1.40 years longer than the payback period
Step-1:Payback period | |||||||
Year | Cash Flow | Cumulative Cash Flow | |||||
0 | $ -44,300 | $ -44,300 | |||||
1 | 11,950 | -32,350 | |||||
2 | 13,350 | -19,000 | |||||
3 | 19,000 | - | |||||
4 | 8,000 | 8,000 | |||||
5 | 3,000 | 11,000 | |||||
So,Payback period is 3 years | |||||||
Step-2: Discounted Payback period | |||||||
Year | Cash Flow | Discount factor | Discounted Cash flow | Cumulative Discounted Cash flow | |||
a | b | c=1.08^-a | d=b*c | e | |||
0 | $ -44,300 | 1.0000 | -44,300 | $ -44,300 | |||
1 | 11,950 | 0.9259 | 11,065 | -33,235 | |||
2 | 13,350 | 0.8573 | 11,445 | -21,790 | |||
3 | 19,000 | 0.7938 | 15,083 | -6,707 | |||
4 | 8,000 | 0.7350 | 5,880 | -827 | |||
5 | 3,000 | 0.6806 | 2,042 | 1,215 | |||
Discounted payback | = | 4+(827/2042) | |||||
= | 4.40 | Years | |||||
Payback period | 3 years | ||||||
Discounted payback period | 4.40 years | ||||||
So, discounted payback period is longer than 1.40 years. | |||||||
Given the following cash flows for a capital project, calculate its payback period and discounted payback...
(Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) $(210) AWNO If the project's appropriate discount rate is 11 percent, what is the project's discounted payback period? The project's discounted payback period is years. (Round to two decimal places.)
Given the following cash flows for a capital project, calculate the Payback period, NPV, PI, IRR, and MIRR. The required rate of return is 8 percent. Year CF 0 $(50,000.00) 1 $15,000.00 2 $15,000.00 3 $15,000.00 4 $15,000.00 5 $5,000.00
(Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) 0 $(180) 1 100 2 65 3 100 4 110 If the project's appropriate discount rate is 13 percent, what is the project's discounted payback period? The project's discounted payback period is _____ years. (Round to two decimal places.)
(Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) $(210) 85 60 95 If the project's appropriate discount rate is 12 percent, what is the project's discounted payback period? The project's discounted payback period is years. (Round to two decimal places.)
Gio's Restaurants is considering a project with the following expected cash flows: (Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) $(240) 0 1 92 65 3 92 4 90 If the project's appropriate discount rate is 8 percent, what is the project's discounted payback period? The project's discounted payback period is years. (Round to two decimal places.) O N M
(Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) $(210) AWNO If the project's appropriate discount rate is 11 percent, what is the project's discounted payback period? The project's discounted payback period is years. (Round to two decimal places.) (Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows: Project A Project B Year Cash Flow...
( Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows. If the project's appropriate discount rate is 11 percent, what is the projects's discounted payback period? expected cash flows: Year Project Cash Flow 0 - $180 million 1 90 million 2 65 million 3 100 million 4 100 million The Project's discounted payback period is ____
( Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows. If the project's appropriate discount rate is 11 percent, what is the projects's discounted payback period? expected cash flows: Year Project Cash Flow 0 -$180 million 1 90 million 2 65 million 3 100 million 4 100 million The Project's discounted payback period is ____ ?
(Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) $(240) 72 80 95 If the project's appropriate discount rate is 11 percent, what is the project's discounted payback period? The project's discounted payback period is years. (Round to two decimal places.) (Discounted payback period) The Callaway Cattle Company is considering the construction of a new feed handling system for its feed lot in Abilene, Kansas. The new system will...
P11-20 (similar to) (Discounted payback period) Glo's Restaurants consiruring a project with the following expected cash flows: Year Project Cash Flow (millions $(240) NO 95 110 If the project's appropriate discount rate is 13 percent, what is the project's discounted payback period? The project's discounted payback period is years. (Round to two decimal places.)