Question1 1 pts A 8,000 gallon storage tank was purchased for $160,000 12 years ago. How...
A 8,000 gallon storage tank was purchased for $220,000 12 years ago. How much would a 12,000 gallon storage tank cost today if the power-sizing exponent were 0.71 and the cost index increased from 150 to 220 over the last 12 years. Express your answer in $ to the nearest $1,000
A 1000-gallon metal tank cost $200,000 when it was built 12 years ago. What would a 2500-gallon tank cost today if the power–sizing exponent is 0.57 and the construction cost index for such facilities has increased from 270 to 900 over the last 12 years? Solve this as follows. i) Consider power-sizing only. ii) Then consider cost index too.
Question 6 15 pts 2000-gallon metal tank to store hazardous materials was bought 5 years ago at cost of $50,000. If a 5,000-gallon tank cost (close to) $86,643 today, what will be the power-sizing exponent? [2 decimal only 1. 2. 3. 4. 5. 1.73, 0.58, 0.60 0.23 1.44 3 1 2
#6) A 2000-gallon metal tank to hold hazardous materials cost $200,000 when it was fabricated 15 years ago. What would a 5,000-gallon tank cost today if the power-sizing exponent is 0.575 and the construction cost index for such facilities has increased from 120 to 400 over the last 15 years? a $337,175 b. $666,667 c. $1,123,917 d. $200,000
Kathy needs to replace the 1000-ft2 heat exchanger she purchased 6 years ago with a 3000-ft2 heat exchanger . If she purchased the 1000-ft2 heat exchanger for $5,000 6 years ago, estimate the cost of the 3000-ft2 heat exchanger today if the power sizing exponent is 0.6 and the cost index for compressors 6 years ago was 150 and today it is 210.
A 1000 gallon tank for water storage costs $650 in 2017. Estimate what a 5000 gallon tank costs in 2007. CEPCI Values Annual Index: 2006 499.6 2007 525.4 Equipment/Facility 2008 575.4 Blower, centrifugal 2009 521.9 2010 550.8 Drer, drum, single atmospheric TABLE 2-1 Example Power-Sizing Exponent Values Power-Sizing Exponent Size Range 10,000 100,000 ft3/min 200-2100 hp 500-7000 f2 10-100 ft2 20,000-70,000 ft2/min 10-1500 f2 0.05-20 million ga/day 5-20 bp 100-1000 gal 100-40,000 gal Compressor Crystallizer, vacuum batch 0.32 0.37 2010...
Reference: Table 1 Tech Engineering in TN is making a product for the overseas market. The following cost data for the product has been compiled. Item Cost Selling price $167 | Materials and purchased parts | $25/unit Direct Labor | 2 hrs at $20 per hour Fixed Cost $1,400,000 2.1 The breakeven volume for this product is A) 14,433 B) 8,383 C) 20,000 D) None of these 2.2. To reduce the breakeven volume to 15,000 units, what should be the...
1. The unit cost of installing a solar power system per km² was $5,000 in 2010 when the construction cost index was 1,850. Construction of a 5 MW power system requires 50 km² of land. Estimate the cost of constructing a solar power system of 20 MW in 2020 given that the construction cost index is 2,450 and the size-factor is 0.75? 2. A company that manufactures general-purpose transducers invested $2 million four years ago in high-yield junk box bonds....