Grant Co. uses the following standard to produce a single unit of its product: Variable overhead (1.30 hrs. per unit @ $3.60/hr.) Actual data for the month show total variable overhead costs of $116,340, and 23,000 units produced. The total variable overhead variance is:
Multiple Choice
$8,700F.
$8,700U.
$58,415U.
$58,415F.
$0
Total Variable overhead variance
= Standard voh - Actual voh
= (1.30*3.60*23,000) - 116,340
= 107,640 - 116,340
= 8700 U
Grant Co. uses the following standard to produce a single unit of its product: Variable overhead...
Regent, Inc. uses the following standard to produce a single unit of its product: overhead $6 (2 hrs. @ $3/hr.). The flexible budget for overhead is $160,000 plus $1.00 per direct labor hour. Actual data for the month show overhead costs of $277,000, and 35,000 units produced. The overhead volume variance is: Multiple Choice $87,000 favorable. $60,000 favorable. $20,000 unfavorable. $80,000 unfavorable. $10,000 unfavorable
Trico Company set the following standard unit costs for its single product. Direct materials (29 Ibs. @ $3 per Ib.) $ 87.00 Direct labor (6 hrs. @ $6 per hr.) 36.00 Factory overhead—variable (6 hrs. @ $4 per hr.) 24.00 Factory overhead—fixed (6 hrs. @ $5 per hr.) 30.00 Total standard cost $ 177.00 The predetermined overhead rate is based on a planned operating volume of 70% of the productive capacity of 60,000 units per quarter. The...
PLease answer all queations ASAP! wil rate 1. Georgia, Inc. has collected the following data on one of its products. The actual cost of the direct materials used is: Direct materials standard (3 lbs @ $2/lb) $6 per finished unit Total direct materials cost variance—unfavorable $14,250 Actual direct materials used 100,000 lbs. Actual finished units produced 25,000 units Multiple Choice $135,750. $164,250. $150,000. $182,000. $100,000. 2. Use the following data to find the total direct labor cost variance if the...
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) Direct labor (8 hrs. @ $16 per hr.) Factory overhead-variable (8 hrs. @ $9 per hr.) Factory overhead-fixed (8 hrs. @ $12 per hr.) Total standard cost $144.00 128.00 72.00 96.00 $440.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 59.000 units per quarter. The following flexible budget information is...
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) Direct labor (7 hrs. @ $14 per hr.) Factory overhead-Variable (7 hrs. @ $6 per hr.) Factory overhead-Fixed (7 hrs. @ $9 per hr.) Total standard cost $144.00 98.00 42.00 63.00 $347.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 67,000 units per quarter. The following flexible budget information is...
Trico Company set the following standard unit costs for its single product. Direct materials (30 lbs. @ $4 per Ib.) Direct labor (5 hrs. @ $14 per hr.) Factory overhead-variable (5 hrs. @ $8 per hr.) Factory overhead-fixed (5 hrs. @ $10 per hr.) Total standard cost $120.00 70.00 40.00 50.00 $280.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 60,000 units per quarter. The following flexible budget information is...
Trico Company set the following standard unit costs for its single product Direct naterials (30 Ibe. e$5.10 per Ib.) Direct labor (6 hrs. $15 per hr.) Factory overhead-variable (6 hrs. e $7 per hr. Factory overhead-fixed (6 hrs. e $11 per hr.) $153.00 90.00 42.00 66.00 $351.00 Total standard cost The predetermined overhead rate is based on a planned operating volume of 80 % of the productive capecity of 56,000 units per quarter. The following flexible budget information is available...
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.10 per Ib.) Direct labor (8 hrs. @ $15 per hr.) Factory overhead-Variable (8 hrs. @ $6 per hr.) Factory overhead-Fixed (8 hrs. @ $9 per hr.) Total standard cost $ 153.00 120.00 48.00 72.00 $ 393.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 65,000 units per quarter. The following flexible budget...
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) $ 144.00 Direct labor (6 hrs. @ $14 per hr.) 84.00 Factory overhead—variable (6 hrs. @ $7 per hr.) 42.00 Factory overhead—fixed (6 hrs. @ $9 per hr.) 54.00 Total standard cost $ 324.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 57,000 units per quarter. The following flexible budget...
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) $ 144.00 Direct labor (7 hrs. @ $14 per hr.) 98.00 Factory overhead—variable (7 hrs. @ $6 per hr.) 42.00 Factory overhead—fixed (7 hrs. @ $9 per hr.) 63.00 Total standard cost $ 347.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 64,000 units per quarter. The following flexible budget...