Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $285,000, and budgeted direct labor hours were 19,000. The average wage rate for direct labor is expected to be $30 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $24,900 $35,800 $19,400 $1,000 Materials requisitioned 19,300 23,400 10,300 14,800 Direct labor cost 10,400 20,500 4,950 5,700 Overhead is assigned as a percentage of direct labor cost. During June, Jobs 39 and 40 were completed; Job 39 was sold at 110 percent of cost. (Naranjo had originally developed Job 40 to order for a customer; however, that customer was near bankruptcy and the chance of Naranjo being paid was growing dimmer. Naranjo decided to hold Job 40 in inventory while the customer worked out its financial difficulties. Job 40 is the only job in Finished Goods Inventory.) Jobs 41 and 42 remain unfinished at the end of the month. Required: 1. Calculate the balance in Work in Process as of June 30. $ 2. Calculate the balance in Finished Goods as of June 30. $ 3. Calculate the cost of goods sold for June. $ 4. Calculate the price charged for Job 39. Round your answer to the nearest cent. $ 5. What if the customer for Job 40 was able to pay for the job by June 30? What would happen to the balance in Finished Goods? What would happen to the balance of Cost of Goods Sold?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Givey - Budgeled oveheall Budgeled Labour for Hour the year 8 2850oo. 14000 hours. Average wage late – $301 hour. Cost sweetBalance in finisheel Goods Job yo is finished and Remmin Hence Balance in finished Good Job yoz 889950 - unsold. Si Cost of G

Add a comment
Know the answer?
Add Answer to:
Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $180,000, and budgeted direct labor hours were 18,000. The average wage rate for direct labor is expected to be $20 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $26,600 $34,200 $15,600 $1,700 Materials requisitioned 16,700 23,400 10,800 12,100 Direct labor...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $260,000, and budgeted direct labor hours were 20,000. The average wage rate for direct labor is expected to be $25 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $23,700 $34,600 $17,000 $0 Materials requisitioned 18,900 21,400 8,350 12,000 Direct labor...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $287,500, and budgeted direct labor hours were 23,000. The average wage rate for direct labor is expected to be $25 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $26,100 $32,800 $18,500 $900 Materials requisitioned 16,000 23,000 10,900 12,500 Direct labor...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $260,000, and budgeted direct labor hours were 20,000. The average wage rate for direct labor is expected to be $25 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $23,700 $34,600 $17,000 $0 12,000 Materials requisitioned 8,350 18,900 10,000 21,400 18,000...

  • Job Casts Using a Plantwide Overhead Rate Naranjo Company designs Industrial prototypes for outside companies. Budgeted...

    Job Casts Using a Plantwide Overhead Rate Naranjo Company designs Industrial prototypes for outside companies. Budgeted overhead for the year was $262,500, and budgeted direct labor hours were 21,000. The average wage rate for direct labor is expected to be $25 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $26,200 $34,500 $15,700 $400 Materials requisitioned 16,100 22,600 12,300 15,800 Direct labor...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $280,000, and budgeted direct labor hours were 16,000. The average wage rate for direct labor is expected to be $35 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $22,700 $35,500 $15,800 $1,700 Materials requisitioned 20,100 21,000 10,300 15,600 Direct labor...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $390,000, and budgeted direct labor hours were 26,000. The average wage rate for direct labor is expected to be $30 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $23,300 $34,800 $19,700 $500 Materials requisitioned 19,800 20,400 10,600 12,600 Direct labor...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $360,000, and budgeted direct labor hours were 24,000. The average wage rate for direct labor is expected to be $30 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $25,500 $32,900 $16,800 $1,400 Materials requisitioned 19,400 23,400 8,700 15,700 Direct labor...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $367,500, and budgeted direct labor hours were 21,000. The average wage rate for direct labor is expected to be $35 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $25,300 $34,300 $15,500 $1,100 Materials requisitioned 20,100 23,800 8,300 12,400 Direct labor...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $385,000, and budgeted direct labor hours were 22,000. The average wage rate for direct labor is expected to be $35 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $26,200 $36,000 $15,900 $1,200 Materials requisitioned 16,600 21,400 8,700 14,400 Direct labor...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT