When calculating a project's payback period, cash flows are:
discounted at the internal rate of return.
discounted at the risk-free rate of return.
not discounted at all.
payback period is the time taken to recover initial investment. It does not take time value of money.
hence the correct answer is not discounted at all
When calculating a project's payback period, cash flows are: discounted at the internal rate of return....
When calculating a project's NPV, cash flows are discounted at: O A) the opportunity cost of capital. OB) the risk-free rate of return. OC) a discount rate of zero. D) the internal rate of return. 0 1 4 5 2 + 5,600 3 + + -18,000 5,600 5,600 5,600 5,600 A firm with a 14% WACC is evaluating one project for this year's capital budget. After-tax cash flows, including depreciation are attached. What is the regular payback for this project?...
project's appropriate discount rate is 12 percent, what is the proces discounted payback period (Discounted Payback periodies Restaurants is considering project with the following expected cash flows The projects discounted payback period is yours (Round to be decimal places) 1 Data Table PROJECT CASH FLOW - $20 million 80 milion 65 milion 80 millon 95 m. (Click on the concated on the h ome of the data above in order to conten t Print Done
( Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows. If the project's appropriate discount rate is 11 percent, what is the projects's discounted payback period? expected cash flows: Year Project Cash Flow 0 - $180 million 1 90 million 2 65 million 3 100 million 4 100 million The Project's discounted payback period is ____
( Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows. If the project's appropriate discount rate is 11 percent, what is the projects's discounted payback period? expected cash flows: Year Project Cash Flow 0 -$180 million 1 90 million 2 65 million 3 100 million 4 100 million The Project's discounted payback period is ____ ?
(Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) $(210) AWNO If the project's appropriate discount rate is 11 percent, what is the project's discounted payback period? The project's discounted payback period is years. (Round to two decimal places.)
(Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) 0 $(180) 1 100 2 65 3 100 4 110 If the project's appropriate discount rate is 13 percent, what is the project's discounted payback period? The project's discounted payback period is _____ years. (Round to two decimal places.)
(Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) $(210) 85 60 95 If the project's appropriate discount rate is 12 percent, what is the project's discounted payback period? The project's discounted payback period is years. (Round to two decimal places.)
Gio's Restaurants is considering a project with the following
expected cash flows:
(Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) $(240) 0 1 92 65 3 92 4 90 If the project's appropriate discount rate is 8 percent, what is the project's discounted payback period? The project's discounted payback period is years. (Round to two decimal places.) O N M
(Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) $(210) AWNO If the project's appropriate discount rate is 11 percent, what is the project's discounted payback period? The project's discounted payback period is years. (Round to two decimal places.) (Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows: Project A Project B Year Cash Flow...
Given the following cash flows for a capital project, calculate its payback period and discounted payback period. The required rate of return is 8 percent. Year 4 Cash Flows $-44300 $11950 2 $13350 3 $19000 $8000 $3000 The discounted payback period is 0.16 year longer than the payback period. 0.80 year longer than the payback period. 1.40 years longer than the payback period. 1.85 years longer than the payback period.