47)
(a) Total Manufacturing Cost = Direct Material Used + Direct Labour + Manufacturing Overheads
= 61,000+72,000+54,000
= $187,000
(b) Direct Material Used = Total Manufacturing Cost - Direct Labour - Manufacturing Overheads
= 252,000 - 53,000 - 90,000
= $109,000
(c) Direct Labour = Total Manufacturing Cost - Direct Material used - Manufacturing Overheads
= 310,000 - 53,000 - 96,000
= $161,000
48)
(a) Total Manufacturing Cost = Direct Labour + Direct Material used + Manufacturing Overheads
= 145,000 + 151,000 +208,000
= $504,000
(b) Total cost of Work in process = Beginning work in process + Total Manufacturing Cost
= 26,000 + 504,000
= $530,000
Presented below are incomplete 2019 manufacturing cost data for Imani Corporation. 47) Manufacturi Total Manufactur ing...
2. Presented below are incomplete 2019 manufacturing cost data for Apple Inc. (20 pts) Direct Materials Used Direct Labor Manufacturing Overhead Total Manufacturing Costs Work in Process (1/1) Work in Process (12/31) Cost of Goods Manufactured (a) $38,000 $80,000 $48,000 ? $120,000 $96,000 ? (b) $149,000 $53,000 $90,000 $292,000 ? $98,000 $311,000 (c) $53,000 $116,000 $121,000 $290,000 $403,000 ? $515,000 Instructions Determine the missing amounts.
) Gabriel Manufacturing Company has the following data: Direct labor $145,000 Direct materials used 151,000 Total manufacturing overhead 208,000 Beginning work in process 26,000 Instructions Compute (a) total manufacturing costs and (b) total cost of work in process ( show the steps please!)
Question 19 Determine the missing amounts in 2019 manufacturing cost data for Tardy Corporation. Direct Materials Used Direct Labor Total Manufacturing Manufacturing Overhead Costs Work in Process (1/1) Work in Process (12/31) Cost of Goods Manufactured $38,000 $80,000 $48,000 $120,000 $96,000 2 $149,000 $53,000 $90,000 $292,000 $98,000 $311,000 O $53,000 $116,000 $121,000 $290,000 $403,000 $515,000
2. Presented below are incomplete 2019 manufacturing cost data for Apple Inc. (20 pts) Direct Material Total a) b) le) Dract Labor 80T000 .000 $116.000 $187000 $149.000 $3.000 Goods Manufacturing Manufacturing Overhead Costs 0 00 $90.000 299.000 $121.000 $290,000 Work in Process (1/1) 3120,000 3 $403000 Won Process 12/31) 0 00 Instructions Determine the missing amounts 000 2 $515.000 Page 5 of 5 759 Words English (US)
Presented below are incomplete 2019 manufacturing cost data for Shell Corporation. Direct Materials Used Direct Labor Manufacturing Overhead Total Manufacturing Costs (a) $48,000 $72,000 ? $194,000 (b) $95,000 ? $80,000 $305,000 (c) ? $80,000 $120,000 $260,000 Instructions Determine the missing amounts. (show the steps please!
Brief Exercise 1-10 Presented below are incomplete manufacturing cost data. Determine the missing amounts for three different situations. Direct Materials Used Direct Labor Used Total Manufacturing Costs $41,500 (1) (2) s (3) $65,000 $76,000 Factory Overhead $52,200 $143,000 $297,000 $59,000 $ $113,000 $311,000 LINK TO TEXT Determine the missing amounts. Total Manufacturing Costs Work in Process (January 1) $124,000 Cost of Goods Manufactured Work in Process (December 31) $85,900 $98,700 $323,800 $297,000 $ $311,000 $465,000 $719,000
Brief Exercise 14-10
Presented below are incomplete manufacturing cost data.
Determine the missing amounts for three different situations.
Direct
Materials
Used
Direct
Labor
Used
Factory
Overhead
Total
Manufacturing
Costs
(1)
$41,900
$62,500
$52,900
$
(2)
$
$76,000
$144,000
$300,000
(3)
$57,400
$
$115,000
$312,000
Determine the missing amounts.
Total
Manufacturing
Costs
Work
in Process
(January 1)
Work
in Process
(December 31)
Cost of
Goods
Manufactured
(1)
$
$122,000
$84,300
$
(2)
$300,000
$
$98,500
$324,500
(3)
$312,000
$467,000
$
$719,000
An incomplete cost of goods manufactured schedule is presented below for Cepeda Manufacturing Company for the year ended December 2020: Complete the cost of goods manufactured schedule for Cepeda Manufacturing Company. CEPEDA MANUFACTURING COMPANY Cost of Goods Manufactured Schedule For the Year Ended December 31, 2020 $212,500 $ 166,000 Work in process (1/1) Direct materials Raw materials inventory(1/1) Raw materials purchases Total raw materials available for use Less: Raw materials inventory (12/31) Direct materials used 17,800 $188,000 Direct labour Manufacturing...
An incomplete cost of goods manufactured schedule is presented
below for Cepeda Manufacturing Company for the year ended December
2020:
Complete the cost of goods manufactured schedule for Cepeda
Manufacturing Company.
Complete the cost of goods
manufactured schedule for Cepeda Manufacturing Company.
CEPEDA MANUFACTURING COMPANY Cost of Goods Manufactured Schedule For the Year Ended December 31, 2020 $217,000 Work in process (1/1) Direct materials Raw materials inventory, (1/1) Raw materials purchases 167,000 Total raw materials available for use 18,000 Less:...
Presented below are incomplete manufacturing cost data. Determine the missing amounts for three different situations. Total Manufacturing Costs Direct Labor Used Direct Materials Used Factory Overhead $ $42,400 $62,800 $52,300 (1) (2) $ $77,800 $142,000 $300,000 $58,600 $ $313,000 $115,000 (3)