Question

At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job...

At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information:

Job 44 Job 45
Direct materials $5,000 $1,200
Direct labor 1,700 2,900
Applied overhead 935 1,595
Balance, June 1 $7,635 $5,695

During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June:

Job 44 Job 45 Job 46 Job 47
Direct materials $2,250 $7,140 $1,650 $1,850
Direct labor 840 6,380 960 660

At the end of June, Jobs 44, 45, and 47 were completed. Only Job 45 was sold. On June 1, the balance in Finished Goods was zero.

Required:
1. Calculate the overhead rate based on direct labor cost. Round to three decimal places.
2. Prepare a brief job-order cost sheet for the four jobs. Show the balance as of June 1 as well as direct materials and direct labor added in June. Apply overhead to the four jobs for the month of June, and show the ending balances.
3. Calculate the ending balances of Work in Process and Finished Goods as of June 30.
4. Calculate the Cost of Goods Sold for June.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1) calculate the overhead rate based on direct labour cost

we don't know pre determined OVERHEAD rate,it should be Calculated by using any of the job either job 44or job 45

we use job 44

PRE DETERMINED OVERHEAD rate=applied overhead/direct labour cost

   =$935/$1700×100=55%

also pre determined OVERHEAD rate same/identifical for job 45

=$1595/$2900×100=55%

2) prepare job cost sheet for 4jobs

Particular job44 job45 job46 job47
Direct material $2250 $7140 $1650 $1850
Direct labour $840 $6380 $960 $660
Applied overhead [direct labour cost×55%]

[$840×55%]

$462

[$6380×55%]

$3509

[$960×55%]

$528

[$660×55%]

$363

Beginning balance $7635 $5695
Total June 30 $11187 $22724 $3138 $2873

3) calculate ending inventory and finished goods

At the end of June job 44,45,47 were completed and remaining job46 balance still working in process

Therefore

Ending inventory job46= $3138

and remaining three jobs (44,45,47) were completed and transferred to finished goods

And later on job 45sold

Therefore

Cost of finished goods job(44,47)=$11187+$2873=$14060

4) calculation of cost of goods sold for June

only job 45 sold during the month

Therefore cost of goods sold =$22724

ALL THE BEST

PLEASE DO SUPPORT US

ANY DOUBT PLEASE COMMENT BELOW

THANK YOU

Add a comment
Know the answer?
Add Answer to:
At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job...

    At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $4,850 $1,400 Direct labor 800 2,800 Applied overhead 560 1,960 Balance, June 1 $6,210 $6,160 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46 Job...

  • At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job...

    At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,250 $1,600 Direct labor 1,500 3,300 Applied overhead 1,125 2,475 Balance, June 1 $7,875 $7,375 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46 Job...

  • Instructions At the beginning of June, Rhone Company had two jobs in process, Job 44 and...

    Instructions At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,250 $1,600 Direct labor 1,500 3,300 Applied overhead 1.125 2,475 Balance, June 1 $7.875 $7,375 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 64 Job 45 Job 46...

  • At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job...

    At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,200 $1,250 Direct labor 1,600 3,500 Applied overhead 1,120 2,450 Balance, June 1 $7,920 $7,200 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46 Job...

  • Ar the beginning of June, Rhone Company had two jobs in process, Job 44 and Job...

    Ar the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cont information Job 44 Job 45 $1,200 Direc labor 1,700 2,900 1.596 Applied overhead Balance June 1 935 57.635 55,895 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June Job 44 Job 45 Job 46 Job 47 Direct materials...

  • 5 At the beginning of June, Donewell Company had two jobs in process, Job 44 and...

    5 At the beginning of June, Donewell Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,000 $1,700 Direct labour 5,200 4,160 Applied overhead 3,100 2,480 Balance, June 1 $13,300 $8,340 During June, two more jobs (46 and 47) were started. The following direct materials and direct labour costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46...

  • Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...

    Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,100 $1,500 Direct labor 1,200 3,000 Applied overhead 780 1.950 Balance, June 1 $7,080 $6,450 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to...

  • help please. theres a lot of pictures, but it is 1 problem. Prepare Job-Order Cost Sheets,...

    help please. theres a lot of pictures, but it is 1 problem. Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and Instructions Amount Descriptions Overhead Rate Job-Order Cost Sheets Concluding Questions Instructions Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct...

  • Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...

    Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,300 $1,300 Direct labor 1,400 3,100 Applied overhead 980 2,170 Balance, June 1 $7,680 $6,570 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to...

  • Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...

    Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of June, Donewell Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,000 $1,800 Direct labour 4,400 3,520 Applied overhead 3,800 3,040 Balance, June 1 $13,200 $8,360 During June, two more jobs (46 and 47) were started. The following direct materials and direct labour costs were added to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT