Answer #1

Note this question is incorrect as in wester region plant Electronic Assembly over budget is 2790 (191250-194040) instead of 2520. still I solve the question for your convenient.

a chip fabrication budget 240300

b) chip fabrication actual 243840

c) Chip fabrication over budget 3540 (4620-1080)

d) western region budget 739800

e) western region actual 745320

f) western region over budget 6060

g) western region budget 739800

h) western region actual 745320

I) western region over budget 5250 (6060-810)

j) saskatoon budget 2345400

k) saskatoon actual 2345070

l) saskatoon over budget 5250

Add a comment
Know the answer?
Add Answer to:
EX 8-1 Budget performance reports for cost centers Partially completed budget performance reports for Saskatoon Company,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Budget Performance Reports for Cost Centers Partially completed budget performance reports for Delmar Company, a manufacturer...

    Budget Performance Reports for Cost Centers Partially completed budget performance reports for Delmar Company, a manufacturer of light duty motors, follow: Delmar Company Budget Performance Report—Vice President, Production For the Month Ended June 30 Plant Actual Budget Over Budget (Under) Budget Eastern Region $4,200,000 $4,250,000 $(50,000) Central Region 6,175,000 6,200,000 (25,000) Western Region (g) (h) $(i) $(j) $(k) $(l) $(75,000) Delmar Company Budget Performance Report—Manager, Western Region Plant For the Month Ended June 30 Department Actual Budget Over Budget (Under)...

  • ses EX 24-1 Budget performance reports for cost centers OBJ. 2 Partially completed budget performance reports...

    ses EX 24-1 Budget performance reports for cost centers OBJ. 2 Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Plant Eastern Region Central Region Western Region Garland Company Budget Performance Report-Vice President, Production For the Month Ended November 30 Actual Budget Over Budget $2,409,400 $2,420,000 2,998,400 3,000,000 (h) (k) Under Budget $(10,600) (1,600) $(12,200) Under Budget Garland Company Budget Performance Report-Manager, Western Region Plant For the Month Ended November 30 Department Actual Budget...

  • Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer...

    Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland Company Budget Performance Report—Vice President, Production For the Month Ended November 30 Plant Actual Budget Over Budget Under Budget Eastern Region $433,800 $433,800 $0 Central Region 312,300 309,200 $3,100 Western Region (g) (h) (i) $(j) $(k) $(l) $2,380 Garland Company Budget Performance Report—Manager, Western Region Plant For the Month Ended November 30 Department Actual Budget Over Budget Under...

  • Budget Performance Reports for Cost Centers Partially completed budget performance reports for Delmar Company, a manufacturer...

    Budget Performance Reports for Cost Centers Partially completed budget performance reports for Delmar Company, a manufacturer of light duty motors, follow: Delmar Company Budget Performance Report—Vice President, Production For the Month Ended June 30 Plant Actual Budget Over Budget (Under) Budget Eastern Region $422,000 $422,000 $0 Central Region 300,800 303,800 (3,000) Western Region (g) (h) (i) $(j) $(k) $(l) $(3,000) Delmar Company Budget Performance Report—Manager, Western Region Plant For the Month Ended June 30 Department Actual Budget Over Budget (Under)...

  • Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer...

    Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland Company Budget Performance Report—Vice President, Production For the Month Ended November 30 Plant Budget Actual Over Budget Under Budget Eastern Region $360,600 $360,600 $0 Central Region 259,600 257,000 (2,600) Western Region (g) (h) (i) $(j) $(k) $(l) $(2,600) Garland Company Budget Performance Report—Manager, Western Region Plant For the Month Ended November 30 Department Budget Actual Over Budget Under...

  • Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer...

    Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland Company Budget Performance Report-Vice President, Production For the Month Ended November 30 Under Budget Plant Budget Actual over Budget Eastern Region $421,800 $421,800 $0 Central Region 303,700 (3,000) 300,700 Western Region (g) (h) (i) $G) $(k) $0) $(3,000) Garland Company Budget Performance Report-Manager, Western Region Plant For the Month Ended November 30 Budget Actual Over Budget Under Budget...

  • C) $22.950 EX 9-1 Budget performance reports for cost centers Obj. 2 Partially completed budget performance...

    C) $22.950 EX 9-1 Budget performance reports for cost centers Obj. 2 Partially completed budget performance reports for Garland Company, a man duty motors, follow: e reports for Garland Company, a manufacturer of light SHOW ME HOW Plant Eastern Region Central Region Western Region Garland Company Budget Performance Report-Vice President, Production For the Month Ended November 30 Budget Actual Over Budget $2,300,000 $2,287,900 3,000,000 2,988.400 (H) Under Budget $ (12,100) (11,600) (G) 0) $ (23,700 Under Budget Garland Company Budget...

  • Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer...

    Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland Company Budget Performance Report—Vice President, Production For the Month Ended November 30 Plant Budget Actual Over Budget Under Budget Eastern Region $521,400 $521,400 $0 Central Region 375,400 371,600 (3,800) Western Region (g) (h) (i) $(j) $(k) $(l) $(3,800) Garland Company Budget Performance Report—Manager, Western Region Plant For the Month Ended November 30 Department Budget Actual Over Budget Under...

  • Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer...

    Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland Company Budget Performance Report-Vice President, Production For the Month Ended November 30 Plant Budget Actual Over Budget Under Budget Eastern Region $533,100 $533,100 $0 Central Region 383,800 380,000 (3,800) Western Region (g) (h) (i) $0) $(k) $(1) $(3,800) Garland Company Budget Performance Report-Manager, Western Region Plant For the Month Ended November 30 Department Budget Actual over Budget Under...

  • Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufa...

    Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland Company Budget Performance Report—Vice President, Production For the Month Ended November 30 Plant Budget Actual Over Budget Under Budget Eastern Region $398,700 $398,700 $0 Central Region 287,100 284,200 (2,900) Western Region (g) (h) (i) $(j) $(k) $(l) $(2,900) Garland Company Budget Performance Report—Manager, Western Region Plant For the Month Ended November 30 Department Budget Actual Over Budget Under...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT