Question

Rretrieved from Project Management: A Systems Approach to Planning, Scheduling, and Controlling): Your manufacturing team informs...

Rretrieved from Project Management: A Systems Approach to Planning, Scheduling, and Controlling):

Your manufacturing team informs you that they have found a way to increase the size of the manufacturing run from 10,000 to 18,000 units in increments of 2,000 units. However, the setup cost will be $150,000 and the defects will cost the same $120 for removal and repair.

  1. Calculate the economic feasibility of make or buy.
  2. Should the probability of defects change if we produce 18,000 units as opposed to 10,000 units?
  3. Would your answer to question 1 change if the company management believes that follow-on contracts will be forthcoming? What would happen if the probability of defects changes to 15 percent, 25 percent, 40 percent, 15 percent, and 5 percent due to learning-curve efficiencies?

Your answers must be justified with an explanation

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Rretrieved from Project Management: A Systems Approach to Planning, Scheduling, and Controlling): Your manufacturing team informs...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Your manufacturing team informs you that they have found a way to increase the size of...

    Your manufacturing team informs you that they have found a way to increase the size of the manufacturing run from 10,000 to 18,000 units in increments of 2,000 units. However, the setup cost will be $150,000 and the defects will cost the same $120 for removal and repair. 1. Calculate the economic feasibility of make or buy. 2. Should the probability of defects change if we produce 18,000 units as opposed to 10,000 units? 3. Would your answer to question...

  • Respond Part B in details and show your step by step answer! TELOXY ENGINEERING (A) Teloxy...

    Respond Part B in details and show your step by step answer! TELOXY ENGINEERING (A) Teloxy Engineering has received a one-time contract to design and build 10,000 units of a new product. During the proposal process, management felt that the new product could be designed and manufactured at a low cost. One of the ingredients necessary to build the product was a small component that could be purchased for $60 in the marketplace, including quantity dis- counts. Accordingly, management budgeted...

  • What should Ajanta do about its recent order from SF? AJANTA PACKAGING: KEY ACCOUNT MANAGEMENT Sandeep Puri and Rakesh Singh wrote this case solely to provide material for class discussion...

    What should Ajanta do about its recent order from SF? AJANTA PACKAGING: KEY ACCOUNT MANAGEMENT Sandeep Puri and Rakesh Singh wrote this case solely to provide material for class discussion. The authors do not intend to iustrate either effective or ineffective handling of a managerial situation. The authors may have disguised certain names and other identifying information to protect confidentiality This publication may not be transmitted, photocopied, digitized, or otherwise reproduced in any form or by any means without the...

  • 4. Perform a SWOT analysis for Fitbit. Based on your assessment of these, what are some strategic options for Fitbit go...

    4. Perform a SWOT analysis for Fitbit. Based on your assessment of these, what are some strategic options for Fitbit going forward? 5. Analyze the company’s financial performance. Do trends suggest that Fitbit’s strategy is working? 6.What recommendations would you make to Fitbit management to address the most important strategic issues facing the company? Fitbit, Inc., in 2017: Can Revive Its Strategy and It Reverse Mounting Losses? connect ROCHELLE R. BRUNSON Baylor University MARLENE M. REED Baylor University in the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT