Question

4.5 At the beginning of June, Galway Company had two jobs in process, Job 78 and Job 79, with the following accumulated cost

3. calculate the ending balances of work in process and finished goods as of June 30.

A. WIP:

B, FG:

4. calculate cost of goods sold for June.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. Ordinary the predetermined overhead rate can be calculate by using estimated overhead and in the case, estimated direct labor cost. so figure were not given. So, it's possible to work backwards from the applied overhead by the beginning of june for job 78 and 79.

Applied Overhead= Predetermined overhead rate× Actual activity level for job 78

750=Predetermined overhead rate×600

Predetermined overhead rate=750/600

=1.25 % Of direct labor cost

(The predetermined overhead rate using job 79 is same Or identical)

2. Job 78 job 79 job 80 job 81

Beginning balance 2350 3050 0 0

Direct material 500 1110 900 100

Direct labor 400 1400 2000 320

Applied overhead 500 1750 2500 400

Total 30 june 3750 7310 5400 820

3. By end of june job 78,79,80 have been completely transfer out of work in process. So, end balance in work in progress consider of job 81.

Work in Progress june 30 $ 820

while three jobs 78,79,80 we're transfer out of work in progress and into finished goods during june, only two jobs remains job 78,80

finished goods june 1

job 78 3750

job 80 5400

finished goods june 30 9150

4. One job 79 was sold during june

cost of good sold 7310

Thanks...

Add a comment
Know the answer?
Add Answer to:
3. calculate the ending balances of work in process and finished goods as of June 30....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...

    Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,300 $1,300 Direct labor 1,400 3,100 Applied overhead 980 2,170 Balance, June 1 $7,680 $6,570 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to...

  • Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...

    Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,100 $1,500 Direct labor 1,200 3,000 Applied overhead 780 1.950 Balance, June 1 $7,080 $6,450 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to...

  • Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...

    Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of March, Mendez Company had two jobs in process, Job 86 and Job 87, with the following accumulated cost information: Direct materials Direct labor Applied overhead Balance, March 1 Job 86 $4,800 1,200 888 $6,888 Job 87 $1,600 3,000 2,220 56,820 During March, two more jobs (88 and 89) were started. The following direct materials and direct labor costs were added to...

  • Instructions At the beginning of June, Rhone Company had two jobs in process, Job 44 and...

    Instructions At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,250 $1,600 Direct labor 1,500 3,300 Applied overhead 1.125 2,475 Balance, June 1 $7.875 $7,375 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 64 Job 45 Job 46...

  • At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job...

    At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,200 $1,250 Direct labor 1,600 3,500 Applied overhead 1,120 2,450 Balance, June 1 $7,920 $7,200 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46 Job...

  • Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...

    Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of June, Donewell Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,000 $1,800 Direct labour 4,400 3,520 Applied overhead 3,800 3,040 Balance, June 1 $13,200 $8,360 During June, two more jobs (46 and 47) were started. The following direct materials and direct labour costs were added to...

  • At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job...

    At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,250 $1,600 Direct labor 1,500 3,300 Applied overhead 1,125 2,475 Balance, June 1 $7,875 $7,375 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46 Job...

  • At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job...

    At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,000 $1,200 Direct labor 1,700 2,900 Applied overhead 935 1,595 Balance, June 1 $7,635 $5,695 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46 Job...

  • At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job...

    At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $4,850 $1,400 Direct labor 800 2,800 Applied overhead 560 1,960 Balance, June 1 $6,210 $6,160 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46 Job...

  • Applying Concepts On June 1, Delman Company's work in process inventory consisted of three jobs with...

    Applying Concepts On June 1, Delman Company's work in process inventory consisted of three jobs with the following costs: Job 40 Job 41 Job 42 Direct materials $1,000 $2,000 $700 Direct labor 1,800 1,200 800 Applied overhead 1,260 840 560 During June, four more jobs were started. Information on costs added to the seven jobs during the month is as follows: Job 40 Job 41 Job 42 Job 43 Job 44 Job 45 Job 46 Direct materials $3,000 $5,000 $4,700...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT