PROBLEM 2-3 Prepare entries in a job order cost system and cost of goods manufactured schedule. Case Inc. is a construction c

(a) Journalize the June transactions: (1) for purchase of raw materials, factory labor costs incurred. and manufacturing over

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Date Account titles and explanation Debit Credit
1 Raw materials $4900
Account payable $4900
(To record purchase of raw materials)
Factory labor $4800
Cash $4800
(To record factory labor costs paid)
Manufacturing overhead (900+400) $1300
Accumulated depreciation- Equipment $900
Account payable $400
(To record manufacturing overhead costs incurred)
2 Work in process inventory $4900
Manufacturing overhead $1500
Raw materials inventory $6400
(To record assignment of direct materials)
Work in process inventory $3600
Manufacturing overhead $1200
Factory labor $4800
(To record assignment of factory labor)
Work in process inventory (3600*1.25) $4500
Manufacturing overhead $4500
(To record assignment of manufacturing overhead)
3 Finished goods inventory $14740
Work in process inventory $14740
(To record completion of jobs)
Cash $18900
Sales $18900
(To record sales of goods)
Cost of goods sold $14740
Finished goods inventory $14740
(To record cost of goods sold)

Calculation of finished goods inventory= Direct materials+Direct labor+Manufacturing overhead

Rodgers= $(600+800+300)+(320+850+390)+(320+850+390)*1.25= $5210

Stevens= $(800+500)+(540+360)+(540+360)*1.25= $3325

Linton= $(900+1300)+(580+1200)+(580+1200)*1.25= $6205

Finished goods inventory= $5210+3325+6205= $14740

b)

Work in process Inventory
6/1 Balance $5540 June Completed work $14740
Direct materials 4900
Direct labor 3600
Manufacturing overhead 4500
6/30 Balance $3800

c) Cost of Unfurnished Jobs: Koss- Direct materials $2000+Direct labor $800+Manufacturing overhead $1000 (800*$1.25)= $3800

d) k

CASE INC.
Cost of Goods Manufactured Schedule
For the Month Ended June 30, 2017
Work in process, June 1 $5540
Direct materials 4900
Direct labor 3600
Manufacturing overhead applied 4500
Total manufacturing costs 13000
Total cost of work in process 18540
Less: Work in inventory, June 30 (3800)
Cost of goods manufactured $14740
Add a comment
Know the answer?
Add Answer to:
PROBLEM 2-3 Prepare entries in a job order cost system and cost of goods manufactured schedule....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Reconcile the balance in Work in Process Inventory with the costs of unfinished jobs. Prepare a...

    Reconcile the balance in Work in Process Inventory with the costs of unfinished jobs. Prepare a cost of goods manufactured schedule for June. Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. $4,100 $33,800 Raw Materials Inventory Work in Process Inventory Manufacturing Overhead Applied Manufacturing Overhead Incurred $5,675 $28,600 Subsidiary data...

  • job order P-3A Case Inc. is a construction company specializing in custom patios. The pa st...

    job order P-3A Case Inc. is a construction company specializing in custom patios. The pa st of goods constructed of concrete, brick, fiberglass, and lumber, depending upon customer p dule. eference. On June 1, 2017, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $4,200 Manufacturing Overhead Applied Work in Process Inventory $5,540 Manufacturing Overhead Incurred Subsidiary data for Work in Process Inventory on June 1 are as follows. $31,650 Job Cost Sheets Customer Job Cost...

  • P2.3A (LO 1, 2, 3, 4, 5), AP Case Inc. is a construction company specializing in...

    P2.3A (LO 1, 2, 3, 4, 5), AP Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $4,200     Manufacturing Overhead Applied $32,640 Work in Process Inventory $5,540     Manufacturing Overhead Incurred $31,650 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets   Customer...

  • Journalize the June transactions: (1) for purchase of raw materials, factory labor costs incurred, and manufacturing...

    Journalize the June transactions: (1) for purchase of raw materials, factory labor costs incurred, and manufacturing overhead cost incurred; (2) assignment of direct materials, labor, and overhead to production; and (3) completion of jobs and sale of goods. Post the entries to Work in Process Inventory. Reconcile the balance in Work in Process Inventory with the costs of unfinished jobs. Prepare a cost of goods manufactured schedule for June. Case Inc. is a construction company specializing in custom patios. The...

  • Problem 2-3A (Video) (Part Level Submission) Case Inc. is a construction company specializing in custom patios....

    Problem 2-3A (Video) (Part Level Submission) Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $3,900 Manufacturing Overhead Applied $35,600 Work in Process Inventory $5,975 Manufacturing Overhead Incurred $29,400 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Cost Element...

  • Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete,...

    Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $4,300 Manufacturing Overhead Applied $30,800 Work in Process Inventory $5,450 Manufacturing Overhead Incurred $32,800 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Cost Element Rodgers Stevens Linton Direct materials...

  • Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete,...

    Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory Work in Process Inventory $4,600 Manufacturing Overhead Applied $35,000 $5,425 Manufacturing Overhead Incurred $29,800 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Cost Element Rodgers Stevens Linton Direct materials...

  • What is the correct finished goods inventory and cost of goods sold when the jobs are...

    What is the correct finished goods inventory and cost of goods sold when the jobs are completed? Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2017, the general ledger for Case Inc. contains the following data. Raw Materials Inventory 4,494 Manufacturing Overhead Applied $34,925 Work in Process Inventory $5,928 Manufacturing Overhead Incurred $33,866 Subsidiary data for Work in Process Inventory on...

  • Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete,...

    Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1,2020, the general ledger for Case Inc. contains the following data Raw Materials Inventory $3,800 Manufacturing Overhead Applied 35,800 Work in Process Inventory $4,800 Manufacturing Overhead Incurred 29,800 Subsidiary data for Work in Process Inventory on June 1 are as follows. 0 ее Customer Job Cost Element Direct materials Direct labor Manufacturing overhead Rodgers...

  • *Problem 2-3A (Video) (Part Level Submission) Case Inc. is a construction company specializing in custom patios....

    *Problem 2-3A (Video) (Part Level Submission) Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory Work in Process Inventory $4,200 Manufacturing Overhead Applied $5,450 Manufacturing Overhead Incurred $30,300 $30,200 Subsidiary data for Work in Process Inventory on June 1 are as follows. Cost Element Direct materials Direct labor...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT