HEY, ALL I NEED IS THE LAST QUESTION PLEASE, THESE SCREENSHOTS ARE FOR TO HELP YOU UNDERSTAND WHAT HAS BEEN DONE BEFORE :D
Answers:
(a).1. Journalize the June transactions for purchase of raw materials, factory labor costs incurred, and manufacturing overhead costs incurred
Debit | Credit | |||
Raw Materials | 6800 | |||
Accounts Payable | 6800 | |||
Factory Labor | 4800 | |||
Cash | 4800 | |||
Manufacturing Overhead | 1300 | |||
Accumulated Depreciation- Equipment | 900 | |||
Accounts Payable | 400 |
(a).2. Journalize the June transactions for assignment of direct materials, labor, and overhead to production
Work in Process Inventory | 4900 | |||
Manufacturing Overhead | 1500 | |||
Raw Materials Inventory | 6400 | |||
Work in Process Inventory | 3600 | |||
Manufacturing Overhead | 1400 | |||
Factory Labor | 5000 | |||
Work in Process Inventory | 5400 | |||
Manufacturing Overhead | 5400 |
(a).3. Journalize the June transactions for completion of jobs and sale of goods.
Finished goods Inventory | 15800 | |||
Work in Process Inventory | 15800 | |||
Cash | 22000 | |||
Sales | 22000 | |||
Cost of Goods Sold | 15800 | |||
Finished Goods Inventory | 15800 |
b. Post the entries to Work in Process Inventory.
Work in Process Inventory | ||||||
6/1 | Balance | 5540 | June | Completed work | 15800 | |
Direct Materials | 4900 | |||||
Direct labor | 3600 | |||||
Overhead applied | 5400 | |||||
6/30 | Balance | 4000 |
c. Reconcile the balance in Work in Process Inventory with the costs of unfinished jobs.
6/30 balance in Work in Process Inventory | 4000 | ||
Unfinished Job (Koss) | |||
Direct materials | 2000 | ||
Direct labor | 800 | ||
Manufacturing overhead | 1200 | ||
4000 |
d. Prepare a cost of goods manufactured schedule for June.
CASE INC. | ||||
Cost of Goods Manufactured Schedule | ||||
For the Month Ended June 30, 2020 | ||||
Work in process, June 1 | 5540 | |||
Direct materials used | 4900 | |||
Direct labor | 3600 | |||
Manufacturing overhead applied | 5400 | |||
Total manufacturing costs | 13900 | |||
Total cost of work in process | 19440 | |||
Less: Work in process, June 30 | 4000 | |||
Cost of goods manufactured | 15440 |
HEY, ALL I NEED IS THE LAST QUESTION PLEASE, THESE SCREENSHOTS ARE FOR TO HELP YOU...
P2.3A (LO 1, 2, 3, 4, 5), AP Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $4,200 Manufacturing Overhead Applied $32,640 Work in Process Inventory $5,540 Manufacturing Overhead Incurred $31,650 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer...
i really just need help with the (a)(3) part. thank you. Lactory Labor 75 4800 76 7 Work in process inventory 4.500 8 manufacturing overhead 4,500 9 0 1 (a)(3) Journalize the June transactions for completion of jobs and sale of goods 2 3 Finished Good Inventory 14.740 Work in process inventory 14,740 5 Cost Element - Completed Projects Rodgers Stevens Linton 2 June 1 Direct Materials 600 800 900 Direct Labor 320 540 580 Mitg O/H 400 675 725...
job order P-3A Case Inc. is a construction company specializing in custom patios. The pa st of goods constructed of concrete, brick, fiberglass, and lumber, depending upon customer p dule. eference. On June 1, 2017, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $4,200 Manufacturing Overhead Applied Work in Process Inventory $5,540 Manufacturing Overhead Incurred Subsidiary data for Work in Process Inventory on June 1 are as follows. $31,650 Job Cost Sheets Customer Job Cost...
PROBLEM 2-3 Prepare entries in a job order cost system and cost of goods manufactured schedule. Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2017, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $4,200 Manufacturing Overhead Applied $32,640 Work in Process Inventory $5,540 Manufacturing Overhead Incurred $31,650 Subsidiary data for Work in Process Inventory on June...
Need help with this whole problem Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. $31,800 Raw Materials Inventory Work in Process Inventory $4,400 $5,450 Manufacturing Overhead Applied Manufacturing Overhead Incurred $30,200 Subsidiary data for Work in Process Inventory on June 1 are as follows. Linton Job Cost Sheets Customer Job...
Journalize the June transactions: (1) for purchase of raw materials, factory labor costs incurred, and manufacturing overhead cost incurred; (2) assignment of direct materials, labor, and overhead to production; and (3) completion of jobs and sale of goods. Post the entries to Work in Process Inventory. Reconcile the balance in Work in Process Inventory with the costs of unfinished jobs. Prepare a cost of goods manufactured schedule for June. Case Inc. is a construction company specializing in custom patios. The...
please help! here is the beggining again.. i hope it is more clear ssignment> Open Assignment CALCULATOR MESSAGE HY INSTRUCTOR PULL SCREEN PRINTER VERSSION BACK NEX Problem 20-03A a-d (Part Level Submission) (Videe) Sandhill Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Sandha Inc. contains the following data Manufacturing Overhead Applied Manufacturing Overhead Incurred Raw Materials Inventory...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1,2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory 4,600 Manufacturing Overhead Applied $35,500 Work in Process Inventory $5,900 Manufacturing Overhead Incurred $30,000 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Cost Element Direct materials Direct labor Rodgers Stevens...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $4,300 Manufacturing Overhead Applied $30,800 Work in Process Inventory $5,450 Manufacturing Overhead Incurred $32,800 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Cost Element Rodgers Stevens Linton Direct materials...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1,2020, the general ledger for Case Inc. contains the following data Raw Materials Inventory $3,800 Manufacturing Overhead Applied 35,800 Work in Process Inventory $4,800 Manufacturing Overhead Incurred 29,800 Subsidiary data for Work in Process Inventory on June 1 are as follows. 0 ее Customer Job Cost Element Direct materials Direct labor Manufacturing overhead Rodgers...