Question

A vertical curve has grades G1 = 2.8% (downgrade) and G2 = 2.2 (upgrade) Assume design...

A vertical curve has grades G1 = 2.8% (downgrade) and G2 = 2.2 (upgrade) Assume design speed = 70 KPH, S=SSD, S ≤ LC, longitudinal friction factor = 0.30, and hesitation time = 2.5 sec. Station PVI = (43+7) and elevation PVI = 53.65 m 1) Design the curve? 2) Calculate the rate of change of curvature? 3) Calculate the rate of change of grade? 4) Determine the station and elevation of PVC? 5) Determine the station and elevation of PVT? 6) Determine the station and elevation of the turning point?

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
A vertical curve has grades G1 = 2.8% (downgrade) and G2 = 2.2 (upgrade) Assume design...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A 1080 ft long tangent crest vertical curve connects tangents ( G1= 4% , G2 =...

    A 1080 ft long tangent crest vertical curve connects tangents ( G1= 4% , G2 = -2.8%). The two stations intersect at ghost station 640+00 where elevation is 1325.000 ft. Determine the stationing and elevations of the following points. 1. PVC 2. PVT 3. High point 4. 640+20

  • a) a 200 m vertical crest curve is designed to connect a +4.5% tangent with a...

    a) a 200 m vertical crest curve is designed to connect a +4.5% tangent with a -2% tangent. What should the design speed be to provide ample stopping sight distance? SSD t Pra) [10 marks) b) A 300 m sag parabolic vertical curve has a PVC at station 2+600.000 and elevation 320.000 m. the initial grade is -4.0% and the final grade is +1.0%. Determine the stationing and elevation of PVI, PVT and the lowest point on the curve. Also...

  • Problem 2. (30 points) You are asked to design a vertical curve that connects -4% and...

    Problem 2. (30 points) You are asked to design a vertical curve that connects -4% and +1% grades along a roadway section with a design speed of 65 mi/h. It is determined that the PVI should be located at sta 10+25 and elevation of 175 ft. You are directed to adopt in your design the minimum requir length of curve that satisfies the design speed. Based on these inputs, determine the followi. a) Length of curve; b) Station and elevation...

  • Transportation Engineering (25 points) As a junior roadway engineer, you have been asked to contr...

    Transportation Engineering (25 points) As a junior roadway engineer, you have been asked to contribute to the design of a section of roadway that runs through a national park. An endangered deer population has been identified in the area and a wildlife underpass under a vertical curve has been proposed, as shown in the figure below. An existing underpass is perpendicular to the roadway at station 20+91.00 (not necessarily under the center of the curve). The top of the underpass...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT