Partially completed budget performance reports for Delmar Company, a manufacturer of light duty motors, follow:

Delmar Company
Budget Performance Report—Vice President, Production
For the Month Ended June 30
Plant Actual Budget Over Budget (Under) Budget
Eastern Region $4,200,000 $4,250,000 $(50,000)
Central Region 6,175,000 6,200,000 (25,000)
Western Region (g) (h) $(i)
$(j) $(k) $(l) $(75,000)
Delmar Company
Budget Performance Report—Manager, Western Region Plant
For the Month Ended June 30
Department Actual Budget Over Budget (Under) Budget
Chip Fabrication $(a) $(b) $(c)
Electronic Assembly 2,575,000 2,500,000 75,000
Final Assembly 1,640,000 1,700,000 $(60,000)
$(d) $(e) $(f) $(60,000)
Delmar Company
Budget Performance Report—Supervisor, Chip Fabrication
For the Month Ended June 30
Cost Actual Budget Over Budget (Under) Budget
Factory wages $1,450,000 $1,200,000 $250,000
Materials 1,575,000 1,600,000 $(25,000)
Power and light 945,000 900,000 45,000
Maintenance 330,000 300,000 30,000
$4,300,000 $4,000,000 $325,000 $(25,000)

a. Complete the budget performance reports by determining the correct amounts for the lettered spaces (a-l) as marked above.

a. $ g. $
b. $ h. $
c. $ i. $
d. $ j. $
e. $ k. $
f. $ l. $

b. Complete the following memo to Randi Wilkes, vice president of production for Delmar Company, explaining the performance of the production division for June.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

ANSWER

a)

S.No. Answer Calculation
a 4,300,000
b 4,000,000
c 300,000 325,000-25,000
d 8,515,000 4,300,000+2,575,000+1,640,000
e 8,200,000 4,000,000+2,500,000+1,700,000
f 375,000 300,000+75,000
g 8,515,000 Equal to d
h 8,200,000 Equal to e
i 315,000 375,000-60,000
j 18,890,000 4,200,000+6,175,000+8,515,000
k 18,650,000 4,250,000+6,200,000+8,200,000
l 315,000 Equal to i

_____________________________________________

If you have any query or any Explanation please ask me in the comment box, i am here to helps you.please give me positive rating.

*****************THANK YOU**************

Add a comment
Know the answer?
Add Answer to:
Budget Performance Reports for Cost Centers Partially completed budget performance reports for Delmar Company, a manufacturer...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Budget Performance Reports for Cost Centers Partially completed budget performance reports for Delmar Company, a manufacturer...

    Budget Performance Reports for Cost Centers Partially completed budget performance reports for Delmar Company, a manufacturer of light duty motors, follow: Delmar Company Budget Performance Report—Vice President, Production For the Month Ended June 30 Plant Actual Budget Over Budget (Under) Budget Eastern Region $422,000 $422,000 $0 Central Region 300,800 303,800 (3,000) Western Region (g) (h) (i) $(j) $(k) $(l) $(3,000) Delmar Company Budget Performance Report—Manager, Western Region Plant For the Month Ended June 30 Department Actual Budget Over Budget (Under)...

  • Partially completed budget performance reports for Delmar Company, a manufacturer of light duty motors, follow: Delmar...

    Partially completed budget performance reports for Delmar Company, a manufacturer of light duty motors, follow: Delmar Company Budget Performance Report—Vice President, Production For the Month Ended June 30 Plant Actual Budget Over Budget (Under) Budget Eastern Region $420,200 $420,200 $0 Central Region 299,500 302,500 (3,000) Western Region (g) (h) (i) $(j) $(k) $(l) $(3,000) Delmar Company Budget Performance Report—Manager, Western Region Plant For the Month Ended June 30 Department Actual Budget Over Budget (Under) Budget Chip Fabrication $(a) $(b) $(c)...

  • Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer...

    Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland Company Budget Performance Report-Vice President, Production For the Month Ended November 30 Under Budget Plant Budget Actual over Budget Eastern Region $421,800 $421,800 $0 Central Region 303,700 (3,000) 300,700 Western Region (g) (h) (i) $G) $(k) $0) $(3,000) Garland Company Budget Performance Report-Manager, Western Region Plant For the Month Ended November 30 Budget Actual Over Budget Under Budget...

  • Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer...

    Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland Company Budget Performance Report—Vice President, Production For the Month Ended November 30 Plant Budget Actual Over Budget Under Budget Eastern Region $360,600 $360,600 $0 Central Region 259,600 257,000 (2,600) Western Region (g) (h) (i) $(j) $(k) $(l) $(2,600) Garland Company Budget Performance Report—Manager, Western Region Plant For the Month Ended November 30 Department Budget Actual Over Budget Under...

  • Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer...

    Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland Company Budget Performance Report—Vice President, Production For the Month Ended November 30 Plant Actual Budget Over Budget Under Budget Eastern Region $433,800 $433,800 $0 Central Region 312,300 309,200 $3,100 Western Region (g) (h) (i) $(j) $(k) $(l) $2,380 Garland Company Budget Performance Report—Manager, Western Region Plant For the Month Ended November 30 Department Actual Budget Over Budget Under...

  • EX 8-1 Budget performance reports for cost centers Partially completed budget performance reports for Saskatoon Company,...

    EX 8-1 Budget performance reports for cost centers Partially completed budget performance reports for Saskatoon Company, a manufacturer OBJ. 2 of light duty motors, follow: Plant Eastern Region Central Region Western Region Saskatoon Company Budget Performance Report-Vice President Production For the Month Ended June 30, 2016 Budget Actual Over Budget $936,000 $933,750 669,600 666,000 Under Budget $2,250 3,600 (h) (k) $5,850 (Continued 348 Chapter 8 Performance Evaluation or Under Budget Saskatoon Company Budget Performance Report-Manager, Western Region Plant For the...

  • Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer...

    Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland Company Budget Performance Report—Vice President, Production For the Month Ended November 30 Plant Budget Actual Over Budget Under Budget Eastern Region $521,400 $521,400 $0 Central Region 375,400 371,600 (3,800) Western Region (g) (h) (i) $(j) $(k) $(l) $(3,800) Garland Company Budget Performance Report—Manager, Western Region Plant For the Month Ended November 30 Department Budget Actual Over Budget Under...

  • Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer...

    Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland Company Budget Performance Report-Vice President, Production For the Month Ended November 30 Plant Budget Actual Over Budget Under Budget Eastern Region $533,100 $533,100 $0 Central Region 383,800 380,000 (3,800) Western Region (g) (h) (i) $0) $(k) $(1) $(3,800) Garland Company Budget Performance Report-Manager, Western Region Plant For the Month Ended November 30 Department Budget Actual over Budget Under...

  • Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufa...

    Budget Performance Reports for Cost Centers Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Garland Company Budget Performance Report—Vice President, Production For the Month Ended November 30 Plant Budget Actual Over Budget Under Budget Eastern Region $398,700 $398,700 $0 Central Region 287,100 284,200 (2,900) Western Region (g) (h) (i) $(j) $(k) $(l) $(2,900) Garland Company Budget Performance Report—Manager, Western Region Plant For the Month Ended November 30 Department Budget Actual Over Budget Under...

  • ses EX 24-1 Budget performance reports for cost centers OBJ. 2 Partially completed budget performance reports...

    ses EX 24-1 Budget performance reports for cost centers OBJ. 2 Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow: Plant Eastern Region Central Region Western Region Garland Company Budget Performance Report-Vice President, Production For the Month Ended November 30 Actual Budget Over Budget $2,409,400 $2,420,000 2,998,400 3,000,000 (h) (k) Under Budget $(10,600) (1,600) $(12,200) Under Budget Garland Company Budget Performance Report-Manager, Western Region Plant For the Month Ended November 30 Department Actual Budget...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT