Total Variable overhead variance

= Standard voh - Actual voh

= (1.30*3.60*23,000) - 116,340

= 107,640 - 116,340

= 8700 U

Add a comment
Know the answer?
Add Answer to:
Grant Co. uses the following standard to produce a single unit of its product: Variable overhead...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Regent, Inc. uses the following standard to produce a single unit of its product: overhead $6...

    Regent, Inc. uses the following standard to produce a single unit of its product: overhead $6 (2 hrs. @ $3/hr.). The flexible budget for overhead is $160,000 plus $1.00 per direct labor hour. Actual data for the month show overhead costs of $277,000, and 35,000 units produced. The overhead volume variance is: Multiple Choice $87,000 favorable. $60,000 favorable. $20,000 unfavorable. $80,000 unfavorable. $10,000 unfavorable

  • Trico Company set the following standard unit costs for its single product.      Direct materials (29...

    Trico Company set the following standard unit costs for its single product.      Direct materials (29 Ibs. @ $3 per Ib.) $ 87.00   Direct labor (6 hrs. @ $6 per hr.) 36.00   Factory overhead—variable (6 hrs. @ $4 per hr.) 24.00   Factory overhead—fixed (6 hrs. @ $5 per hr.) 30.00      Total standard cost $ 177.00    The predetermined overhead rate is based on a planned operating volume of 70% of the productive capacity of 60,000 units per quarter. The...

  • PLease answer all queations ASAP! wil rate 1. Georgia, Inc. has collected the following data on...

    PLease answer all queations ASAP! wil rate 1. Georgia, Inc. has collected the following data on one of its products. The actual cost of the direct materials used is: Direct materials standard (3 lbs @ $2/lb) $6 per finished unit Total direct materials cost variance—unfavorable $14,250 Actual direct materials used 100,000 lbs. Actual finished units produced 25,000 units Multiple Choice $135,750. $164,250. $150,000. $182,000. $100,000. 2. Use the following data to find the total direct labor cost variance if the...

  • Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....

    Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) Direct labor (8 hrs. @ $16 per hr.) Factory overhead-variable (8 hrs. @ $9 per hr.) Factory overhead-fixed (8 hrs. @ $12 per hr.) Total standard cost $144.00 128.00 72.00 96.00 $440.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 59.000 units per quarter. The following flexible budget information is...

  • Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....

    Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) Direct labor (7 hrs. @ $14 per hr.) Factory overhead-Variable (7 hrs. @ $6 per hr.) Factory overhead-Fixed (7 hrs. @ $9 per hr.) Total standard cost $144.00 98.00 42.00 63.00 $347.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 67,000 units per quarter. The following flexible budget information is...

  • Trico Company set the following standard unit costs for its single product. Direct materials (30 lbs....

    Trico Company set the following standard unit costs for its single product. Direct materials (30 lbs. @ $4 per Ib.) Direct labor (5 hrs. @ $14 per hr.) Factory overhead-variable (5 hrs. @ $8 per hr.) Factory overhead-fixed (5 hrs. @ $10 per hr.) Total standard cost $120.00 70.00 40.00 50.00 $280.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 60,000 units per quarter. The following flexible budget information is...

  • Trico Company set the following standard unit costs for its single product Direct naterials (30 Ibe....

    Trico Company set the following standard unit costs for its single product Direct naterials (30 Ibe. e$5.10 per Ib.) Direct labor (6 hrs. $15 per hr.) Factory overhead-variable (6 hrs. e $7 per hr. Factory overhead-fixed (6 hrs. e $11 per hr.) $153.00 90.00 42.00 66.00 $351.00 Total standard cost The predetermined overhead rate is based on a planned operating volume of 80 % of the productive capecity of 56,000 units per quarter. The following flexible budget information is available...

  • Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....

    Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.10 per Ib.) Direct labor (8 hrs. @ $15 per hr.) Factory overhead-Variable (8 hrs. @ $6 per hr.) Factory overhead-Fixed (8 hrs. @ $9 per hr.) Total standard cost $ 153.00 120.00 48.00 72.00 $ 393.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 65,000 units per quarter. The following flexible budget...

  • Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....

    Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) $ 144.00 Direct labor (6 hrs. @ $14 per hr.) 84.00 Factory overhead—variable (6 hrs. @ $7 per hr.) 42.00 Factory overhead—fixed (6 hrs. @ $9 per hr.) 54.00 Total standard cost $ 324.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 57,000 units per quarter. The following flexible budget...

  • Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....

    Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) $ 144.00 Direct labor (7 hrs. @ $14 per hr.) 98.00 Factory overhead—variable (7 hrs. @ $6 per hr.) 42.00 Factory overhead—fixed (7 hrs. @ $9 per hr.) 63.00 Total standard cost $ 347.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 64,000 units per quarter. The following flexible budget...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT