognized (A *B) | 3000000 | 6078799 | 10000000 |
Less:Revenue recognized in previous year | 0 | 3000000 | 6078799 |
Revenue recognized in current year | 3000000 | 3078799 | 3921201 |
Calculation of amount of Revenue and Gross Profit to be recognized in each of the years:
Particulars | 2021 | 2022 | 2023 |
Revenue | 3000000 | 3078799 | 3921201 |
Less:Cost incurred | 2640000 | 3840000 | 4020000 |
Gross profit | 360000 | -761201 | -98799 |
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9] (The following information...
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9) [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000...
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9] The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $ 2,640,000...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,640,000 $ 2,300,000 $ 2,926,000 Estimated costs to complete as of year-end 6,160,000 2,660,000 0 Billings during the year 2,080,000 2,860,000 5,060,000 Cash collections during the year 1,840,000 2,800,000 5,360,000 Westgate recognizes revenue over time according to...
! 9 Required information [The following information applies to the questions displayed below.) Part 5 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,926,000 10 points Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,640,000 $ 2,300,000 $ 2,926,000 Estimated costs to complete as of year-end 6,160,000 2,660,000 0 Billings during the year 2,080,000 2,860,000 5,060,000 Cash collections during the year 1,840,000 2,800,000 5,360,000 Westgate recognizes revenue over time according to...
8 Required information (The following information applies to the questions displayed below.) Part 4 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 10 points Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000 1,840,000 2022 $2,300,000...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,926,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000 1,840,000 2022 $2,300,000 2,660,000 2,860,000 2,800,000 5,060,000 5,360,000 Westgate recognizes revenue over time according to percentage of completion. Problem...
Required Information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year- end Billings during the year Cash collections during the year 2021 $2, 640,000 6,160,000 2,080,000 1, 840,000 2022 $2,300,000 2,660,000 2,860,000 2,800,000 2023...
5 Required information (The following information applies to the questions displayed below.) Part 1 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: - 2023 $2,926,000 10 points Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000...
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9) The following information applies to the questions displayed below) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $1,870,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021...