Solution
Mercer Asbestos Removal Company
First-stage allocation of costs to the activity cost pools:
Mercer Asbestos Removal Company |
|||||
First-stage allocation of costs to the activity cost pools: |
|||||
Removing Asbestos |
Estimating and Job Setup |
Working on non-routine jobs |
Other |
Total |
|
Wages and Salaries |
$184,800 |
$30,800 |
$61,600 |
$30,800 |
$308,000 |
Disposal Fees |
$494,200 |
$0 |
$211,800 |
$0 |
$706,000 |
Equipment Depreciation |
$36,000 |
$4,500 |
$22,500 |
$27,000 |
$90,000 |
On-site Supplies |
$35,000 |
$10,000 |
$5,000 |
$0 |
$50,000 |
Office Expenses |
$31,500 |
$73,500 |
$42,000 |
$63,000 |
$210,000 |
Licensing and Insurance |
$102,500 |
$0 |
$205,000 |
$102,500 |
$410,000 |
Total Cost |
$884,000 |
$118,800 |
$547,900 |
$223,300 |
$1,774,000 |
Note: the allocation of overhead costs is done based on percentage consumption across activities.
Computation of activity rates for the activity cost pool:
Activity Cost |
Activity Cost Pool |
Activity rate |
|
Removing Asbestos |
$884,000 |
850,000 square feet |
$1.04 per square feet |
Estimating and job setup |
$118,800 |
400 jobs |
$297 per job |
Working on non-routine jobs |
$547,900 |
100 non-routine jobs |
$5,479 non-routine jobs |
Routine 1,000 sq. ft. job |
Routine 2,000 sq. ft. job |
Nonroutine 2,000 sq. ft. job |
|
Total cost of the job |
$1,337 |
$2,377 |
$7,856 |
Average cost per thousand square feet |
$1,337 |
$1,188.50 |
$3,928 |
Computations:
Total cost of routine 1,000 sq. ft. job = total cost/number thousand square feet
Total cost = cost of removing asbestos + cost of estimating and job setup
= ($1.04) x 1,000 + $297 = $1,337
Average cost = total cost/number of thousand square feet
= $1,337/1 = $1,337
Total cost of routine 2,000 square feet asbestos removal job:
(1.04 x 2,000) + 297 = $2,377
Average cost = $2,377/2 = $1,188.50
Total cost of non-routine 2,000 square feet asbestos removal job:
Total cost = cost of removing asbestos + cost of estimating and job setup + cost of working on non-routine jobs
= ($1.04 x 2,000) + 297 + 5,479 = $7,856
Average cost = 7,856/2 = $3,928
Problem 7-18 Activity-Based Costing and Bidding on Jobs [LO7-2, L07-3, L07-4] Mercer Asbestos Removal Company removes...
Problem 7-18 Activity-Based Costing and Bidding on Jobs (L07-2, L07-3, L07-4] Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors...
Problem 7-18 Activity-Based Costing and Bidding on Jobs (L07-2, LO7-3, LO7.4) Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos contaminated ceiling plaster in industrial buildings. The on-site...
ULI. PROBLEM 7-18 Activity-Based Costing and Bidding on Jobs LO7-2, L07-3, LO7-4 Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estima tor and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos contaminated ceiling plaster in Activity-Based Costing:...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos Insulation and related products from bulldings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos Insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos contaminated celling plaster in industrial buildings. The on-site supervision believe that nonroutine work is far more expensive than routine...
1.34 points Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than...
Please note that each box with a dropdown must be filled. Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors...