Removing asbestos Estimating and Job Setup Working on Nonroutine Jobs Other Total
Wages and salaries (400000*60%)= $240000 (400000*10%)= $40000 (400000*20%)= $80000 (400000*10%)= $40000 $400000
Disposal fees (791000*60%)= 474600 - (791000*40%)= 316400 - 791000
Equipment depreciation (96000*40%)= 38400 (96000*5%)= 4800 (96000*25%)= 24000 (96000*30%)= 28800 96000
On-site supplies (60000*60%)= 36000 (60000*25%)= 15000 (60000*15%)= 9000 - 60000
Office expenses (300000*10%)= 30000 (300000*35%)=105000 (300000*25%)= 75000 (300000*30%)= 90000 300000
Licensing and insurance (500000*30%)= 150000 - (500000*50%)= 250000 (500000*20%)= 100000 500000
Total $969000 $164800 $754400 $258800 $2147000

2) Activity rate= Activity cost pools/Total activity

Removing asbestos= $969000/850= $1140 per thousand square feet

Estimating and Job Setup= $164800/400= $412 per job

Working on Nonroutine Jobs= $754400/100= $7544 per nonroutine job

3-a) Calculation of A routine 1000-square-foot asbestos removal job

Removing asbestos (1*$1140) $1140
Estimating and Job Setup (1*$412) 412
Working on Nonroutine Jobs 0
Total cost $1552
Average cost per thousand square feet ($1552/1 thousand square feet) $1552

b) Calculation of A routine 2000-square-foot asbestos removal job

Removing asbestos (2*$1140) $2280
Estimating and Job Setup (1*$412) 412
Working on Nonroutine Jobs 0
Total cost $2692
Average cost per thousand square feet ($2692/2 thousand square feet) $1346

c) Calculation of A nonroutine 2000-square-foot asbestos removal job

Working on Nonroutine Jobs (1*$7544) $7544
Removing asbestos (2*$1140) 2280
Estimating and Job Setup (1*$412) 412
Total cost $10236
Average cost per thousand square feet ($10236/2 thousand square feet) $5118
Add a comment
Know the answer?
Add Answer to:
Problem 7-18 Activity-Based Costing and Bidding on Jobs (L07-2, LO7-3, LO7.4) Mercer Asbestos Removal Company removes...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 7-18 Activity-Based Costing and Bidding on Jobs [LO7-2, L07-3, L07-4] Mercer Asbestos Removal Company removes...

    Problem 7-18 Activity-Based Costing and Bidding on Jobs [LO7-2, L07-3, L07-4] Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos contaminated ceiling plaster in industrial buildings. The on-site...

  • Problem 7-18 Activity-Based Costing and Bidding on Jobs (L07-2, L07-3, L07-4] Mercer Asbestos Removal Company removes p...

    Problem 7-18 Activity-Based Costing and Bidding on Jobs (L07-2, L07-3, L07-4] Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors...

  • ULI. PROBLEM 7-18 Activity-Based Costing and Bidding on Jobs LO7-2, L07-3, LO7-4 Mercer Asbestos Removal Company...

    ULI. PROBLEM 7-18 Activity-Based Costing and Bidding on Jobs LO7-2, L07-3, LO7-4 Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estima tor and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos contaminated ceiling plaster in Activity-Based Costing:...

  • Activity-Based Costing and Bidding on Jobs Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and...

    Activity-Based Costing and Bidding on Jobs Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estima- tor and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work...

  • Mercer Asbestos Removal Company removes potentially toxic asbestos Insulation and related products from bulldings. There has...

    Mercer Asbestos Removal Company removes potentially toxic asbestos Insulation and related products from bulldings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos Insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos contaminated celling plaster in industrial buildings. The on-site supervision believe that nonroutine work is far more expensive than routine...

  • Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has...

    Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...

  • Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has...

    Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...

  • Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has...

    Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...

  • Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There...

    Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...

  • 1.34 points Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings....

    1.34 points Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company's estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT