Question

TELOXY ENGINEERING (A) Teloxy Engineering has received a one-time contract to design and build 10,000 units of a new product. During the proposal process, management felt that the new product could be designed and manufactured at a low cost. One of the ingredients necessary to build the product was a small component that could be purchased for $60 in the marketplace, including quantity dis- counts. Accordingly, management budgeted $650,000 for the purchasing and handling of 10,000 components plus scrap. During the design stage, your engineering team informs you that the final design will require a somewhat higher-grade component that sells for $72 with quantity discounts. The new price is substantially higher than you had budgeted for. This will create a cost overrun You meet with your manufacturing team to see if they can manufacture the component at a cheaper price than buying it from the outside. Your manufacturing team informs you that they can produce a maximum of 10.000 units, just enough to fulfill your contract. The setup cost will be $100,000 and the raw material cost is $40 per component. Since Teloxy has never man ufactured this product before, manufacturing expects the following defects Percent defective Probability of 0 10 20 30 40 10 20 30 2515 All defective parts must be removed and repaired at a cost of $120 per part 1. Using expected value, is it economically better to make or buy the component? 2. Strategically thinking. why might management opt for other than the most economical choice? TELOXY ENGINEERING (B) Your manufacturing team informs you that they have found a way to increase the size of the manufacturing run from 10,000 to 18,000 units in increments of 2000 units. However, the setup cost will be $150,000 rather than $100,000 for all production runs greater than 10,000 units and defects will cost the same $120 for removal and repair 1. Calculate the economic feasibility of make or buy 2. Should the probability of defects change if we produce 18,000 units as opposed to 10,000 units? 3. Would your answer to question 1 change if Teloxy management believes that follow on contracts will be forthcoming? What would happen if the probability of defects changes to 15 percent, 25 percent, 40 percent, 15 percent, and 5 percent due to learning-curve efficiencies?

Respond Part B in details and show your step by step answer!

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

1) cost of production = $(100000+40*10000)

cost/parts = total cost/10000 = $50

Now, considering defects parts cost

since each defective parts needs to be replaced with cost of $120

so, total cost = 228000

adding this to cost of production, we get

Production cost/parts= 728000/10000= $72.8

Market value /parts = $72

Thus its economically better to buy the component

B)

1)economic feasibility depends upon the return on investment(roi) which is given by

ROI = Present Value Of Benefits / Present Value Of Costs

if the roi is higher,more the process is economical feasible and vice versa

i think in this case it is not economically feasible because the value of cost is higher than the benefits range

2)yes the probability of defects will change as it depends upon the number of products.so as it increases the probabilty increases.

3)yes the economic feasibility could change ina positive way if the contract goes bigger as their is more chance of getting higher rate of return on each component.so it will change.

Add a comment
Know the answer?
Add Answer to:
Respond Part B in details and show your step by step answer! TELOXY ENGINEERING (A) Teloxy...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Rretrieved from Project Management: A Systems Approach to Planning, Scheduling, and Controlling): Your manufacturing team informs...

    Rretrieved from Project Management: A Systems Approach to Planning, Scheduling, and Controlling): Your manufacturing team informs you that they have found a way to increase the size of the manufacturing run from 10,000 to 18,000 units in increments of 2,000 units. However, the setup cost will be $150,000 and the defects will cost the same $120 for removal and repair. Calculate the economic feasibility of make or buy. Should the probability of defects change if we produce 18,000 units as...

  • Your manufacturing team informs you that they have found a way to increase the size of...

    Your manufacturing team informs you that they have found a way to increase the size of the manufacturing run from 10,000 to 18,000 units in increments of 2,000 units. However, the setup cost will be $150,000 and the defects will cost the same $120 for removal and repair. 1. Calculate the economic feasibility of make or buy. 2. Should the probability of defects change if we produce 18,000 units as opposed to 10,000 units? 3. Would your answer to question...

  • Please show your work Use the following information to answer Questions #5 and #6 12 30...

    Please show your work Use the following information to answer Questions #5 and #6 12 30 Product A Units produced and sold Product B 30,000 Machine hours required per unit 12.000 23 Receiving orders per product line 50 150 Production orders per product line 12 18 Production runs 8 Inspections 20 Total budgeted machine hours are 100,000. The budgeted overhead costs are as shown below. 96.000 Machine hat Receiving costs $450,000 used Engineering costs 300,000 Machine setup costs 25,000 Inspection...

  • show your work Application Problem 4-2B al, b (Part Level Submission) Derby Transportation Inc. designs and...

    show your work Application Problem 4-2B al, b (Part Level Submission) Derby Transportation Inc. designs and buids trains for rail networks across Canada. The company, which is publicly traded, has an October 31 year end. On March 15, 2020, Derby Transportation signed a contract with OM Corridor Corp. to design and build 10 high-speed trains, with each train consisting of seven passenger cars. The high-speed train will operate between Ottawa and Montreal. The following events took place in 2020 in...

  • Knickknack, Inc. manufactures two products: Odds and Ends. The firm uses a single, plantwide overhead rate...

    Knickknack, Inc. manufactures two products: Odds and Ends. The firm uses a single, plantwide overhead rate based on direct-labor hours. Production and product-costing data are as follows: Production quantity Direct material Direct labor (not including setup time) Manufacturing overhead Total cost per unit Odds 1,000 units $ 40 30 (2 hr. at $15) 96 (2 hr. at $48) $ 166 Ends 5,000 units $ 60 45 (3 hr. at $15) 144 (3 hr. at $48) $ 249 Manufacturing overhead budget:...

  • Required information [The following information applies to the questions displayed below.] Knickknack, Inc. manufactures two products:...

    Required information [The following information applies to the questions displayed below.] Knickknack, Inc. manufactures two products: Odds and Ends. The firm uses a single, plantwide overhead rate based on direct-labor hours. Production and product-costing data are as follows: Odds $ Production quantity Direct material Direct labor (not including setup time) Manufacturing overhead 40 20 (2 hr. at $15) 96 (2 hr. at $48) 166 Ends 5,000 units $ 60 15 (3 hr. at $15) 144 (3 hr. at $48) $...

  • [The following information applies to the questions displayed below.] Knickknack, Inc. manufactures two products: Odds and...

    [The following information applies to the questions displayed below.] Knickknack, Inc. manufactures two products: Odds and Ends. The firm uses a single, plantwide overhead rate based on direct-labor hours. Production and product-costing data are as follows: Odds Ends Production quantity 1,000 units 5,000 units Direct material $ 40 $ 60 Direct labor (not including setup time) 30 (2 hr. at $15) 45 (3 hr. at $15) Manufacturing overhead 96 (2 hr. at $48) 144 (3 hr. at $48) Total cost...

  • 25-15 ACTIVITY-BASED COSTING AND ACTIVITY-BASED MANAGEMENT, AUTOMOTIVE SUPPLIER O'Sullivan Company is an automotive component supplier. O'Sullivan...

    25-15 ACTIVITY-BASED COSTING AND ACTIVITY-BASED MANAGEMENT, AUTOMOTIVE SUPPLIER O'Sullivan Company is an automotive component supplier. O'Sullivan has been approached by Honda Canada's Alliston, Ontario, plant to consider expanding its production of part 24Ž2 to a total annual quantity of 2,000 units. This part is a low-volume, complex product with a high gross margin that is based on a proposed (quoted) unit sales price of $7.50. O'Sullivan uses a traditional costing system that allocates indirect manufacturing costs based on direct labour...

  • LIVE UCIUI ing di 10 OD dation on an expansion strategy? CEMENT 05-15 ACTIVITY-BASED COSTING AND...

    LIVE UCIUI ing di 10 OD dation on an expansion strategy? CEMENT 05-15 ACTIVITY-BASED COSTING AND ACTIVITY-BASED MANAGEMENT, AUTOMOTIVE SUPPLIER O'Sullivan Company is an automotive component supplie motive component supplier. O'Sullivan has been approached by Honda Canada's Alliston, Ontario, plant to consider expanding its production of part 2422 to a total annual quantity of 2.000 units. This part is a low-volume, complex product with a high gross margin that is based on a proposed (quoted) unit sales price of $7.50....

  • Required information [The following information applies to the questions displayed below.] Knickknack, Inc. manufactures two products:...

    Required information [The following information applies to the questions displayed below.] Knickknack, Inc. manufactures two products: Odds and Ends. The firm uses a single, plantwide overhead rate based on direct-labor hours. Production and product-costing data are as follows: Odds $ Production quantity Direct material Direct labor (not including setup time) Manufacturing overhead 40 20 (2 hr. at $15) 96 (2 hr. at $48) 166 Ends 5,000 units $ 60 15 (3 hr. at $15) 144 (3 hr. at $48) $...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT