Question

Presented below are incomplete 2019 manufacturing cost data for Imani Corporation. 47) Manufacturi Total Manufactur ing Costs
0 0
Add a comment Improve this question Transcribed image text
Answer #1

47)

(a) Total Manufacturing Cost = Direct Material Used + Direct Labour + Manufacturing Overheads

= 61,000+72,000+54,000

= $187,000

(b) Direct Material Used = Total Manufacturing Cost - Direct Labour - Manufacturing Overheads

= 252,000 - 53,000 - 90,000

= $109,000

(c) Direct Labour = Total Manufacturing Cost - Direct Material used - Manufacturing Overheads

= 310,000 - 53,000 - 96,000

= $161,000

48)

(a) Total Manufacturing Cost = Direct Labour + Direct Material used + Manufacturing Overheads

= 145,000 + 151,000 +208,000

= $504,000

(b) Total cost of Work in process = Beginning work in process + Total Manufacturing Cost

= 26,000 + 504,000

= $530,000

Add a comment
Know the answer?
Add Answer to:
Presented below are incomplete 2019 manufacturing cost data for Imani Corporation. 47) Manufacturi Total Manufactur ing...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 2. Presented below are incomplete 2019 manufacturing cost data for Apple Inc. (20 pts) Direct Materials...

    2. Presented below are incomplete 2019 manufacturing cost data for Apple Inc. (20 pts) Direct Materials Used Direct Labor Manufacturing Overhead Total Manufacturing Costs Work in Process (1/1) Work in Process (12/31) Cost of Goods Manufactured (a) $38,000 $80,000 $48,000 ? $120,000 $96,000 ? (b) $149,000 $53,000 $90,000 $292,000 ? $98,000 $311,000 (c) $53,000 $116,000 $121,000 $290,000 $403,000 ? $515,000 Instructions Determine the missing amounts.

  • ) Gabriel Manufacturing Company has the following data: Direct labor                               &

    ) Gabriel Manufacturing Company has the following data: Direct labor                                               $145,000 Direct materials used                                  151,000 Total manufacturing overhead                   208,000 Beginning work in process                           26,000 Instructions Compute (a) total manufacturing costs and (b) total cost of work in process ( show the steps please!)

  • Question 19 Determine the missing amounts in 2019 manufacturing cost data for Tardy Corporation. Direct Materials...

    Question 19 Determine the missing amounts in 2019 manufacturing cost data for Tardy Corporation. Direct Materials Used Direct Labor Total Manufacturing Manufacturing Overhead Costs Work in Process (1/1) Work in Process (12/31) Cost of Goods Manufactured $38,000 $80,000 $48,000 $120,000 $96,000 2 $149,000 $53,000 $90,000 $292,000 $98,000 $311,000 O $53,000 $116,000 $121,000 $290,000 $403,000 $515,000

  • 2. Presented below are incomplete 2019 manufacturing cost data for Apple Inc. (20 pts) Direct Material...

    2. Presented below are incomplete 2019 manufacturing cost data for Apple Inc. (20 pts) Direct Material Total a) b) le) Dract Labor 80T000 .000 $116.000 $187000 $149.000 $3.000 Goods Manufacturing Manufacturing Overhead Costs 0 00 $90.000 299.000 $121.000 $290,000 Work in Process (1/1) 3120,000 3 $403000 Won Process 12/31) 0 00 Instructions Determine the missing amounts 000 2 $515.000 Page 5 of 5 759 Words English (US)

  • Presented below are incomplete 2019 manufacturing cost data for Shell Corporation. Direct Materials Used Direct Labor...

    Presented below are incomplete 2019 manufacturing cost data for Shell Corporation. Direct Materials Used Direct Labor Manufacturing Overhead Total Manufacturing Costs (a) $48,000 $72,000 ? $194,000 (b) $95,000 ? $80,000 $305,000 (c) ? $80,000 $120,000 $260,000 Instructions Determine the missing amounts. (show the steps please!

  • Brief Exercise 1-10 Presented below are incomplete manufacturing cost data. Determine the missing amounts for three...

    Brief Exercise 1-10 Presented below are incomplete manufacturing cost data. Determine the missing amounts for three different situations. Direct Materials Used Direct Labor Used Total Manufacturing Costs $41,500 (1) (2) s (3) $65,000 $76,000 Factory Overhead $52,200 $143,000 $297,000 $59,000 $ $113,000 $311,000 LINK TO TEXT Determine the missing amounts. Total Manufacturing Costs Work in Process (January 1) $124,000 Cost of Goods Manufactured Work in Process (December 31) $85,900 $98,700 $323,800 $297,000 $ $311,000 $465,000 $719,000

  • Brief Exercise 14-10 Presented below are incomplete manufacturing cost data. Determine the missing amounts for three...

    Brief Exercise 14-10 Presented below are incomplete manufacturing cost data. Determine the missing amounts for three different situations. Direct Materials Used Direct Labor Used Factory Overhead Total Manufacturing Costs (1) $41,900 $62,500 $52,900 $ (2) $ $76,000 $144,000 $300,000 (3) $57,400 $ $115,000 $312,000 Determine the missing amounts. Total Manufacturing Costs Work in Process (January 1) Work in Process (December 31) Cost of Goods Manufactured (1) $ $122,000 $84,300 $ (2) $300,000 $ $98,500 $324,500 (3) $312,000 $467,000 $ $719,000

  • An incomplete cost of goods manufactured schedule is presented below for Cepeda Manufacturing Company for the...

    An incomplete cost of goods manufactured schedule is presented below for Cepeda Manufacturing Company for the year ended December 2020: Complete the cost of goods manufactured schedule for Cepeda Manufacturing Company. CEPEDA MANUFACTURING COMPANY Cost of Goods Manufactured Schedule For the Year Ended December 31, 2020 $212,500 $ 166,000 Work in process (1/1) Direct materials Raw materials inventory(1/1) Raw materials purchases Total raw materials available for use Less: Raw materials inventory (12/31) Direct materials used 17,800 $188,000 Direct labour Manufacturing...

  • An incomplete cost of goods manufactured schedule is presented below for Cepeda Manufacturing Company for the...

    An incomplete cost of goods manufactured schedule is presented below for Cepeda Manufacturing Company for the year ended December 2020: Complete the cost of goods manufactured schedule for Cepeda Manufacturing Company. Complete the cost of goods manufactured schedule for Cepeda Manufacturing Company. CEPEDA MANUFACTURING COMPANY Cost of Goods Manufactured Schedule For the Year Ended December 31, 2020 $217,000 Work in process (1/1) Direct materials Raw materials inventory, (1/1) Raw materials purchases 167,000 Total raw materials available for use 18,000 Less:...

  • Presented below are incomplete manufacturing cost data. Determine the missing amounts for three different situations. Total...

    Presented below are incomplete manufacturing cost data. Determine the missing amounts for three different situations. Total Manufacturing Costs Direct Labor Used Direct Materials Used Factory Overhead $ $42,400 $62,800 $52,300 (1) (2) $ $77,800 $142,000 $300,000 $58,600 $ $313,000 $115,000 (3)

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT