Computation of revenue to be recognized in each year : in '000s
Particulars Year 20X5 Year 20X6 Year 20X7
Total Estimated cost to complete the contract $6000 $6700 $7500
Cost incurred till date $2000 $4500 $7500
% of completion = Cost incurred till date / Total
estimated cost of contract 33.33% 67.16% 100%
Amount of revenue to be recognized in each year
= Total contract revenue * % of completion $ 2333 $ 2368 $2299
$7000*33.333% $7000*(67.16-33.33)% $7000(100-67.16)%
Computation of expense to be recognized in each year
Since the changes in the estimated costs are not known in respective years. So, actual costs should be accounted for each years. in '000s
Year 20X5 Year 20X6 Year 20X7
Amount of expense to be recognized in each year $2000 $2500 $3000
4 marks) In 20X5 We Build Stuff Corp.(WBSC) entered into a $7 million, long-term contract to...