Question

Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...

Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS

At the beginning of June, Donewell Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information:

Job 44 Job 45
Direct materials $5,000 $1,800
Direct labour 4,400 3,520
Applied overhead 3,800 3,040
Balance, June 1 $13,200 $8,360

During June, two more jobs (46 and 47) were started. The following direct materials and direct labour costs were added to the four jobs during the month of June:

Job 44 Job 45 Job 46 Job 47
Direct materials $2,500 $7,110 $1,800 $1,700
Direct labour 800 6,400 900 560

At the end of June, Jobs 44, 45, and 47 were completed. Only Job 45 was sold. On June 1, the balance in Finished Goods was zero.

Required:

1. Calculate the overhead rate based on direct labour cost. Round the percentage to the nearest whole number. For example, .6372 would be rounded to 64%.
%

2. Prepare a brief job-order cost sheet for the four jobs. Show the balance as of June 1 as well as direct materials and direct labour added in June. Apply overhead to the four jobs for the month of June, and show the ending balances. Round your answers to the nearest whole dollar. For those boxes in which no entry is required, enter "0".

Donewell Company
Job-Order Cost Sheet
For the Month of June
Job 44 Job 45 Job 46 Job 47
Beginning balance, June 1 $ $ $ $
Direct materials
Direct labour
Applied overhead
Total, June 30 $ $ $ $

3. Calculate the ending balances of Work in Process and Finished Goods as of June 30. Round your answers to the nearest dollar.

Work in process $
Finished goods $

4. Calculate the Cost of Goods Sold for June. Round your answer to the nearest dollar.
$

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1) overhead rate = 3800/4400 = 86%

2) Calculate following

Donewell Company
Job-Order Cost Sheet
For the Month of June
Job 44 Job 45 Job 46 Job 47
Beginning balance, June 1 $13200 $8360 $ $
Direct materials 2500 7110 1800 1700
Direct labour 800 6400 900 560
Applied overhead 688 5504 774 482
Total, June 30 $17188 $27374 $3474 $2742

3. Calculate the ending balances of Work in Process and Finished Goods as of June 30. Round your answers to the nearest dollar.

Work in process $3474
Finished goods 17188+2742 = 19930

4) Cost of goods sold = 27374

Add a comment
Know the answer?
Add Answer to:
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...

    Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,100 $1,500 Direct labor 1,200 3,000 Applied overhead 780 1.950 Balance, June 1 $7,080 $6,450 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to...

  • Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...

    Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,300 $1,300 Direct labor 1,400 3,100 Applied overhead 980 2,170 Balance, June 1 $7,680 $6,570 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to...

  • Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...

    Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of March, Mendez Company had two jobs in process, Job 86 and Job 87, with the following accumulated cost information: Direct materials Direct labor Applied overhead Balance, March 1 Job 86 $4,800 1,200 888 $6,888 Job 87 $1,600 3,000 2,220 56,820 During March, two more jobs (88 and 89) were started. The following direct materials and direct labor costs were added to...

  • 5 At the beginning of June, Donewell Company had two jobs in process, Job 44 and...

    5 At the beginning of June, Donewell Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,000 $1,700 Direct labour 5,200 4,160 Applied overhead 3,100 2,480 Balance, June 1 $13,300 $8,340 During June, two more jobs (46 and 47) were started. The following direct materials and direct labour costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46...

  • help please. theres a lot of pictures, but it is 1 problem. Prepare Job-Order Cost Sheets,...

    help please. theres a lot of pictures, but it is 1 problem. Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and Instructions Amount Descriptions Overhead Rate Job-Order Cost Sheets Concluding Questions Instructions Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct...

  • At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job...

    At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,250 $1,600 Direct labor 1,500 3,300 Applied overhead 1,125 2,475 Balance, June 1 $7,875 $7,375 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46 Job...

  • Instructions At the beginning of June, Rhone Company had two jobs in process, Job 44 and...

    Instructions At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,250 $1,600 Direct labor 1,500 3,300 Applied overhead 1.125 2,475 Balance, June 1 $7.875 $7,375 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 64 Job 45 Job 46...

  • At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job...

    At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,000 $1,200 Direct labor 1,700 2,900 Applied overhead 935 1,595 Balance, June 1 $7,635 $5,695 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46 Job...

  • At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job...

    At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $4,850 $1,400 Direct labor 800 2,800 Applied overhead 560 1,960 Balance, June 1 $6,210 $6,160 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46 Job...

  • At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job...

    At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,200 $1,250 Direct labor 1,600 3,500 Applied overhead 1,120 2,450 Balance, June 1 $7,920 $7,200 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46 Job...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT