Date | Account titles and explanation | Debit | Credit |
1 | Raw materials | $4900 | |
Account payable | $4900 | ||
(To record purchase of raw materials) | |||
Factory labor | $4800 | ||
Cash | $4800 | ||
(To record factory labor costs paid) | |||
Manufacturing overhead (900+400) | $1300 | ||
Accumulated depreciation- Equipment | $900 | ||
Account payable | $400 | ||
(To record manufacturing overhead costs incurred) | |||
2 | Work in process inventory | $4900 | |
Manufacturing overhead | $1500 | ||
Raw materials inventory | $6400 | ||
(To record assignment of direct materials) | |||
Work in process inventory | $3600 | ||
Manufacturing overhead | $1200 | ||
Factory labor | $4800 | ||
(To record assignment of factory labor) | |||
Work in process inventory (3600*1.25) | $4500 | ||
Manufacturing overhead | $4500 | ||
(To record assignment of manufacturing overhead) | |||
3 | Finished goods inventory | $14740 | |
Work in process inventory | $14740 | ||
(To record completion of jobs) | |||
Cash | $18900 | ||
Sales | $18900 | ||
(To record sales of goods) | |||
Cost of goods sold | $14740 | ||
Finished goods inventory | $14740 | ||
(To record cost of goods sold) | |||
Calculation of finished goods inventory= Direct materials+Direct labor+Manufacturing overhead
Rodgers= $(600+800+300)+(320+850+390)+(320+850+390)*1.25= $5210
Stevens= $(800+500)+(540+360)+(540+360)*1.25= $3325
Linton= $(900+1300)+(580+1200)+(580+1200)*1.25= $6205
Finished goods inventory= $5210+3325+6205= $14740
b)
Work in process Inventory | |||||
6/1 | Balance | $5540 | June | Completed work | $14740 |
Direct materials | 4900 | ||||
Direct labor | 3600 | ||||
Manufacturing overhead | 4500 | ||||
6/30 | Balance | $3800 |
c) Cost of Unfurnished Jobs: Koss- Direct materials $2000+Direct labor $800+Manufacturing overhead $1000 (800*$1.25)= $3800
d) k
CASE INC. | ||
Cost of Goods Manufactured Schedule | ||
For the Month Ended June 30, 2017 | ||
Work in process, June 1 | $5540 | |
Direct materials | 4900 | |
Direct labor | 3600 | |
Manufacturing overhead applied | 4500 | |
Total manufacturing costs | 13000 | |
Total cost of work in process | 18540 | |
Less: Work in inventory, June 30 | (3800) | |
Cost of goods manufactured | $14740 | |
PROBLEM 2-3 Prepare entries in a job order cost system and cost of goods manufactured schedule....
Reconcile the balance in Work in Process Inventory with the
costs of unfinished jobs. Prepare a cost of goods manufactured
schedule for June.
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. $4,100 $33,800 Raw Materials Inventory Work in Process Inventory Manufacturing Overhead Applied Manufacturing Overhead Incurred $5,675 $28,600 Subsidiary data...
job order P-3A Case Inc. is a construction company specializing in custom patios. The pa st of goods constructed of concrete, brick, fiberglass, and lumber, depending upon customer p dule. eference. On June 1, 2017, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $4,200 Manufacturing Overhead Applied Work in Process Inventory $5,540 Manufacturing Overhead Incurred Subsidiary data for Work in Process Inventory on June 1 are as follows. $31,650 Job Cost Sheets Customer Job Cost...
P2.3A (LO 1, 2, 3, 4, 5), AP Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $4,200 Manufacturing Overhead Applied $32,640 Work in Process Inventory $5,540 Manufacturing Overhead Incurred $31,650 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer...
Journalize the June transactions: (1) for purchase of raw
materials, factory labor costs incurred, and manufacturing overhead
cost incurred; (2) assignment of direct materials, labor, and
overhead to production; and (3) completion of jobs and sale of
goods.
Post the entries to Work in Process Inventory.
Reconcile the balance in Work in Process Inventory with the costs
of unfinished jobs.
Prepare a cost of goods manufactured schedule for June.
Case Inc. is a construction company specializing in custom patios. The...
Problem 2-3A (Video) (Part Level Submission) Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $3,900 Manufacturing Overhead Applied $35,600 Work in Process Inventory $5,975 Manufacturing Overhead Incurred $29,400 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Cost Element...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $4,300 Manufacturing Overhead Applied $30,800 Work in Process Inventory $5,450 Manufacturing Overhead Incurred $32,800 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Cost Element Rodgers Stevens Linton Direct materials...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory Work in Process Inventory $4,600 Manufacturing Overhead Applied $35,000 $5,425 Manufacturing Overhead Incurred $29,800 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Cost Element Rodgers Stevens Linton Direct materials...
What is the correct finished goods inventory and cost of goods
sold when the jobs are completed?
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2017, the general ledger for Case Inc. contains the following data. Raw Materials Inventory 4,494 Manufacturing Overhead Applied $34,925 Work in Process Inventory $5,928 Manufacturing Overhead Incurred $33,866 Subsidiary data for Work in Process Inventory on...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1,2020, the general ledger for Case Inc. contains the following data Raw Materials Inventory $3,800 Manufacturing Overhead Applied 35,800 Work in Process Inventory $4,800 Manufacturing Overhead Incurred 29,800 Subsidiary data for Work in Process Inventory on June 1 are as follows. 0 ее Customer Job Cost Element Direct materials Direct labor Manufacturing overhead Rodgers...
*Problem 2-3A (Video) (Part Level Submission) Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory Work in Process Inventory $4,200 Manufacturing Overhead Applied $5,450 Manufacturing Overhead Incurred $30,300 $30,200 Subsidiary data for Work in Process Inventory on June 1 are as follows. Cost Element Direct materials Direct labor...