Question

Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $180,000, and budgeted direct labor hours were 18,000. The average wage rate for direct labor is expected to be $20 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $26,600 $34,200 $15,600 $1,700 Materials requisitioned 16,700 23,400 10,800 12,100 Direct labor cost 7,800 20,500 5,450 3,000 Overhead is assigned as a percentage of direct labor cost. During June, Jobs 39 and 40 were completed; Job 39 was sold at 115 percent of cost. (Naranjo had originally developed Job 40 to order for a customer; however, that customer was near bankruptcy and the chance of Naranjo being paid was growing dimmer. Naranjo decided to hold Job 40 in inventory while the customer worked out its financial difficulties. Job 40 is the only job in Finished Goods Inventory.) Jobs 41 and 42 remain unfinished at the end of the month.

Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overh

0 0
Add a comment Improve this question Transcribed image text
Answer #1
1 Balance in Work in process as of June 30            [Refer working note 2] $52,875
2 Balance in Finished goods as of June 30              [Refer working note 3] $88,350
3 Cost of goods sold for June 30                             [Refer working note 4] $55,000
4 Price charged for Job 39                                      [Refer working note 5] $63,250
5 Finished goods would decrease
Cost of goods sold would increase

.

.

Working note 1 - Calcualation of Overhead rate
Estimated overhead Cost    $180,000
Estimated labor cost [Estimated labor hours x Wage rate = 18,000 hours x $20 per hour] $360,000
Overhead Rate          [(Estimated overhead Cost / Estimated labor cost ) x 100 = ($180,000 / $360,000) x 100    50%

.

.

Working note 2 - Calculation of Balance in Work in process as of June 30
Total cost incurred for Job 41 until June 30             [Refer working note 6] $34,575
Total cost incurred for Job 42 until June 30              [Refer working note 6] $18,300
Work in process                                                         [34,575 + $18,300] $52,875

.

.

Working note 3 - Calculation of Balance in Finished goods as of June 30
The only job that is completed and unsold at June 30 is Job 40
Total cost incurred for Job 40                [Refer working note 6] $88,350

.

.

Working note 4 - Calculation of Cost of goods sold for June 30
The only job that is completed and sold in June is Job 39
Total cost incurred for Job 39                [Refer working note 6] $55,000

.

.

Working note 5 - Calculation of Price charged for Job 39
Total cost incurred for Job 39      [Refer working note 6] $55,000
Price charged for Job 39              [Total cost incurred for Job 39 x 115% = $55,000 x 115%]

$63,250

.

.

Working note 6 - Calculation of total cost incurred for each job
` Job 39 Job 40 Job 41 Job 42
Beginning balance (a) $26,600 $34,200 $15,600 $1,700
Manufacturing costs incurred during June:
   Materials requisitioned (b) $16,700 $23,400 $10,800 $12,100
   Direct labor labor (c) $7,800 $20,500 $5,450 $3,000
   Overhead applied      [Direct labor cost x Overhead rate]          (d)

$3,900.

[$7,800 x 50%]

$10,250

[$20,500 x 50%]

$2,725

[$5,450 x 50%]

$1,500

[$12,100 x 50%]

   Total manufacturing costs incurred during June           (e = b + c + d)    $28,400 $54,150 $18,975 $16,600
Total cost incurred                                                          (a + e) $55,000 $88,350 $34,575 $18,300
Add a comment
Know the answer?
Add Answer to:
Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $280,000, and budgeted direct labor hours were 16,000. The average wage rate for direct labor is expected to be $35 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $22,700 $35,500 $15,800 $1,700 Materials requisitioned 20,100 21,000 10,300 15,600 Direct labor...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $260,000, and budgeted direct labor hours were 20,000. The average wage rate for direct labor is expected to be $25 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $23,700 $34,600 $17,000 $0 Materials requisitioned 18,900 21,400 8,350 12,000 Direct labor...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $287,500, and budgeted direct labor hours were 23,000. The average wage rate for direct labor is expected to be $25 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $26,100 $32,800 $18,500 $900 Materials requisitioned 16,000 23,000 10,900 12,500 Direct labor...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $285,000, and budgeted direct labor hours were 19,000. The average wage rate for direct labor is expected to be $30 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $24,900 $35,800 $19,400 $1,000 Materials requisitioned 19,300 23,400 10,300 14,800 Direct labor...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $260,000, and budgeted direct labor hours were 20,000. The average wage rate for direct labor is expected to be $25 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $23,700 $34,600 $17,000 $0 12,000 Materials requisitioned 8,350 18,900 10,000 21,400 18,000...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $390,000, and budgeted direct labor hours were 26,000. The average wage rate for direct labor is expected to be $30 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $23,300 $34,800 $19,700 $500 Materials requisitioned 19,800 20,400 10,600 12,600 Direct labor...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $367,500, and budgeted direct labor hours were 21,000. The average wage rate for direct labor is expected to be $35 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $25,300 $34,300 $15,500 $1,100 Materials requisitioned 20,100 23,800 8,300 12,400 Direct labor...

  • Job Casts Using a Plantwide Overhead Rate Naranjo Company designs Industrial prototypes for outside companies. Budgeted...

    Job Casts Using a Plantwide Overhead Rate Naranjo Company designs Industrial prototypes for outside companies. Budgeted overhead for the year was $262,500, and budgeted direct labor hours were 21,000. The average wage rate for direct labor is expected to be $25 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $26,200 $34,500 $15,700 $400 Materials requisitioned 16,100 22,600 12,300 15,800 Direct labor...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $360,000, and budgeted direct labor hours were 24,000. The average wage rate for direct labor is expected to be $30 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $25,500 $32,900 $16,800 $1,400 Materials requisitioned 19,400 23,400 8,700 15,700 Direct labor...

  • Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

    Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $385,000, and budgeted direct labor hours were 22,000. The average wage rate for direct labor is expected to be $35 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $26,200 $36,000 $15,900 $1,200 Materials requisitioned 16,600 21,400 8,700 14,400 Direct labor...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT