As we know that,

the formula to calculate variable cost as per high-low method is = (Highest activity cost-lowest activity cost)/(highest activity hours-lowest activity hours).

i.e.....Highest activity cost=11240

        lowest activity cost =7000

        highest activity hours=490

        lowest activity hours=270

       therefore,

   1)    variable cost per hour as per high-low method =(11240-7000)/(490-270) = 19.27273

       fixed cost as per high-low cost method is =highest activity cost-(variable cost per hour*highest activity hours)

                                                                   = 11240-(490*19.273)

                                                                     =1796.23

      2) fixed cost per hour =total fixed cost/highest activity hours

                                     = 1796.23/490

                                    =3.666

Add a comment
Know the answer?
Add Answer to:
Online beach na g mentMan.do invokeretakeAssignmentSessionLocator assignment-takenprogresse sing High-Low to Clot hed Cost Calculate the Variable...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Using High-Low to Calculate Fixed Cost Calculate the Variable Rate, and Construct a Cost Function Pizza...

    Using High-Low to Calculate Fixed Cost Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost($) Employee Hours January 9,490 510 February 7,000 590 March 7,531 620 April 8,140 470 May 9,787 550 June 8,490 430 July 12,708 700 August 7,500 390 Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant. In your calculations, round the...

  • Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza...

    Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month   Labor Cost($)   Employee Hours     January      9,490         380     February      7,000         440     March      7,531         460     April      8,140         350     May      9,787         410     June      8,490         320     July      11,042     ...

  • Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza...

    Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month January February March Labor Cost($) Employee Hours 9,490 7,000 7,531 8,140 9,787 8,490 April May June July 13,416 7,500 August Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant In your calculations, round the variable rate per employee hour to the nearest...

  • Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza...

    Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost($) Employee Hours January 9,490 570 February 7,000 660 March 7,531 700 April 8,140 May 9,787 620 480 June 8,490 July 13,520 790 August 7,500 440 Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant. In your calculations, round the variable...

  • #1 #2 #3 Please show work Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate,...

    #1 #2 #3 Please show work Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost($) Employee Hours January 290 9,490 7,000 February 330 March 7,531 April 8,140 May 9,787 310 240 June 8,490 July 10,776 400 August 7,500 220 Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant. In...

  • Using High-Low to Calculate and cont Calculate the Variable Roster, and Construct a cost functie Piazza...

    Using High-Low to Calculate and cont Calculate the Variable Roster, and Construct a cost functie Piazza Vesuvio makes speciaky puzzas. Data for the past 3 months were collected: Month Labor Cost($) Employee Hours Lanuary 9.490 February 7,000 March 7,531 April May 9,787 June 8.490 July 11,820 August 7,500 300 Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant In your calculations, round the variable rate per employee hour to the nearest...

  • Using High-Low to Calculate Predicted Total Variable Cost and Total Cost for a Time Period that...

    Using High-Low to Calculate Predicted Total Variable Cost and Total Cost for a Time Period that Differs from the Data Period Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost Employee Hours January $7,000   360 February 8,140 550 March 9,899 630 April 9,787 610 May 8,490 480 June 7,450 350 July 9,490 570 August 7,531 310 Assume that this information was used to construct the following formula for monthly labor cost. Total Labor...

  • Using High-Low to Calculate Predicted Total Variable Cost and Total Cost for Budgeted Output Pizza Vesuvio...

    Using High-Low to Calculate Predicted Total Variable Cost and Total Cost for Budgeted Output Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost Employee Hours January $7,000 430 February $9,899 620 March $8,140 700 April $9,787 680 May $8,490 550 June $7,531 420 July $9,490 640 August $7,450 380 Assume that this information was used to construct the following formula for monthly labor cost. Total Labor Cost = $6629+ ($2.16 x Employee Hours)...

  • Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza...

    Using High-Low to Calculate Fixed Cost, Calculate the Variable Rate, and Construct a Cost Function Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month   Labor Cost($)   Employee Hours     January      9,290         310     February      6,800         360     March      7,331         380     April      7,940         290     May      9,587         340     June      8,290         260     July      10,378     ...

  • Calculator Using High-Low to Calculate Predicted Total Variable Cost and Total Cost for Budgeted Output Pizza...

    Calculator Using High-Low to Calculate Predicted Total Variable Cost and Total Cost for Budgeted Output Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost Employee Hours January $6,800 370 February $9,699 560 March $7,940 640 April $9,587 620 May $8,290 490 June $7,331 360 July $9,290 580 August $7.250 320 Assume that this information was used to construct the following formula for monthly labor cost. Total Labor Cost - $6559 + ($2.16 x...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT