Question

Cost of a Manufactured Product-Job Costing System NOS Poldark is a contractor specializing in custom-built Jacuzzis. As of Ma
What is the total amount left in the Work in Process account at the end of may?
George:
DM:
DL:
FOH:
Total:
0 0
Add a comment Improve this question Transcribed image text
Answer #1

The total cost of George held in work in progress for the month ending May is as follows:

Direct Material 1,100

Direct Labour 800

FOH (0.80 of DL) 640

Total cost 2,540

Add a comment
Know the answer?
Add Answer to:
What is the total amount left in the Work in Process account at the end of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Cost of a Manufactured Product-Job Costing System Ross Poldark is a contractor specializing in custom-built Jacuzzis....

    Cost of a Manufactured Product-Job Costing System Ross Poldark is a contractor specializing in custom-built Jacuzzis. As of May 1, 2018, Poldark has incurred the following costs for each of the jobs listed below. Poldark uses the Job Order Cost system. ENYS CARNE TRURO 2,100 $ 1,850 $ 800 DL 1,900 1,600 660 FOH 1,520 1,280 528 TOTAL $ 5,520 $ 4,730 $ 1,988 DM During May, Poldark incurs the following costs below. Poldark begins one job during the month...

  • Cost of a Manufactured Product-Job Costing System Ross Poldark is a contractor specializing in custom-built Jacuzzis....

    Cost of a Manufactured Product-Job Costing System Ross Poldark is a contractor specializing in custom-built Jacuzzis. As of May 1, 2018, Poldark has incurred the following costs for each of the jobs listed below. Poldark uses the Job Order Cost system. ENYS CARNE TRURO DM $ 2,100 $ 1,850 $ 800 DI 1,900 1,600 660 FOH 1,520 1,280 528 TOTAL $ 5,520 $ 4,730 $ 1,988 During May, Poldark incurs the following costs below. Poldark begins one job during the...

  • Cost of a Manufactured Product- Job Costing System Ross Poldark is a contractor specializing in custom-built...

    Cost of a Manufactured Product- Job Costing System Ross Poldark is a contractor specializing in custom-built Jacuzzis. As of May 1, 2018, Poldark has incurred the following costs for each of the jobs listed below. Poldark uses the Job Order Cost system. DM DL FOH TOTAL ENYS 2,500 2,000 1,200 5,700 CARNE TRURO $ 2,000 $ 900 1,200 800 720 480 $ 3,920 $ 2,180 $ During May, Poldark incurs the following costs below. Poldark begins one job during the...

  • Cost of a Manufactured Product - Job Costing System 1) During may, Poldark incurs the following...

    Cost of a Manufactured Product - Job Costing System 1) During may, Poldark incurs the following costs below. Poldark begins on job during the month of may and completes the other three during the course of the month. Factory overhead is charged to the jobs on the basis of $.60 per dollar of direct labor hours. 2) Determine the total costs of each completed jobs in the space below. 3) What is the total amount left in the Work in...

  • Cost of a Manufactured Product- Job Costing System Robert Perez is a contractor specializing in custom-built Jacuzzis....

    Cost of a Manufactured Product- Job Costing System Robert Perez is a contractor specializing in custom-built Jacuzzis. Perez uses the Job Order Cost system. As of May 1, 2018, Perez has incurred the following costs for each of the jobs listed below HERMAN ALTON STINER $ 900 DM s 2,000 DMS 2500 DI. 800 DL 1,200 DL 2,000 560 FOH 840 FOH 1,400 FOH TOTAL: 2,260 TOTAL: $ 4,040 TOTAL:$ 5,900 During May, Perez incurs the following costs below. Perez...

  • 3. calculate the ending balances of work in process and finished goods as of June 30....

    3. calculate the ending balances of work in process and finished goods as of June 30. A. WIP: B, FG: 4. calculate cost of goods sold for June. 4.5 At the beginning of June, Galway Company had two jobs in process, Job 78 and Job 79, with the following accumulated cost information: Job 79 Direct materials Direct labor Applied overhead Balance, June 1 Job 78 $1,000 600 750 $2,350 $ 800 1,000 1.250 $3,050 During June, two more jobs (80...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT