Question

Given the following cash flows for a capital project, calculate the Payback period, NPV, PI, IRR,...

Given the following cash flows for a capital project, calculate the Payback period, NPV, PI, IRR, and MIRR. The required rate of return is 8 percent.

                Year

                                 CF

0

$(50,000.00)

1

$15,000.00

2

$15,000.00

3

$15,000.00

4

$15,000.00

5

$5,000.00

1 0
Add a comment Improve this question Transcribed image text
Answer #1

Calculations Recquired Rate of Return = 8%. as Initial Investment = ($50.ooo) 1 [ Year o Cash place) 6 Annual Cashflows Pvaa) Payback = Year leefare full Recovery O Period + Unrecovered Cost at the Start of the Year Cashflow during the year 150.000cole Grafitability - Index Present Value of Initial Annual Cashflows Insestment $ 53,084.82 $ 50,000 PI = 1.06d) IRR Internal (By trial Rate of Return) S Error Methad) NPV @ 10% is $ 652.5g (Lower Rote NPV @ ill. is 04-496.06 (Higher R

Add a comment
Know the answer?
Add Answer to:
Given the following cash flows for a capital project, calculate the Payback period, NPV, PI, IRR,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. Given the following set of cash flows for a project, calculate the NPV, PI, IRR,...

    1. Given the following set of cash flows for a project, calculate the NPV, PI, IRR, MIRR, Payback, Discounted Payback and Accounting Rate of Return. Assume a cost of capital of 10%. Assuming that this is an independent project, should the project be accepted? Why or why not? (20 pts.) Year                Cash Flow                 Net Profit                   Depreciation 0                    -$125,000 1                    $22,000                     $15,000                      $10,000 2                    $58,000                     $43,000                      $25,000 3                    -$30,000                   $24,000                      $21,000 4                    $35,000                     $28,000                      $18,000 5                    $28,000                     $20,000                      $15,000 6                    $60,000                     ...

  • (Payback period, NPV, PI, and IRR calculations )You are considering a project with an initial cash...

    (Payback period, NPV, PI, and IRR calculations )You are considering a project with an initial cash outlay of 90,000 and expected free cash flows of 30,000 at the end of each year for 6 years. The required rate of return for this project is 8 percent. a. What is the project's payback period? b. What is the project's NPV ? c. What is the project's PI ? d. What is the project's IRR ?

  • ​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash...

    ​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of ​$85.000 and expected free cash flows of ​$20,000 at the end of each year for 7 years. The required rate of return for this project is 6 percent. a. What is the​ project's payback​ period? b. What is the​ project's NPV​? c. What is the​ project's PI​? d. What is the​ project's IRR​?

  • Given the following cash flows for a capital project, calculate the NPV and IRR. The required...

    Given the following cash flows for a capital project, calculate the NPV and IRR. The required rate of return is 8 percent Cash Flows Year 0$-50825 Year 1 $18550 Year 2 $11350 Year 3 $20900 Year 4 $9200 Year 5 $4250

  • ​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash...

    ​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of ​$85 comma 000 and expected free cash flows of ​$30 comma 000 at the end of each year for 6 years. The required rate of return for this project is 6 percent. a. What is the​ project's payback​ period? b. What is the​ project's NPV​? c. What is the​ project's PI​? d. What is the​ project's IRR​?

  • Given the following cash flows for a capital project, calculate its payback period and discounted payback...

    Given the following cash flows for a capital project, calculate its payback period and discounted payback period. The required rate of return is 8 percent. Year 4 Cash Flows $-44300 $11950 2 $13350 3 $19000 $8000 $3000 The discounted payback period is 0.16 year longer than the payback period. 0.80 year longer than the payback period. 1.40 years longer than the payback period. 1.85 years longer than the payback period.

  • Given a project with the following cash flows and a cost of capital of 9%. Calculate...

    Given a project with the following cash flows and a cost of capital of 9%. Calculate the NPV, IRR, MIRR, and PI. For each of the four calculations, give a brief interpretation of what it measures and how it should be used to evaluate a project. Should the project be accepted? Why or why not? Time Period        Cash Flow         0                         -$200,000         1                         $50,000         2                         $70,000         3                         -$80,000         4                         $75,000         5                         $100,000         6                         $120,000...

  • Calculate the Payback Period, IRR, NPV, and PI if cash flows are as follows: -$2M; $600K;...

    Calculate the Payback Period, IRR, NPV, and PI if cash flows are as follows: -$2M; $600K; $850K; $900K: and $700K. (WACC is 10%)

  • Suppose You are given the following cash flows: find the payback period, the IRR, and the...

    Suppose You are given the following cash flows: find the payback period, the IRR, and the required rate of return in 8% 1. Suppose you are given the following cash flows: Initial Investment -120 Year 1 Cash Flow +70 Year 2 Cash Flow +60 Year 3 Cash Flow +40 a. (7 points) What is the payback period on the investment? +20 70 60 40 1 3 tr 3.02 Ø & 3 years b. (7 points) What is the IRR for...

  • This assignment supports the following objectives: Calculate IRR, NPV and Payback Period Analyze the cash flows...

    This assignment supports the following objectives: Calculate IRR, NPV and Payback Period Analyze the cash flows generated by mutually exclusive projects Formulate a recommendation using IRR, NPV and Payback Period as the criteria Background Suppose that your firm is considering the following two mutually exclusive projects. Both projects have the same initial cost of $312,500 and the resulting annual cash flows for the first five years are as shown in the table below: Year Alpha Beta 0 $ (312,500) $...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT